Mavlon Bid review
BID REVIEW · 23 NOVEMBER 2026

Alabama Port Authority 11712-02: McDuffie Main 25 kV Switchgear Upgrade (rebid)

Alabama Port Authority, McDuffie Coal Terminal, Mobile, Alabama. Engineer: Alliance Engineering. Project 11712, Task 2.

Bids due Thu 3 Dec 2026, 1:30 PMPage 3Questions due Wed 25 Nov 2026, 4 PM CSTPage 6Questions to Taylor Williams, Alliance EngineeringPage 3Type Supply only, plus 40 hours on sitePage 4

One PDF of 48 pages. The single-line diagram and layouts are images with no text, so they were read by eye. Each point below links to its source page: click a page chip to see the wording on that page.

48
Pages read
12
Positions on the single-line
21
Where the documents disagree
35
Questions for the buyer
All 35 questions and 21 conflicts, with their pages, in one file.

What matters most for your price

  1. Programming, SCADA work, site testing, and training: the booklet says the job is supply-only, but the attached programming specification requires the supplier to do all of it. The price form has no line for it, and unlisted work counts as included.Page 2Page 8
  2. The layout drawing marks the tie and one main as 2000 A, and every feeder as 1200 A. The single-line, specification, and data sheet call for 1200 A breakers and 600 A switches.Page 35 · LayoutPage 38 · Single-line
  3. The single-line shows one utility source. The specification requires two independent incoming sources and an automatic transfer scheme.Page 22Page 38 · Single-line
  4. The section count is 1, 13, or 15, depending on the document. The layout adds two CPT cabinets that no other document mentions.Page 39 · Data sheetPage 40Page 35 · Layout
  5. Main bus: tin-plated aluminum in the specification, copper in the data sheet.Page 21Page 39 · Data sheet

What this bid covers

Supplied by the bidder
  • A new outdoor 25 kV switchgear line-up replacing the existing one, on a platform built by others. Page 15
  • Two main vacuum breakers, one tie vacuum breaker, eight fused feeders, and one spare position. Page 15
  • Protection and metering: SEL-351S relays on both mains and the tie; SEL-735 meters on the mains, the tie, and every feeder. Page 27
  • A network section with a managed Ethernet switch (Cisco IE-3300 or IE-3400, or approved equal) and a fiber panel. Page 25
  • A battery section: 48 VDC station battery and charger with 10 hours of full-load reserve and a built-in 120 VAC panelboard. Page 31
  • Spare parts in the base bid, including three spare MV fuses of each type and rating. Page 33
  • Factory testing, delivery, bonds, and 40 hours of on-site commissioning support at an hourly rate. Page 8
By others or not stated
  • The platform and foundation. Page 18
  • Installation Page 4
  • Detailed on-site programming and testing, per the main specification. The programming specification says the opposite (see the first mismatch). Page 33
  • Not stated: who supplies the eight new splice enclosures, the feeder cables, and the 1200 A switch upstream of the left main. Page 38 · Single-line
System voltage23 kV system, 25 kV classp.18Main and tie bus1200 A continuousp.21Short circuit25 kA symmetrical; about 9.3 kA availablep.39BIL125 kVp.39EnclosureOutdoor NEMA 3R, coastal, coal dustp.17Control power48 VDCp.31

Single-line diagram, read from the image 250525-EL-OL-0001A

Drawing 250525-EL-OL-0001A, Rev A, page 38. It has no text layer, so every label was read from the image. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.

Matches the other documentsSomething to checkNot in this bidShown below
Single-line diagram

