Mavlon Bid review
BID REVIEW · 24 NOVEMBER 2026

Abwasserverband Thurau, Lot 46 BKP 231.11: three transformer stations with 24 kV switchgear

Neubau ARA Thurau – Los 46, BKP 231.11 Trafostationen (Etappe West und Ost)

Abwasserverband Thurau (AVT), Uzwil. Lot 46, BKP 231.11: 14 SF6-free 24 kV MV panels (TS 01: 7, TS 02: 3, TS 03: 4), three 1000 kVA transformers, LV disconnection points, 48 VDC UPS, and MV ring cables. Open procedure under the GPA; documents in German.

Offer due Fri 15 Jan 2027, 12:00 CET (SIMAP + 1 paper copy)Conditions (Teil A) p.5Questions closed Fri 20 Nov 2026; answers due 4 DecConditions (Teil A) p.5Award Price 50%, quality 35%, bidder 15%Conditions (Teil A) p.12Scope Supply, installation, testing, commissioning, documentationConditions (Teil A) p.16

Eleven PDFs, seven drawings, and the escalation form were read page by page. The three single-line diagrams, supply overview, protection concept draft, and both layouts were read directly from the drawings. Every point links to its source page: click a page chip to see the wording on the page.

The question window has closed. Questions were due by 20.11.2026; the buyer's answers are due by 04.12.2026 and are not in this package. Until the offer deadline, the buyer may still issue corrections and additions that bidders must include in their offer. Missing items or errors in the bill must be reported with the offer (Teil A, item 27). If work can be interpreted two ways and affects the price, the bidder must state this with the offer, or the site manager's interpretation applies (Teil A 6.4.4). Form B3 requires a list of all deviations, reservations, and exclusions. Therefore, the points below go into the offer: on the remarks page (Teil B chapter 8) and in the B3 deviation list. Conditions (Teil A) p.5Conditions (Teil A) p.8Conditions (Teil A) p.22Enclosures list (B3) p.1
211
Pages read
14
Positions on the single-line
14
Where the documents disagree
22
Points for your offer
All 22 questions and 14 conflicts, with their pages, in one file.

What matters most for your price

  1. Escalation: Teil A, Teil B, and the B2 form use the SIA 122 price formula with 20% fixed, but the contract (C1 3.5) has SIA 123 PKI ticked. Under the contract's order of precedence, the contract deed comes first, so SIA 123 likely prevails unless clarified. Deliveries are in 2029 and from June 2033.Contract (C1) p.6Conditions (Teil A) p.24Contract (C1) p.14
  2. C5 requires 3 VTs and a summation CT in every ring, transformer, and station-breaker panel, plus more protection functions. The single-lines and protection draft show about 9 fewer VT sets and 5 fewer summation CTs. The bill and Teil A make the draft and single-line the basis.EMSRL concept (C5) p.21Bill of quantities (B1) p.5Protection concept draft · CT/VT dots
  3. C5 describes a network control cabinet per station with redundant PLCs, servers, and panels. The bill has no line item for it, and Teil A 7.3.6 assigns the control rack and process-control integration to the owner.EMSRL concept (C5) p.26Conditions (Teil A) p.30
  4. TS 03 LV disconnection point: the bill specifies two ways and a coupler, but every drawing and C5 5.16 show one breaker per transformer.Bill of quantities (B1) p.22Single-line TS 03 · NS03:01EMSRL concept (C5) p.23
  5. TS 03 is delivered in June 2033, six years after TS 01 and TS 02, while C5 requires one switchgear type across all stations.Conditions (Teil A) p.17EMSRL concept (C5) p.20

What this bid covers

Supplied by the bidder
  • Delivery, installation, testing, commissioning, and documentation of the MV switchgear, transformers, and LV disconnection points, including their auxiliary equipment and cables. Conditions (Teil A) p.16
  • One complete MV switchgear per station to B1 chapter 2.1, the single-line, and the layout, with all switching and earthing devices, protection, metering, voltage indication, and secondary cabinets. TS 01: 7 panels, TS 02: 3, TS 03: 4. Bill of quantities (B1) p.10
  • Three 1000 kVA distribution transformers, one per station. Bill of quantities (B1) p.10
  • Per station: MV cable from switchgear to transformer (3×1×95/25 mm² Cu XKDT-Y, 15 m) and LV cable to the disconnection point (four parallel systems of 4x1x185 mm², 8 m), with trays and fixings. Bill of quantities (B1) p.11
  • Per station: an LV disconnection point, a 48 VDC UPS for the switchgear, control and communication cabling to the owner's rack, earthing, commissioning with the integral test, and documentation. Bill of quantities (B1) p.12
  • MV ring cables XKDT-YT 3x1x95/25 mm² Cu: TS 01 to TS 02, 20 m; TS 01 to TS 03, 140 m; TS 02 to TS 03, 110 m. Bill of quantities (B1) p.25
  • Project-wide lump sums: project management and shop drawings, interface coordination, plant-specific protection concept with calculations and setting tables, ESTI documents, programme, documentation, and training. Bill of quantities (B1) p.9
  • Clarifying the metering interface with the grid operator, including CTs, VTs, and billing metering, and executing the resulting work within the bidder's scope. Conditions (Teil A) p.31
By others or not stated
  • MV cable from the grid to the handover point in TS 01: laid by the grid operator (SAK). Conditions (Teil A) p.30
  • Station rooms, duct banks between stations, earthing grid, and foundation connection points: by the owner. Conditions (Teil A) p.29
  • Room ventilation, downstream LV distributions and their cables, 230 VAC supply to the UPS, control and communication rack in each station, and process-control integration: by the owner. Conditions (Teil A) p.30
  • ESTI approval application and fees: by the owner; the bidder supplies the documents. Conditions (Teil A) p.31
  • The diesel standby generator (1000 - 1250 kVA on the supply overview) is not in the bill and, as far as the package states, not in this lot. Supply overview (EVS) · NEA
Rated voltage24 kV, run at 20 kV, 50 Hzp.3Busbar and feeders630 Ap.3Short-time current20 kA, 1 sp.20Arc ratingIAC AFLR 20 kA, 1 sp.3InsulationSF6-freep.3Panels14: TS 01 7, TS 02 3, TS 03 4p.1

