Alabama Port Authority, McDuffie Coal Terminal, Mobile, Alabama. Engineer: Alliance Engineering. Project 11712, Task 2.
One PDF of 48 pages. The single-line diagram and layouts are images with no text, so they were read by eye. Each point below links to its source page: click a page chip to see the wording on that page.
Drawing 250525-EL-OL-0001A, Rev A, page 38. It has no text layer, so every label was read from the image. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.

| # | Position | Equipment on the drawing | Feeds | Checks | Where it is written |
|---|---|---|---|---|---|
| M1 | Main N.E | 1200 A drawout vacuum breaker, 2 CT cores (1200/5), 2 fused PT sets, SEL-351S, SEL-735 | Utility, cable P-000A | 4 same4 to check | Drawing · M1 |
| F1 | P-0001 · N.E SWGR | Fixed load-break switch, 200E SLOW fuse, CT 600/5, fused PT set, SEL-735 | Feeds the N.E pad-mount switchgear: 600 A, 23 kV switch with 150E SLOW (EMS1) and 200E SLOW (ETS1) fuses | 2 same5 to check | Drawing · F1 |
| F2 | P-0002 · ASSEMBLY BUILDING | Fixed load-break switch, 20E SLOW fuse, CT 600/5, fused PT set, SEL-735 | Feeds a 500 kVA transformer, 23 kV to 480 V, Z = 5.0% | 2 same4 to check | Drawing · F2 |
| F3 | P-0003 · 32N | Fixed load-break switch, 250E SLOW fuse, CT 600/5, fused PT set, SEL-735 | Feeds a 2500 kVA transformer (23 kV / 480 V, Z = 6.37%) and a 5000 kVA transformer (23 kV / 4160 V, Z = 6.8%), each behind a 200E SLOW fuse | 2 same4 to check | Drawing · F3 |
| F4 | P-0004 · 43E | Fixed load-break switch, 250E SLOW fuse, CT 600/5, fused PT set, SEL-735 | Feeds the 43E pad-mount switch: CLS 100E to a 3750 kVA transformer (43E 480 V switchboard) and CLS 125E to a 3500 kVA transformer (43E 13.2 kV switchgear) | 2 same4 to check | Drawing · F4 |
| F5 | P-0005 · WATER PUMPS | Fixed load-break switch, 30E SLOW fuse, CT 600/5, fused PT set, SEL-735 | Feeds a 1000 kVA transformer, 23 kV to 480 V, Z = 5.7% | 2 same4 to check | Drawing · F5 |
| T | Bus tie | Drawout vacuum breaker 1200 A, CT 1200/5, one fused PT set, SEL-351S, SEL-735 | Links the N.E and N.W buses | 1 same3 to check | Drawing · T |
| M2 | Main N.W | 1200 A drawout vacuum breaker, 2 CT cores (1200/5), 2 fused PT sets, SEL-351S, SEL-735 | Future secondary feeder | 1 same3 to check | Drawing · M2 |
| SP | Prepared space | Provisions only; type to be confirmed | - | 2 to check | Drawing · SP |
| F6 | P-0006 · N.W SWGR | Fixed load-break switch, 200E SLOW fuse, CT 600/5, fused PT set, SEL-735 | Feeds the N.W pad-mount switchgear: 600 A switch, 23 kV, 150E SLOW fuse (NWMT, to the 23 kV / 4.16 kV transformer for the N.W building) and 200E SLOW fuse (SRDT, railroad building) | 2 same5 to check | Drawing · F6 |
| F7 | P-0007 · 14W | Fixed load-break switch, 100E SLOW fuse, 600/5 CT, fused PT set, SEL-735 | Feeds a 3750 kVA transformer, 23 kV to 480 V, Z = 5.8% | 2 same5 to check | Drawing · F7 |
| F8 | P-0008 · MAINT. SHOPS | Fixed load-break switch, 20E SLOW fuse, CT 600/5, fused PT set, SEL-735 | Feeds a 750 kVA transformer, 23 kV to 480 V, Z = 5.0% | 2 same5 to check | Drawing · F8 |
Biggest cost impact first. Each item shows both sides and their page numbers.