Switchgear, position by position

#PositionEquipment on the drawingFeedsChecksWhere it is written
M1Main N.E1200 A drawout vacuum breaker, 2 CT cores (1200/5), 2 fused PT sets, SEL-351S, SEL-735Utility, cable P-000A4 same4 to checkDrawing · M1
F1P-0001 · N.E SWGRFixed load-break switch, 200E SLOW fuse, CT 600/5, fused PT set, SEL-735Feeds the N.E pad-mount switchgear: 600 A, 23 kV switch with 150E SLOW (EMS1) and 200E SLOW (ETS1) fuses2 same5 to checkDrawing · F1
F2P-0002 · ASSEMBLY BUILDINGFixed load-break switch, 20E SLOW fuse, CT 600/5, fused PT set, SEL-735Feeds a 500 kVA transformer, 23 kV to 480 V, Z = 5.0%2 same4 to checkDrawing · F2
F3P-0003 · 32NFixed load-break switch, 250E SLOW fuse, CT 600/5, fused PT set, SEL-735Feeds a 2500 kVA transformer (23 kV / 480 V, Z = 6.37%) and a 5000 kVA transformer (23 kV / 4160 V, Z = 6.8%), each behind a 200E SLOW fuse2 same4 to checkDrawing · F3
F4P-0004 · 43EFixed load-break switch, 250E SLOW fuse, CT 600/5, fused PT set, SEL-735Feeds the 43E pad-mount switch: CLS 100E to a 3750 kVA transformer (43E 480 V switchboard) and CLS 125E to a 3500 kVA transformer (43E 13.2 kV switchgear)2 same4 to checkDrawing · F4
F5P-0005 · WATER PUMPSFixed load-break switch, 30E SLOW fuse, CT 600/5, fused PT set, SEL-735Feeds a 1000 kVA transformer, 23 kV to 480 V, Z = 5.7%2 same4 to checkDrawing · F5
TBus tieDrawout vacuum breaker 1200 A, CT 1200/5, one fused PT set, SEL-351S, SEL-735Links the N.E and N.W buses1 same3 to checkDrawing · T
M2Main N.W1200 A drawout vacuum breaker, 2 CT cores (1200/5), 2 fused PT sets, SEL-351S, SEL-735Future secondary feeder1 same3 to checkDrawing · M2
SPPrepared spaceProvisions only; type to be confirmed-2 to checkDrawing · SP
F6P-0006 · N.W SWGRFixed load-break switch, 200E SLOW fuse, CT 600/5, fused PT set, SEL-735Feeds the N.W pad-mount switchgear: 600 A switch, 23 kV, 150E SLOW fuse (NWMT, to the 23 kV / 4.16 kV transformer for the N.W building) and 200E SLOW fuse (SRDT, railroad building)2 same5 to checkDrawing · F6
F7P-0007 · 14WFixed load-break switch, 100E SLOW fuse, 600/5 CT, fused PT set, SEL-735Feeds a 3750 kVA transformer, 23 kV to 480 V, Z = 5.8%2 same5 to checkDrawing · F7
F8P-0008 · MAINT. SHOPSFixed load-break switch, 20E SLOW fuse, CT 600/5, fused PT set, SEL-735Feeds a 750 kVA transformer, 23 kV to 480 V, Z = 5.0%2 same5 to checkDrawing · F8

Where the documents disagree 21

Biggest cost impact first. Each item shows both sides and their page numbers.