Single-line diagram, read from the image IBG 8500004-12-5103 · IBG 8500004-12-5104 · IBG 8500004-12-5101

MS-Prinzipschema TS 01 ARA (Biologie), 8500004-12-5103, last revised 08.10.2026. Manufacturer and type are blank ("Fabrikat: -"); 24 kV, 630 A, with no short-circuit rating on the sheet. Red is medium voltage and blue is low voltage. Nothing is marked as new, existing, or by others, and this sheet has no ownership boundary line. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.

Matches the other documentsSomething to checkNot in this bidShown below
Single-line diagram

Switchgear, position by position

TS 01, 7 panels

#PositionEquipment on the drawingFeedsChecksWhere it is written
MS01:01MS01:01 · SAKIncomer: motor-operated breaker and load-break/earthing switch, CT 200/1, summation CT 60/1, VT on the SAK section, arrester, UMGSAK 20 kV grid; cable laid by the grid operator3 same3 to checkDrawing · MS01:01
MS01:02MS01:02 · HochführungRiser, no switching deviceCable loop to MS01:031 same1 to checkDrawing · MS01:02
MS01:03MS01:03 · MessungUtility metering: CT and VT (EVU), 10 A fuse, meter boxBilling meter "WZ / BZ"4 to checkDrawing · MS01:03
MS01:04MS01:04 · StationsschalterStation breaker: motor-operated breaker with load-break/earthing switch, CT 200/1, busbar VTMain busbar of TS 011 same4 to checkDrawing · MS01:04
MS01:05MS01:05 · TS 02 ARARing feeder: motorized breaker, load-break/earthing switch, CT 200/1, summation CT 60/1, arrester, relayRing cable to TS 02 ARA, XKDT-YT 3x1x95/25 mm²2 same4 to checkDrawing · MS01:05
MS01:06MS01:06 · Tr01:01Transformer feeder: motorized breaker, load-break/earthing switch, CT 50/1, relayTr01:01, 1000 kVA, 20 kV / 420 V2 same4 to checkDrawing · MS01:06
MS01:07MS01:07 · TS 03 ARARing feeder: motorized breaker, load-break/earthing switch, CT 200/1, summation CT 60/1, arrester, relayRing cable to TS 03 ARA, XKDT-YT 3x1x95/25 mm²2 same4 to checkDrawing · MS01:07

TS 02, 3 panels

#PositionEquipment on the drawingFeedsChecksWhere it is written
MS02:01MS02:01 · TS 03 ARARing feeder: motorized breaker, load-break/earthing switch, CT 200/1, summation CT 60/1, arrester, relayRing cable to TS 03 ARA, XKDT-YT 3x1x95/25 mm²2 same4 to checkDrawing · MS02:01
MS02:02MS02:02 · Tr02:01Transformer feeder: motorized breaker, load-break/earthing switch, CT 50/1, relayTr02:01, 1000 kVA, 20 kV / 420 V1 same5 to checkDrawing · MS02:02
MS02:03MS02:03 · TS 01 ARARing feeder: motor-operated breaker + load-break/earthing switch, CT 200/1, arrester, relayRing cable to TS 01 ARA, XKDT-YT 3x1x95/25 mm²1 same5 to checkDrawing · MS02:03

TS 03, 4 panels

#PositionEquipment on the drawingFeedsChecksWhere it is written
MS03:01MS03:01 · TS 02 ARARing feeder: motorized breaker, load-break/earthing switch, CT 200/1, summation CT 60/1, arrester, relayRing cable to TS 02 ARA, XKDT-YT 3x1x95/25 mm²2 same5 to checkDrawing · MS03:01
MS03:02MS03:02 · Tr03:01Transformer and generator feeder: motor-operated breaker, load-break/earthing switch, busbar VT, cable-side VT and CT with verified metering coresTr03:01, 1000 kVA; standby generator on its LV side2 same4 to checkDrawing · MS03:02
MS03:03MS03:03 · TS 01 ARARing feeder: motorized breaker, load-break/earthing switch, CT 200/1, summation CT 60/1, arrester, relayRing cable to TS 01 ARA, XKDT-YT 3x1x95/25 mm²2 same5 to checkDrawing · MS03:03
MS03:04MS03:04 · ReserveSpare feeder, fully equipped: breaker (motor), load-break/earthing switch, CT 200/1, summation CT 60/1, arrester, and relayNone stated1 same3 to checkDrawing · MS03:04

Where the documents disagree 14

Biggest cost impact first. Each item shows both sides and their page numbers.