Ready to send. Biggest cost impact first.
| Requirement | Status | Note | Page |
|---|---|---|---|
| Submit a sealed bid by courier by 1:30 PM, Thu 3 Dec 2026. No fax or email. | Required | Page 3 | |
| Bid bond or certified check: 5% of the bid, up to $10,000. | Required | Page 6 | |
| Include the Beason-Hammon certificate and E-Verify evidence with the bid. | Required | Page 6 | |
| Bid is valid for 60 days. Award is based on best value: cost, solution, and delivery. Alternates that exceed the specification are allowed. | Required | Page 3 | |
| Provide a performance bond for 100% of the contract. Submit the contract and bonds within 10 days of notice of award. | Required | Page 4 | |
| Liquidated damages are $1,200 per day for late delivery against the bidder's own schedule. Remove statements to the contrary. | To clarify | Commercial risk to include in the price. | Page 5 |
| Split lead time into drawings, manufacturing (with factory test), and shipping. | Required | Page 4 | |
| Bidder must state: factory test (yes or no); one or two line-ups; full bill of materials; whether tie PTs and CTs for transfer are included; spares list; 125 or 48 VDC; and whether the 10-hour battery requirement is met. | Required | Page 4 | |
| Two-year guarantee from final acceptance. | To clarify | Final acceptance depends on installation by others. | Page 5 |
| Site access requires a TWIC card, a port badge, and a vehicle decal. This applies to the 40 hours on site. | Required | Page 5 | |
| List exceptions to SPEC-002 on a separate sheet titled "Exceptions". Exceptions not listed count as accepted. | To clarify | This applies even though SPEC-002 is "for reference only". | Page 43 |
| ANSI/IEEE C37.20.2 and/or C37.20.3, NEMA, NEC, and FM apply. The data sheet adds UL "as applicable". | To clarify | UL question is open. | Page 16 |
| Outdoor NEMA 3R; coastal, coal dust, humidity up to 100%, up to 3,300 ft. Galvanized or stainless steel is acceptable. | Required | Page 19 | |
| 1200 A bus, epoxy-insulated for 27 kV class, braced to the data sheet short-circuit rating. | Required | Page 21 | |
| Copper ground bus running the full length of both sections, sized for 2 seconds. | Required | Page 21 | |
| At least 36 in from cable entry to the termination pads; NEMA 2-hole pads. | Required | Page 21 | |
| Mains and tie: drawout vacuum breakers, 1200 A, electrically operated, local and remote control. | Required | Page 22 | |
| Feeders: load-interrupter switch with current-limiting fuses, blown-fuse indication, class 0.3 B-0.2 CTs, and class 0.3 PTs. | Required | Page 23 | |
| Every section: low-voltage compartment of at least 42U, shorting CT terminal blocks, and 20% spare terminals and panel space. | Required | Page 20 | |
| Controls section: design goal of 8 cal/cm² or less incident energy (or state it); stainless sun shield; thermal calculations; inside temperature at or below 95°F. | To clarify | 95°F is not possible without air conditioning. | Page 24 |
| 48 VDC battery with 10 hours of reserve at full load, including meters; charger; sizing calculations. | To clarify | With motor operators and 11 or 12 meters, the battery cabinet becomes large (7.0 ft on the layout). | Page 31 |
| Infrared windows in all sections, heaters, grounding jaw on feeders, #4/0 ground lug at both ends, and LED indicating lights. | Required | Page 39 · Data sheet | |
| Documents: general arrangement, one-lines, wiring, relay and meter documents, battery calculations, manuals, and network diagram; as-builts within 2 weeks of shipment. | Required | Page 34 | |
| Routine factory tests with certified reports; factory test procedure for review; vendor powers up the equipment at the factory test. | Required | Page 32 | |
| SEL-351S relays, "or approved equal". | Required | Page 28 | |
| SEL-735 meters, no "or equal" given. | Required | Named product, no alternate. | Page 27 |
| Cisco IE-3300 or IE-3400 managed switch, or approved equal. | Required | Page 25 |