1Are programming, SCADA work, site testing, and training in the bid?High cost
One document says
  • The index says the programming specification is for reference only. Page 2
  • The job is supply only, with 40 hours on site. Page 4
  • The main specification is the "sole basis" for pricing. Page 15
  • Others do detailed programming and testing on site. Page 33
Another says
  • The programming specification requires the supplier to do all engineering to configure, test, and commission. Page 43
  • The supplier sets all relays and coordinates with the utility. Page 44
  • The supplier configures all HMI, SCADA, and DCS communications. Page 46
  • Site testing, staying until buyer acceptance, and operator training. Page 47
Why it matters The price form has only four lines, and unlisted work is included in the bid price. If the programming specification applies, relay settings, utility coordination, SCADA setup, site testing, and training are unpaid. The programming specification is Rev A dated 13 Aug 2026, older than the main specification Rev B dated 5 Oct 2026. Page 8Question 1 ↓
2Site support: 40 hours or until the buyer accepts?High cost
One document says
  • 40 hours of on-site support. Page 4
  • Price form line 4: 40 hours of on-site commissioning help at an hourly rate. Page 8
Another says
  • Staff stay on site until the buyer accepts the system. Page 47
Why it matters A fixed 40 hours versus open-ended time on site. Question 1 ↓
3Tie and N.W main: 2000 A on the layout, 1200 A everywhere elseHigh cost
One document says
  • Layout: "TIE SECTION 2000A" and "MAIN-N.W 2000A", but "MAIN-N.E 1200A". Page 35 · Layout
Another says
  • Single-line: all three breakers are 1200 A frame. Page 38 · Single-line
  • Specification: 1200 A frame and rating for the mains and tie. Page 22
  • Data sheet: 1200 A main bus is checked; 2000 A is not. Page 39 · Data sheet
Why it matters 2000 A breakers, CTs, and bus use a larger, more expensive frame. The layout carries only the note "FOR VISUAL REPRESENTATION ONLY". Question 2 ↓
4Feeders: 1200 A on the layout, 600 A switches everywhere elseHigh cost
One document says
  • Layout: all eight feeders are labeled "1200A". Page 35 · Layout
Another says
  • Data sheet: 600 A load-break switch with grounding jaw and operating handle. Page 39 · Data sheet
  • Single-line: 20E to 250E fuses and 600/5 CTs. Page 38 · Single-line
Why it matters A 1200 A feeder would be a different device, most likely a breaker. Question 2 ↓
5One source or two?Design and cost
One document says
  • Single-line: only the left main connects to the utility. The right main is a "POTENTIAL FUTURE SECONDARY FEEDER". Page 38 · Single-line
  • Specification: a single utility source feeds the bus through two main breakers. Page 16
Another says
  • Specification: the two mains are "two independent incoming source connections". Page 22
  • Automatic transfer on both mains and the tie. Page 27
Why it matters Determines whether the right main needs real incoming terminations now and what the automatic transfer must do. Question 3 ↓
6How many sections: 1, 13, or 15?High cost
One document says
  • Data sheet: quantity is 1 section. Page 39 · Data sheet
  • Data sheet note 5: 13 sections in total. Page 40
Another says
  • Layout: 8 front sections and 7 rear sections (15 total), including two "CPT CABINET"s and a "BATTERY CABINET". Page 35 · Layout
  • Specification: a dedicated network section and a dedicated battery section. The layout shows no network section. Page 15
Why it matters Each extra cabinet is a priced section, and length counts toward the 35 ft preference. A likely reading of "13" is the 12 positions on the single-line plus one combined battery and network section. Page 18Question 4 ↓
7How many SEL-735 meters: 11 or 12?Cost
One document says
  • Specification: one more SEL-735 in the controls section to meter the whole line-up. Page 25
Another says
  • Programming specification: 11 SEL-735 meters. Page 44
  • Single-line: 11 meters (2 mains, the tie, and 8 feeders). Page 38 · Single-line
  • Data sheet note 7: SEL-735 on all breakers and fused feeders. Page 40
Why it matters A 12th meter also needs its own instrument transformers, which are not on the single-line. With two mains and a tie, one CT set cannot meter the whole line-up. Question 5 ↓
8Main bus: aluminum or copper?High cost
One document says
  • Specification: tin-plated aluminum main bus. Page 21
Another says
  • Data sheet: copper main bus and copper conductive parts, with tin plating. Page 39 · Data sheet
Why it matters The specification says the stricter requirement applies, but does not say which one that is here. Page 16Question 6 ↓
9Spare position: ready for a fused feeder or a breaker, and on which bus?Cost
One document says
  • Ready for a future fused feeder and meter. Page 18
  • Single-line: "PREPARED SPACE" on the N.W bus. Page 38 · Single-line
Another says
  • Ready for a future vacuum breaker, SEL-351S, and SEL-735. Page 23
  • Layout: "SPACE" on the N.E bus, between 43E and Water Pumps. Page 35 · Layout
Why it matters A breaker-ready cell costs more than a fused-switch cell, and the bus location changes the general arrangement. Question 10 ↓
10Feeder switches: manual handle or motor-operated with remote control?Cost
One document says
  • Specification: "electrically and manually operated" switches with remote operation. Page 22
  • Programming specification: remote control points for the eight feeders. Page 46