1Escalation: SIA 122 price formula or SIA 123 PKI?High cost
One document says
  • Teil A 6.8.1: escalation uses the SIA 122 price formula and the KBOB method, with 20% non-adjustable. Teil B 5.3.1 states the same. Conditions (Teil A) p.24
  • The B2 form the bidder must complete is the SIA 122 sheet: reference date 15.01.2027, fixed share a = 20.00%. Escalation form (B2) p.1
Another says
  • Contract C1 3.5, checked box: "PKI mit NPK-Kostenmodellen nach Norm SIA 123, Ausgabe 2021 sowie SIA 123-C1, Ausgabe 2023". Contract (C1) p.6
  • C1 18.2: rank decides between contract components. The contract deed ranks first; the B2 form becomes part of the contract only through the offer, which ranks lower. Contract (C1) p.14
Why it matters With deliveries in 2029 and from June 2033, the escalation method determines a large share of the real price. By rank, SIA 123 PKI likely prevails unless clarified. Do not assume SIA 122 without flagging it; the B2 form is still mandatory with the offer. Conditions (Teil A) p.24Contract (C1) p.3Question 1 ↓
2CTs, VTs, and summation CTs: C5 requires many more than the drawings showHigh cost
One document says
  • C5 5.10: the station breaker, ring panels, and network transformers each require 3 CTs (protection and metering core), 1 summation CT, and 3 VTs 20/0.1 kV. Generator transformers require the same with verified cores. EMSRL concept (C5) p.21
Another says
  • Single-lines: VTs are only on the busbars, the SAK section, and the MS03:02 cable side. No summation CT in MS01:04, MS01:06, MS02:02, MS02:03, or MS03:02. Single-line TS 01 · MS01:04
  • The protection draft shows the same CT and VT dots. Protection concept draft · CT/VT dots
  • B1 2.2: CTs, VTs, and summation CTs follow "gemäss Schutzkonzeptentwurf, Prinzipschema" and the grid operator's rules. Teil A 7.3.2: the protection draft is the basis. Bill of quantities (B1) p.5
Why it matters Read literally, C5 adds about 9 sets of 3 line VTs and 5 summation CTs, plus a metering core in every CT. Line VTs in compact SF6-free panels can also change panel width. The bill and Teil A favor the drawings, but C5 is also listed among the technical requirements. Conditions (Teil A) p.28Question 2 ↓
3Network control system (NLS): in C5, not in the billHigh cost
One document says
  • C5 7: an NLS control cabinet per switchgear with redundant PLCs, a gateway, switches, and a server; server 1 is in TS 01 and operator panels are in TS 02. EMSRL concept (C5) p.26
  • The layouts show an "NLS / PLS" box in each station. Layout TS 01 / TS 02 · NLS / PLS
  • Teil A 7.3.2: technical requirements come from the bill, the "EMSRL Konzepte", and the other documents. Conditions (Teil A) p.28
Another says
  • The bill has no NLS item. B1 4.6: the rack, higher-level communication, and process-control integration are by the owner. Bill of quantities (B1) p.13
  • Teil A 7.3.6: supply and installation of the control and communication rack, and integration into the process-control system, are in the owner's column. The bidder's cabling ends "bis zu den Racks". Conditions (Teil A) p.30
  • C5 is a plant-wide concept and the basis for the construction project, not a lot description. EMSRL concept (C5) p.9
Why it matters Redundant PLCs, servers, and panels in three stations would be a major cost. The documents (B1 4.6 and Teil A 7.3.6) indicate the NLS is not in Lot 46, but nothing states this outright; state the assumption in the offer. Question 3 ↓
4Warranty start: per station or at acceptance of the whole works?Cost
One document says
  • Teil A 6.7: the warranty periods for TS 01, TS 02, and TS 03 each start separately at acceptance of that station. Conditions (Teil A) p.24
  • Teil A 6.9.1: a separate stage invoice applies to Etappe West after acceptance of TS 01 and TS 02, against the joint surety owed for that stage. Teil A 7.3.8: acceptance is per station. Conditions (Teil A) p.25
Another says
  • C1 18.2 (Art. 157): notice and limitation periods for all parts start at acceptance of the whole works, "sofern in diesem Werkvertrag nicht ausdrücklich etwas anderes vereinbart wurde". Contract (C1) p.16
Why it matters Etappe Ost will not be ready for commissioning until February 2034. Teil A is part of the contract, and its per-station rule, per-stage surety, and per-station acceptance read as the "expressly agreed otherwise" case. Per station is the likely reading, but flag it anyway. Conditions (Teil A) p.32Conditions (Teil A) p.17Question 4 ↓
5TS 03 LV disconnection point: two ways and a coupler, or one breaker?Cost
One document says
  • B1 7.4.1: "mit zwei Einspeise-/Abgangswegen, Leistungsschaltern, Kopplung/ZEP", matching the TS 01 text word for word. Bill of quantities (B1) p.22
Another says
  • TS 03 single-line: "NS Trennstelle NS03:01" has one breaker and a separate ZEP box, with no coupler. Single-line TS 03 · NS03:01
  • Supply overview and layout 4002 show only NS03:01 and the ZEP. Layout TS 03 · NS03:01
  • C5 5.16: one LV breaker per transformer. B1 7.4.1 itself says "gemäss Kapitel 2.4 und Prinzipschema". EMSRL concept (C5) p.23
Why it matters It is unclear whether one air circuit breaker of at least 1'500 A, a coupler, and a board section are required. Everything except the bill text supports one breaker, so 7.4.1 looks copied from TS 01. C5 4.6 calls for an incomer and a coupler per station, but for the downstream main LV board, which is by the owner. EMSRL concept (C5) p.17Question 5 ↓
6Power-quality analysers: 4 at MS01:04, or 1 in MS01:01?Cost
One document says
  • B1 2.1: power-quality analyser at the grid handover point, "(MS01:04 Stationsschalter / z.B. Janiza UMG 512-Pro)", "Anzahl: 4x". Bill of quantities (B1) p.4
Another says
  • TS 01 single-line: "UMG" is drawn in MS01:01 SAK only, not in MS01:04 or any other panel on the three sheets. Single-line TS 01 · MS01:01
Why it matters It is unclear whether three extra analysers of the UMG 512-Pro class with their CT and VT wiring are required, and in which panels. Question 6 ↓
7Utility metering CTs and VTs: supplied by SAK or by the bidder?Cost
One document says
  • C5 14: Metering consists of meters, "Messwandler", and the SAK metering board. SAK specifies and provides it at its own cost. Installation and wiring are by the customer. EMSRL concept (C5) p.52
Another says