Another says
  • Data sheet: 600 A load-break switch "with grounding jaw and operating handle". Page 39 · Data sheet
Why it matters Eight motor operators, plus their load on the 48 VDC battery, which must last 10 hours. Question 8 ↓
11Warranty: two years or twelve months?Cost
One document says
  • Two years from final acceptance. Page 5
Another says
  • Network compartment: twelve months after being placed in service, "consistent with" the rest of the line-up. Page 34
  • Programming specification: 12 months after site testing or 18 months after shipment. This covers engineering services only. Page 48
Why it matters Final acceptance depends on installation by others, so the two-year period has no fixed end for the supplier. Question 14 ↓
12Bus link between the two line-upsCost
One document says
  • Specification: the two sections "share a common rear structure", with a continuous bus across both. Page 16
Another says
  • Layout: the two line-ups are 9 ft apart with a dashed "BUS" link. The specification itself refers to this layout. Page 36 · Layout top view
Why it matters The 9 ft aisle is intended. Unresolved: a "common rear structure" does not fit a 9 ft gap, and no document says who supplies the bus link across it or at what rating. Question 7 ↓
13Controls section: no air conditioning, yet cooler than outsideCost
One document says
  • Air conditioning is not required unless the vendor shows it is needed. Page 25
Another says
  • The inside of the compartment must stay at or below 95°F at the highest outdoor temperature, 104°F. Page 25
Why it matters Fans alone cannot keep the inside cooler than the outside air. The limit implies air conditioning. Question 11 ↓
14One line-up or two, and the 35 ft preferenceDesign
One document says
  • Bidders state one or two line-ups; line-ups under 35 ft are preferred. Page 4
  • Specification: one line-up or several. Page 17
Another says
  • Specification: the owner has selected a split arrangement. Page 16
  • Layout: lower row has 29.5 ft of switchgear plus a 7.0 ft battery cabinet, 36.5 ft total. Page 36 · Layout top view
Why it matters Determines whether a single line-up is a compliant base bid and whether the battery cabinet counts toward 35 ft. Question 13 ↓
15Factory acceptance test: optional, separate line, or included?Cost
One document says
  • Bidders state whether they will perform a factory test. Page 4
  • Price form: one lump sum for "Factory Testing and Delivery". Data sheet: factory inspection only. Page 8
Another says
  • Specification: price a witnessed test as a separate line. Page 33
  • Programming specification: full factory test of the programming and networks. Page 46
Why it matters Unlisted work counts as included, so there is nowhere on the price form for a separate witnessed test. Question 15 ↓
16Metal-clad or metal-enclosed?Cost
One document says
  • Specification: metal-clad, metal-enclosed, or both. Page 19
Another says
  • Programming specification: "a new outdoor 25 kV metal-clad switchgear lineup". Page 44
Why it matters Fused feeders are usually metal-enclosed. This one matters less because the programming specification is marked for reference only. Question 32 ↓
17UL listingCompliance
One document says
  • Specification codes list does not include UL. Page 16
Another says
  • Data sheet checks "UL Underwriter's Laboratories (Certifications As Applicable)". Page 39 · Data sheet
Why it matters A UL label on the MV assembly limits manufacturers and adds cost. Question 25 ↓
18Lowest outdoor temperatureDesign
One document says
  • Specification: 14°F (-10°C). Page 19
Another says
  • Data sheet: 0°F. Page 39 · Data sheet
Why it matters Affects heater and battery sizing. Question 23 ↓
19Cable entryDesign
One document says
  • Specification: bottom cable entry. Page 19
Another says
  • Specification, next section: top or bottom entry. Data sheet checks "Bottom" and "Right". Page 20
Why it matters Minor, but changes the cable compartments. Question 24 ↓
20Future extensionDesign
One document says
  • Specification: future extension is possible at either end. Page 21
Another says
  • Data sheet: "Provision for Future Expansion" is not ticked. Page 40 · Data sheet
Why it matters Bus extension provisions at both ends of both line-ups add cost. Question 29 ↓
21Platform size: 33 ft or 30 ft?Site
One document says
  • Layout top view, Rev B: platform is 33.0 ft by 44.5 ft. Page 36 · Layout top view
Another says
  • Site plan, Rev A: footprint is 44.5 ft by 30 ft. It was not reissued with Rev B. Page 37 · Site plan
Why it matters This is mostly for the platform builder, but it limits the line-up length. Question 33 ↓
Minor errors in the documents (no cost impact)
  • The single-line number is written three ways: 250525-EL-OL-0001A on the drawing, and 250525.01-EL-0001A and 250525.01-EL-OL-0001A on the data sheet. Page 39 · Data sheet
  • The specification calls the single-line "revised", but Rev A is the only revision on the sheet. Page 15
  • The data sheet header says "Issued for Bid", and the footer says "Re-Issue for Bid". It has no document number, though other pages cite it as 250525.01-EL-DS-001. Page 39 · Data sheet
  • Section 6.2 is cited, but there is no Section 6.2. Page 32
  • "Protection and control for both breakers" appears where there are three breakers. Page 22
  • "Two (3) SEL-351S" and "Ten (11) SEL-735". Page 45
  • The warranty mentions "RTAC programming", but no RTAC is listed anywhere. Page 48