  • Teil A 7.3.6, bidder's column: Clarify the metering interface "inklusive Messwandler" with the grid operator and build what follows within the bidder's scope. Conditions (Teil A) p.31
  • TS 01 single-line: "Spannungswandler EVU (Messung)" and "Stromwandler EVU (Messung)" in MS01:03. Single-line TS 01 · Legend 10.) and 11.)
Why it matters Supply by SAK means installation only; supply by the bidder means buying grid-approved, verified transformers. MS03:02 also has verified cores for generator metering, with no party named for them or the verification cost. Single-line TS 03 · Legend 9.) and 10.)Question 8 ↓
8Protection functions: C5 5.11 or the protection draft?Design
One document says
  • C5 5.11: Station breaker and ring panels "ANSI 25 / 49 / 59N / 67 / 67N / 67NIEF / Sammelschienenschutz"; network transformers 49 / 51> / 51>> / 51N / 27 / 59; generator transformers 49 / 67>v / 67>r / 67>>v / 51N / 32R / 59 / 25. EMSRL concept (C5) p.21
Another says
  • Protection draft: Ring panels 49 I, 50P/51P, 50BF, 50SOTF, 67P, 67N/32N, 68 (no 25, 59N, 67NIEF, or busbar protection); transformer feeders without 51N, 27, and 59; MS03.02 without 51N and 32R. Protection concept draft · TS 02 tables
  • B1 2.2: Functions are based on the protection draft. Each C5 group also states "ANSI Ergänzungen gemäss separatem Schutzkonzept". Bill of quantities (B1) p.5
Why it matters 25, 27, 59, and 59N need line or open-delta VT inputs not shown on the single-lines (see the CT and VT point); busbar protection requires extra engineering. The bidder must complete the protection concept anyway. Question 2 ↓
9Surge arresters: one end of each ring cable, or both ends?Cost
One document says
  • C5 4.9: Arresters at the SAK incoming cable and "pro Ringleitung an einem Ende" (one end per ring cable): 4 sets. EMSRL concept (C5) p.18
Another says
  • Single-lines: 4.) at both ends of all three ring cables and in reserve MS03:04, plus MS01:01: 8 sets. Single-line TS 03 · MS03:04
Why it matters The drawings show four more arrester sets than C5 requires. Question 12 ↓
10Standby generator: 1.0 MVA or 1.25 MVA?Design
One document says
  • C5 3.3: "muss eine 1.25 MVA Netzersatzanlage (NEA) eingesetzt werden". Supply overview: "1000 - 1250 kVA". EMSRL concept (C5) p.10
Another says
  • C5 4.4: Standby feed of 1.0 MVA. C5 4.5: Genset LTP 850 kVA, PRP 800 kVA, COP 728 kVA, feeding in "über einen 1.0 MVA Transformator". EMSRL concept (C5) p.17
  • B1 2.3 gives one 1'000 kVA spec for all three transformers, including Tr03:01. Bill of quantities (B1) p.6
Why it matters Based on the C5 4.5 genset figures, a 1000 kVA Tr03:01 is enough and the 1.25 MVA figure is the outlier. This is worth one line in the offer, along with the question of whether Tr03:01 needs any special design for reverse feed. Supply overview (EVS) · NEAQuestion 13 ↓
11UPS loads: switchgear only, or the NLS as well?Cost
One document says
  • B1 2.6: loads are protection devices, motor drives, closing and trip coils, and binary signals of the MV switchgear; 2 h autonomy. Bill of quantities (B1) p.8
Another says
  • C5 11.2: the UPS feeds the MV switchgear controls and the network control system at 48 VDC. EMSRL concept (C5) p.44
Why it matters Battery size for 2 h depends on whether NLS PLCs and servers are connected to it. This depends on the NLS point. Question 14 ↓
12MS02:03: no summation CT, but directional earth-fault protection requiredDesign
One document says
  • TS 02 single-line: MS02:03 has CT 6.) only; the other end of the cable (MS01:05) and every other ring panel have 7.). Single-line TS 02 · MS02:03
Another says
  • Protection draft: no black dot at MS02:03, but its table lists "ANSI 67N/32N". Protection concept draft · MS02.03
Why it matters Sensitive directional earth-fault protection on this cable needs the core-balance CT: one more CT and its wiring. C5 calls for a mounting rail for the summation CTs directly below the switchgear, which affects who installs it. EMSRL concept (C5) p.24Question 18 ↓
13TS 03 ring panels: destinations swapped on the single-lineDrawing
One document says
  • TS 03 single-line: "MS03:01 TS 02 ARA" and "MS03:03 TS 01 ARA". Single-line TS 03 · Panel headers
Another says
  • Supply overview (cable routing traced), protection draft, and layout 4002: MS03:01 to TS 01 ARA and MS03:03 to TS 02 ARA. Supply overview (EVS) · TS 03 header
  • Teil A figure 2: same as the overview. Conditions (Teil A) p.17 · Figure 2
Why it matters Panel labelling, cable routing, and pairing of the fibre-linked directional comparison protection between ring ends. Question 20 ↓
14LV transformer cable: three different descriptionsCost
One document says
  • B1 2.5: "Purwil TrafoCable bandiert 4x4x185 mm² CU (oder technisch gleichwertig)". Bill of quantities (B1) p.7
Another says
  • B1 4.3.2: "vier Parallelsysteme mit je 4x1x185 mm² CU". Bill of quantities (B1) p.11
  • Single-lines: "CFW PowerCable Typ TN-C/PUR 4x4x185mm²"; C5 6.2 calls for EMC-optimised LV cables "wie CFW". EMSRL concept (C5) p.24
Why it matters Four 4-core cables or sixteen single cores, and two named products. "Or equal" is allowed, so it is mainly a price and termination question. Question 21 ↓
Minor errors in the documents (no cost impact)
  • The TS 01 single-line labels its LV points "NS02:01" and "NS02:02"; the supply overview and layout 4001 call them NS01:01 and NS01:02. Single-line TS 01 · LV board
  • Layout 4001 labels the TS 02 transformer "Tr01:01" and its reserve space "Tr01.02"; the single-line and overview say Tr02:01. Layout TS 01 / TS 02 · TS 02 transformer
  • Layout 4001 is dated 07.09.2026 (last revised 07.09.2026), while the single-lines, overview, and layout 4002 carry revision 08.10.2026. This older TS 01 / TS 02 layout may explain the Tr01 label error. Layout TS 01 / TS 02 · Title block
  • The protection concept draft uses the same title and number "8500004-12-5000" as the supply overview, so the two sheets cannot be distinguished in a drawing list. Protection concept draft · Title block
  • Teil B page 17 still contains the drafting note "noch Trafogrösse ergänzen" in the key-person reference form. Offer forms (Teil B) p.17
  • MS01:03: The small breaker label "25/10 plomb." has two overlapping digits, so its rating is unreadable. Single-line TS 01 · MS01:03