Questions for the buyer 35

Ready to send. Biggest cost impact first.

1Programming and site workThe index says 250525-EL-SPEC-002 is "attached for reference only", and the project is supply-only with 40 hours on site. SPEC-002 calls for the supplier to provide all relay settings, utility coordination, HMI/SCADA/DCS setup, site testing until acceptance, and training. Which SPEC-002 work is in the base bid? Page 8 says unlisted items are included in the bid items. If any SPEC-002 work is needed, please add price lines to the Schedule of Prices.Page 2Page 8Page 43
2Breaker and feeder ratingsLAY-0001 labels the tie and N.W main "2000A" and every feeder "1200A". The single-line, SPEC-001, and the data sheet specify 1200 A breakers and 600 A fused load-break switches. Please confirm 1200 A for the tie and both mains, and 600 A fused switches for the feeders.Page 35 · LayoutPage 39 · Data sheet
3Second sourceThe single-line shows only the left main connected to the utility; the right main is a "POTENTIAL FUTURE SECONDARY FEEDER". SPEC-001 calls the mains "two independent incoming source connections" and specifies automatic transfer. (a) Is a second source part of this project? (b) Should the right main include incoming terminations now, and for what cable? (c) With one source, what should the transfer scheme do?Page 38 · Single-linePage 22
4Section countThe data sheet lists 1 section, and note 5 lists 13 sections. LAY-0001 shows 15, including two CPT cabinets and a battery cabinet, but no network section. Please confirm the sections. Does "13" mean the 12 positions on the single-line plus one battery and network section? Are the two CPT cabinets required, and if so, what rating, primary connection, and secondary voltage are required?Page 40Page 35 · Layout
5Twelfth meterSPEC-001 specifies one more SEL-735 in the controls section to meter the whole line-up. SPEC-002 and the single-line show 11. Is the twelfth meter required? If so, which instrument transformers should it use?Page 25Page 44
6Bus materialSPEC-001 specifies a tin-plated aluminum main bus, while the data sheet marks copper. Which is required? Is the other acceptable as an alternate?Page 21Page 39 · Data sheet
7Bus link between the line-upsLAY-0002 shows the two line-ups 9 ft apart with a "BUS" link, and SPEC-001 refers to it. SPEC-001 also says the sections "share a common rear structure". (a) Is the link a bus duct or bus bridge across the aisle, and is it part of the switchgear supply? (b) What are its length, entry points, and rating? (c) Must it be outdoor-rated and supported from the platform?Page 36 · Layout top viewPage 16
8Feeder switch operationSPEC-001 specifies electrically and manually operated feeder switches with remote control, and SPEC-002 specifies remote control points on all eight feeders. The data sheet ticks a switch "with grounding jaw and operating handle". Are motor operators required on all eight? Are fixed-mounted switches acceptable?Page 22Page 39 · Data sheet
9Cables and splice enclosuresThe single-line shows eight new MV splice enclosures, feeder cables P-0001 to P-0008, incoming cable P-000A, and a 1200 A switch upstream of the left main. Are any of these in the switchgear supply, or are they existing or supplied by others?Page 38 · Single-line
10Spare positionOne page calls for provisions for a future fused feeder and meter; another calls for a future vacuum breaker with SEL-351S and SEL-735. Which is required? The single-line places the space on the N.W bus; LAY-0001 places it on the N.E bus between 43E and Water Pumps. Which bus is correct?Page 18Page 23
11Air conditioningSPEC-001 limits the controls compartment to 95°F at 104°F outdoors, but says air conditioning is not required. Ventilation cannot keep the inside cooler than the outside. Please confirm that air conditioning should be included, or relax the 95°F limit.Page 25
12Short-circuit ratingsPlease confirm the ratings for the breakers, bus bracing, and fused switches. The data sheet lists "Symm Short Circuit: 25kA", an available fault of about 9.3 kA, and "Interrupting Capacity 42000 RMS" for the feeders.Page 39 · Data sheetPage 39 · Data sheet
13Single or split line-upIs one continuous line-up a compliant base bid, since SPEC-001 says the owner selected a split arrangement? For the 35 ft preference, does the 7.0 ft battery cabinet count toward the length?Page 4Page 16
14WarrantyWhich warranty applies? Page 5 requires two years from final acceptance; SPEC-001 states 12 months after being placed in service; SPEC-002 states 12 months after site testing or 18 months after shipment.Page 5Page 34Page 48