Points for the remarks and deviation list in your offer 22

The question window closed on 20.11.2026, so these points go into the offer: on the remarks page (Teil B chapter 8) and in the B3 deviation list. Check any answers the buyer publishes by 04.12.2026 first. Ordered by highest cost impact first. Each item has ready-to-paste German wording.

1Escalation methodTeil A 6.8.1, Teil B 5.3.1, and form B2 specify the SIA 122 price formula (KBOB, 20% fixed), while contract C1 3.5 has "PKI mit NPK-Kostenmodellen nach Norm SIA 123" checked. Under C1 18.2, order of precedence decides between contract documents, so the contract deed would prevail. Which method applies? We submit form B2 as required and ask the buyer to confirm SIA 122 per B2 or correct C1 3.5.
German wording for your offer

Teil A Ziff. 6.8.1, Teil B Ziff. 5.3.1 und Beilage B2 sehen die Gleitpreisformel nach SIA 122 (KBOB, nicht überwälzungsberechtigter Anteil 20 %) vor. Im Werkvertrag C1 Ziff. 3.5 ist jedoch «PKI mit NPK-Kostenmodellen nach Norm SIA 123» angekreuzt. Gemäss C1 Ziff. 18.2 gilt die Rangfolge der Vertragsbestandteile, womit die Vertragsurkunde vorginge. Welches Verfahren gilt? Wir reichen das Formular B2 wie verlangt ein und bitten um Bestätigung, dass die Teuerung nach SIA 122 gemäss B2 abgerechnet wird, bzw. um Korrektur von C1 Ziff. 3.5.

Contract (C1) p.6Conditions (Teil A) p.24Contract (C1) p.14
2CTs, VTs, and protection functionsC5 5.10 and 5.11 require 3 VTs and a summation CT in the station breaker, ring, and transformer panels; verified cores and a summation CT for the generator transformer; and ANSI 25, 27, 59, 59N, 51N, 32R, 67NIEF, and busbar protection. The single-lines and protection draft show VTs only on the busbars (and in MS01:01 and MS03:02), no summation CTs in MS01:04, MS01:06, MS02:02, MS02:03, and MS03:02, and fewer protection functions. We offer per the single-line and protection draft (B1 2.2, Teil A 7.3.2). Please confirm.
German wording for your offer

C5 Ziff. 5.10/5.11 verlangen im Stationsschalter sowie in Ring- und Trafofeldern je 3 Spannungswandler und einen Summenstromwandler, für Generatortransformatoren geeichte Kerne und einen Summenstromwandler sowie u. a. ANSI 25, 27, 59, 59N, 51N, 32R, 67NIEF und Sammelschienenschutz. Die Prinzipschemata und der Schutzkonzeptentwurf zeigen Spannungswandler nur an den Sammelschienen (bzw. MS01:01 und MS03:02), keine Summenstromwandler in MS01:04, MS01:06, MS02:02, MS02:03 und MS03:02 sowie reduzierte Schutzfunktionen. Wir offerieren gemäss Prinzipschema und Schutzkonzeptentwurf (LV Ziff. 2.2, Teil A Ziff. 7.3.2). Bitte bestätigen.

EMSRL concept (C5) p.21EMSRL concept (C5) p.22Protection concept draft · CT/VT dots
3Network control system (NLS)C5 chapter 7 describes an NLS control cabinet per switchgear with a redundant PLC, gateway, switches, and server, plus operator panels in TS 01 and TS 02. The bill has no item for this, and B1 4.6 and Teil A 7.3.6 assign the rack and process-control integration to the owner. We assume the NLS is not part of Lot 46 and our scope ends at the cabling to the racks. Please confirm.
German wording for your offer

C5 Kap. 7 beschreibt je MSA einen Steuerschrank NLS mit redundanter SPS, Gateway, Switches und Server sowie Bedienpanels in TS 01/TS 02. Das LV enthält dafür keine Position; gemäss LV Ziff. 4.6 und Teil A Ziff. 7.3.6 sind das Rack und die Einbindung in das Prozessleitsystem bauseits. Wir gehen davon aus, dass das NLS nicht Bestandteil von Los 46 ist und unser Leistungsumfang mit der Verkabelung bis zu den Racks endet. Bitte bestätigen.

EMSRL concept (C5) p.26Conditions (Teil A) p.30
4Warranty startTeil A 6.7 starts the warranty separately for each station upon its acceptance, while C1 18.2 starts notice and limitation periods upon acceptance of the entire works unless the contract expressly agrees otherwise. Teil A 6.9.1 (surety per stage) and 7.3.8 (acceptance per station) support a per-station start. We assume a per-station warranty start. Please confirm.
German wording for your offer

Gemäss Teil A Ziff. 6.7 beginnen die Garantiefristen je Trafostation separat mit deren Abnahme. Gemäss C1 Ziff. 18.2 beginnen die Rüge- und Verjährungsfristen mit der Abnahme des gesamten Werks, «sofern in diesem Werkvertrag nicht ausdrücklich etwas anderes vereinbart wurde». Teil A Ziff. 6.9.1 (Solidarbürgschaft je Etappe) und Ziff. 7.3.8 (Abnahme je Trafostation) stützen den Beginn je Station. Wir gehen von einem Fristbeginn je Trafostation aus. Bitte bestätigen.

Conditions (Teil A) p.24Contract (C1) p.16
5TS 03 LV disconnection pointBill item 7.4.1 describes two incoming/outgoing ways with a coupler for TS 03, while single-line 5101, the supply overview, layout 4002, and C5 5.16 ("Je Transformator ist ein Niederspannungs-Leistungsschalter") show one breaker NS03:01 with ZEP. We offer one breaker with ZEP. Please confirm.
German wording for your offer

LV Pos. 7.4.1 beschreibt für TS 03 zwei Einspeise-/Abgangswege mit Kopplung. Prinzipschema 5101, Energieversorgungsschema, Disposition 4002 und C5 Ziff. 5.16 («Je Transformator ist ein Niederspannungs-Leistungsschalter ...») zeigen hingegen nur NS03:01 mit einem Leistungsschalter und ZEP. Wir offerieren einen Leistungsschalter mit ZEP. Bitte bestätigen.

Bill of quantities (B1) p.22EMSRL concept (C5) p.23Single-line TS 03 · NS03:01
6Power-quality analyzersB1 2.1 lists "Anzahl: 4x" analyzers at the MS01:04 station breaker, while the TS 01 single-line shows one UMG in MS01:01. How many are required, and in which panels?
German wording for your offer

LV Ziff. 2.1 nennt «Anzahl: 4x» Netzqualitätsanalysatoren am Stationsschalter MS01:04; das Prinzipschema TS 01 zeigt ein UMG im Feld MS01:01. Bitte Anzahl und Einbauorte der Geräte angeben.

Bill of quantities (B1) p.4Single-line TS 01 · MS01:01
7Motor operationB1 2.1 requires a 48 VDC spring-charging motor in all panels and lists only MS01:04 under "Leistungsschalter Motorisiert", while the single-lines show a motor on every breaker. Are all breakers motor-operated for remote control? Should the load-break and earthing switches also be motorized?
German wording for your offer

LV Ziff. 2.1 verlangt einen Federaufzugmotor 48 VDC für alle Schaltfelder, nennt unter «Leistungsschalter Motorisiert» aber nur MS01:04. Die Prinzipschemata zeigen Motorantriebe an allen Leistungsschaltern. Sind alle Leistungsschalter fernsteuerbar mit Motorantrieb auszuführen, und sind auch die Lasttrennschalter/Erdtrenner zu motorisieren?