15Factory testIs a witnessed factory test mandatory? Should it be a separate price line, as SPEC-001 states, or included in item 3 "Factory Testing and Delivery"? If witnessed, how many people will attend, and for how many days?Page 33Page 8
16Drawings with the bidThe data sheet checks "Vendor Drawings Required Prior to Bid". Which drawings must be included with the bid? Page 6 lists only items (a) to (d) for the envelope.Page 39 · Data sheetPage 6
17System groundingThe data sheet checks "Delta". Please confirm the 23 kV source grounding, the PT connection, and how ground fault (50G/51G) should be sensed. No ground CT is shown on the single-line.Page 39 · Data sheetPage 28
18CT cores on the mainsEach main has two 1200/5 CT cores on the single-line. Are both protection class, or is one protection class and one metering class (0.3 B-0.2)?Page 38 · Single-linePage 23
19Revenue meteringSPEC-002 calls the SEL-735 a "Revenue / Power Quality Meter". Is revenue-grade metering required anywhere, such as on the utility main? If yes, where and to what class?Page 44
20Transfer sensingOn the single-line, the main PTs are on the bus side of each breaker, with none on the line side. Should line-side voltage sensing be added for the automatic transfer? Which PTs and CTs are required in the tie section?Page 38 · Single-linePage 4
21Surge arrestersSPEC-001 has a "Grounding and Surge Protection" section but specifies no surge device. The data sheet leaves "Surge Suppression on Incoming Section" unchecked, and the single-line shows no arresters. Please confirm none are required, or provide the location and rating.Page 31Page 40 · Data sheet
22Lockout relaysThe relay I/O lists "86 Lockout". Are separate 86 lockout relays required on the mains and the tie? If yes, which functions trip them?Page 28
23Lowest temperatureSPEC-001 states 14°F (-10°C); the data sheet states 0°F. Which applies?Page 19Page 39 · Data sheet
24Cable entrySPEC-001 states bottom entry in one section and "top or bottom" in the next. The data sheet checks "Bottom" and "Right". Please confirm bottom entry for all cables. What does "Right" mean?Page 19Page 20
25UL labelIs a UL listing or label required for the MV assembly? The data sheet checks UL "As Applicable"; SPEC-001 does not list UL.Page 39 · Data sheetPage 16
26Control voltageSPEC-001 calls for 48 VDC, while bidders are asked to state 125 VDC, 48 VDC, or both. Is 125 VDC for trip and close with 48 VDC for communications acceptable?Page 4Page 31
27120 VAC supplyWhere does the 120 VAC for the panelboard (heaters, lights, air conditioning, charger) come from: the CPT cabinets on LAY-0001, or the existing 240/120 V panel and 25 kVA transformer on the single-line? What voltage and kVA are available?Page 18Page 38 · Single-line
28Fuse ratingsFuses are sized per a coordination study not included in the package. Please confirm that the single-line fuse ratings are final. (a) P-0001 and P-0006 are 200E, and each feeds a downstream 200E fuse. (b) P-0007 is 100E on a 3750 kVA transformer (about 94 A). (c) P-0008 is 20E on a 750 kVA transformer (about 19 A).Page 22Page 38 · Single-line
29Future extensionSPEC-001 calls for future extension at either end, but the data sheet leaves "Provision for Future Expansion" unchecked. Are extension provisions required at both ends of both line-ups?Page 21Page 40 · Data sheet
30Delivery and sitePlease confirm delivery to McDuffie Coal Terminal, 1901 Ezra Trice Blvd, Mobile, AL 36603. Who unloads and sets the equipment on the platform? Are there any shipping split or crane limits? Is a seismic or wind design basis required?Page 13Page 19
31NameplatesThe data sheet refers to an attached nameplate list and checks "Attachments Included", but no attachment is in the package. Please send the nameplate schedule or confirm use of standard engraved nameplates.Page 39 · Data sheetPage 40 · Data sheet
32Construction classSPEC-002 says "metal-clad switchgear", while SPEC-001 allows metal-clad, metal-enclosed, or both. Are metal-enclosed fused feeders with metal-clad breaker sections compliant?Page 44Page 19
33Current drawingsPlease confirm the current drawings: single-line 250525-EL-OL-0001A Rev A (08/10/26), LAY-0001 Rev A, LAY-0002 Rev B, and LAY-0003 Rev A. LAY-0003 shows a 30 ft footprint, while LAY-0002 shows 33 ft.Page 38 · Single-linePage 36 · Layout top viewPage 37 · Site plan
34Cross-referencesSome section references in SPEC-001 appear incorrect: 5.9 for the battery (the battery is in 5.13) and 6.2 for arc-flash isolation (there is no 6.2). SPEC-002 says "Two (3)" and "Ten (11)". Please confirm the intended sections and confirm that the counts are 3 and 11.Page 18Page 32Page 45
35RTACThe SPEC-002 warranty mentions RTAC programming, but no RTAC is listed anywhere. Please confirm that no SEL RTAC is to be supplied.Page 48