Bill of quantities (B1) p.4Bill of quantities (B1) p.4
8Utility metering transformersUnder C5 chapter 14, the SAK provides the metering, including CTs and VTs, while under Teil A 7.3.6 the metering CTs and VTs are to be built within our scope. Are the utility CTs and VTs in MS01:03 provided by the SAK? Who supplies the verified cores in MS03:02 and pays for their verification?
German wording for your offer

Gemäss C5 Kap. 14 stellt die SAK die Messeinrichtung inkl. Messwandler zur Verfügung; gemäss Teil A Ziff. 7.3.6 sind die Messwandler innerhalb unseres Lieferumfangs umzusetzen. Werden die EVU-Strom- und -Spannungswandler in MS01:03 von der SAK beigestellt? Wer liefert die amtlich geeichten Wandlerkerne in MS03:02 und trägt die Eichkosten?

EMSRL concept (C5) p.52Conditions (Teil A) p.31
9LV link TS 01 to TS 02The single-lines and supply overview show an LV link from NS01:02 to NS02:02 (CFW PowerCable 4x4x185 mm²). Teil A 7.3.6 assigns downstream LV cables from the disconnection points to the owner. Is this cable part of Lot 46, and if so, what is its length?
German wording for your offer

Die Prinzipschemata und das Energieversorgungsschema zeigen eine NS-Verbindung NS01:02–NS02:02 (CFW PowerCable 4x4x185 mm²). Gemäss Teil A Ziff. 7.3.6 sind die Kabelverbindungen ab den Niederspannungstrennstellen bauseits. Gehört dieses Kabel zu Los 46 (Länge?) oder ist es bauseits?

Supply overview (EVS) · LV linkConditions (Teil A) p.30
10Same switchgear type for TS 03C5 5.9 requires one MV switchgear type throughout. TS 03 is delivered from June 2033. Must TS 03 be the same type as TS 01 and TS 02, or is an equivalent successor type allowed?
German wording for your offer

C5 Ziff. 5.9 verlangt den Ausbau «mit einem Mittelspannungstyp». TS 03 wird ab Juni 2033 geliefert. Muss garantiert werden, dass TS 03 mit dem gleichen Typ wie TS 01/02 geliefert wird, oder ist ein gleichwertiger Nachfolgetyp zulässig?

EMSRL concept (C5) p.20Conditions (Teil A) p.17
11Second transformer provisionThe layouts show a "Reserveplatz" for a second 1000 kVA transformer in each station, and C5 requires changeover "Trafo 1 – Trafo 2 ohne Unterbruch ... je Station". Apart from the extendable busbar ends, must anything else be prepared now (reserve panel, space, secondary equipment)?
German wording for your offer

Die Dispositionen zeigen je Station einen «Reserveplatz» für einen zweiten Transformator 1000 kVA; C5 Ziff. 7.1.3 verlangt eine «Umschaltung Trafo 1 – Trafo 2 ohne Unterbruch mit Lastüberwachung je Station». Ist heute ausser der Erweiterbarkeit der Sammelschiene eine weitere Vorbereitung (Reservefeld, Platz, Sekundärtechnik) für den zweiten Transformator vorzusehen?

Layout TS 01 / TS 02 · ReserveplatzEMSRL concept (C5) p.28
12Surge arrestersC5 4.9 requires arresters at one end of each ring cable, while the single-lines show them at both ends and in reserve panel MS03:04. We will offer per the single-lines. Please confirm.
German wording for your offer

C5 Ziff. 4.9 verlangt Überspannungsableiter pro Ringleitung an einem Ende; die Prinzipschemata zeigen Ableiter an beiden Enden sowie im Reservefeld MS03:04. Wir offerieren gemäss Prinzipschema. Bitte bestätigen.

EMSRL concept (C5) p.18Single-line TS 03 · MS03:04
13Standby generator and Tr03:01C5 4.5 specifies the genset as LTP 850 / PRP 800 / COP 728 kVA, feeding through a 1.0 MVA transformer, while C5 3.3 and the supply overview specify 1.25 MVA or 1000 - 1250 kVA. We assume 1.0 MVA and Tr03:01 per B1 2.3. Please confirm and state whether Tr03:01 needs a different design for reverse feed.
German wording for your offer

Gemäss C5 Ziff. 4.5 hat die NEA die Leistungen LTP 850 kVA / PRP 800 kVA / COP 728 kVA und speist «über einen 1.0 MVA Transformator» ein. C5 Ziff. 3.3 nennt hingegen 1.25 MVA, das Energieversorgungsschema 1000–1250 kVA. Wir gehen von 1.0 MVA und Tr03:01 gemäss LV Ziff. 2.3 aus. Bitte bestätigen und angeben, ob Tr03:01 für die Rückspeisung abweichend auszulegen ist.

EMSRL concept (C5) p.17EMSRL concept (C5) p.10Supply overview (EVS) · NEA
14UPS sizingShould the 48 VDC UPS feed only the switchgear (B1 2.6), or also the network control system (C5 11.2)? What continuous load applies for the 2 h autonomy?
German wording for your offer

Soll die USV 48 VDC gemäss LV Ziff. 2.6 nur die MSA versorgen oder gemäss C5 Ziff. 11.2 auch das Netzleitsystem? Bitte die vorgesehene Dauerlast für die Autonomiezeit von 2 Stunden angeben.