Requirements to meet

27 · 6 to clarify
RequirementStatusNotePage
Submit a sealed bid by courier by 1:30 PM, Thu 3 Dec 2026. No fax or email.RequiredPage 3
Bid bond or certified check: 5% of the bid, up to $10,000.RequiredPage 6
Include the Beason-Hammon certificate and E-Verify evidence with the bid.RequiredPage 6
Bid is valid for 60 days. Award is based on best value: cost, solution, and delivery. Alternates that exceed the specification are allowed.RequiredPage 3
Provide a performance bond for 100% of the contract. Submit the contract and bonds within 10 days of notice of award.RequiredPage 4
Liquidated damages are $1,200 per day for late delivery against the bidder's own schedule. Remove statements to the contrary.To clarifyCommercial risk to include in the price.Page 5
Split lead time into drawings, manufacturing (with factory test), and shipping.RequiredPage 4
Bidder must state: factory test (yes or no); one or two line-ups; full bill of materials; whether tie PTs and CTs for transfer are included; spares list; 125 or 48 VDC; and whether the 10-hour battery requirement is met.RequiredPage 4
Two-year guarantee from final acceptance.To clarifyFinal acceptance depends on installation by others.Page 5
Site access requires a TWIC card, a port badge, and a vehicle decal. This applies to the 40 hours on site.RequiredPage 5
List exceptions to SPEC-002 on a separate sheet titled "Exceptions". Exceptions not listed count as accepted.To clarifyThis applies even though SPEC-002 is "for reference only".Page 43
ANSI/IEEE C37.20.2 and/or C37.20.3, NEMA, NEC, and FM apply. The data sheet adds UL "as applicable".To clarifyUL question is open.Page 16
Outdoor NEMA 3R; coastal, coal dust, humidity up to 100%, up to 3,300 ft. Galvanized or stainless steel is acceptable.RequiredPage 19
1200 A bus, epoxy-insulated for 27 kV class, braced to the data sheet short-circuit rating.RequiredPage 21
Copper ground bus running the full length of both sections, sized for 2 seconds.RequiredPage 21
At least 36 in from cable entry to the termination pads; NEMA 2-hole pads.RequiredPage 21
Mains and tie: drawout vacuum breakers, 1200 A, electrically operated, local and remote control.RequiredPage 22
Feeders: load-interrupter switch with current-limiting fuses, blown-fuse indication, class 0.3 B-0.2 CTs, and class 0.3 PTs.RequiredPage 23
Every section: low-voltage compartment of at least 42U, shorting CT terminal blocks, and 20% spare terminals and panel space.RequiredPage 20
Controls section: design goal of 8 cal/cm² or less incident energy (or state it); stainless sun shield; thermal calculations; inside temperature at or below 95°F.To clarify95°F is not possible without air conditioning.Page 24
48 VDC battery with 10 hours of reserve at full load, including meters; charger; sizing calculations.To clarifyWith motor operators and 11 or 12 meters, the battery cabinet becomes large (7.0 ft on the layout).Page 31
Infrared windows in all sections, heaters, grounding jaw on feeders, #4/0 ground lug at both ends, and LED indicating lights.RequiredPage 39 · Data sheet
Documents: general arrangement, one-lines, wiring, relay and meter documents, battery calculations, manuals, and network diagram; as-builts within 2 weeks of shipment.RequiredPage 34
Routine factory tests with certified reports; factory test procedure for review; vendor powers up the equipment at the factory test.RequiredPage 32
SEL-351S relays, "or approved equal".RequiredPage 28
SEL-735 meters, no "or equal" given.RequiredNamed product, no alternate.Page 27
Cisco IE-3300 or IE-3400 managed switch, or approved equal.RequiredPage 25

Not in the package