Bill of quantities (B1) p.8EMSRL concept (C5) p.44
15Transformer dataB1 2.3 states "Verlustreduziert" without values; C5 5.14 specifies uk about 5% and a design for THDi 40%. Are the C5 values binding, and which minimum loss values apply? Losses are scored under ZK2.
German wording for your offer

LV Ziff. 2.3 nennt «Verlustreduziert» ohne Werte; C5 Ziff. 5.14 gibt «Kurzschlussspannung Uk ca. 5%» und «Auslegung für THDi 40%» an. Gelten diese Werte aus C5 verbindlich, und welche Verlustwerte sind mindestens einzuhalten?

Bill of quantities (B1) p.6EMSRL concept (C5) p.22
16MV cable loops inside TS 01The TS 01 single-line shows two XKDT-Y 3x1x95/25 mm² connections (MS01:02 to MS01:03 and MS01:03 to MS01:04). The bill lists only the switchgear-to-transformer cable (item 4.3.1, 15 m). Should these loops be included in item 4.1.1 or offered separately?
German wording for your offer

Das Prinzipschema TS 01 zeigt zwei MS-Kabelverbindungen XKDT-Y 3x1x95/25 mm² (MS01:02 zu MS01:03 und MS01:03 zu MS01:04). Das LV enthält nur die Verbindung Schaltanlage–Transformator (Pos. 4.3.1, 15 m). Sind diese Verbindungen in Pos. 4.1.1 einzurechnen oder separat zu offerieren?

Supply overview (EVS) · TS 01 loopsBill of quantities (B1) p.11
17SecuritiesTeil A 6.7 requires a joint surety, but no security is ticked in C1 5.1, and the mandatory forms required by C1 5.3 are missing from the package. Please provide the type, amount, and duration of the securities, along with the forms.
German wording for your offer

Teil A Ziff. 6.7 verlangt eine Solidarbürgschaft. In C1 Ziff. 5.1 ist jedoch keine Sicherheit angekreuzt, und die gemäss C1 Ziff. 5.3 zwingend zu verwendenden Formulare liegen nicht bei. Bitte Art, Höhe und Dauer der Sicherheiten angeben und die Formulare zur Verfügung stellen.

Conditions (Teil A) p.24Contract (C1) p.8
18Summation CT in MS02:03Panel MS02:03 has no summation CT on the single-line, while the protection draft requires ANSI 67N/32N there. Should a 60/1 A summation CT be provided on the mounting rail below the switchgear required by C5 6.1?
German wording for your offer

Das Feld MS02:03 hat im Prinzipschema keinen Summenstromwandler; der Schutzkonzeptentwurf fordert dort jedoch ANSI 67N/32N. Ist ein Summenstromwandler 60/1 A auf der gemäss C5 Ziff. 6.1 unterhalb der MSA anzubringenden Montageschiene vorzusehen?

Single-line TS 02 · MS02:03EMSRL concept (C5) p.24
19Grid dataPlease provide the short-circuit level at the handover point, the neutral earthing of the 20 kV grid, the SAK grid-connection rules for MV (C5 4.2), and the network calculation (C7 no. 1). They are not in the package.
German wording for your offer

Bitte die Kurzschlussleistung am Übergabepunkt, die Sternpunktbehandlung des 20-kV-Netzes, die «Netzanschlussbedingungen Mittelspannung SAK» (C5 Ziff. 4.2) und die Netzberechnung (C7 Nr. 1) zur Verfügung stellen; diese Unterlagen liegen nicht bei.

EMSRL concept (C5) p.13Test plan (C7) p.1
20TS 03 ring panel labelsSingle-line 5101 labels MS03:01 "TS 02 ARA" and MS03:03 "TS 01 ARA", while the supply overview, protection draft, layout 4002, and Teil A figure 2 reverse them. Please confirm the correct assignment.
German wording for your offer

Im Prinzipschema TS 03 (5101) sind MS03:01 mit «TS 02 ARA» und MS03:03 mit «TS 01 ARA» bezeichnet; im Energieversorgungsschema, im Schutzkonzeptentwurf, in der Disposition 4002 und in Teil A Abbildung 2 ist es umgekehrt. Bitte die richtige Zuordnung bestätigen.

Single-line TS 03 · Panel headersSupply overview (EVS) · TS 03 header
21LV cable typeB1 2.5 says "Purwil TrafoCable bandiert 4x4x185 mm²", item 4.3.2 says "vier Parallelsysteme mit je 4x1x185 mm²", and the single-lines say "CFW PowerCable 4x4x185mm²". Please confirm the cable type.
German wording for your offer

In LV Ziff. 2.5 ist «Purwil TrafoCable bandiert 4x4x185 mm²» aufgeführt, in Pos. 4.3.2 «vier Parallelsysteme mit je 4x1x185 mm²» und in den Schemata «CFW PowerCable 4x4x185mm²». Bitte bestätigen Sie den Kabeltyp.

Bill of quantities (B1) p.7Bill of quantities (B1) p.11
22Clerical pointsPlease confirm or correct: the TS 01 single-line labels its LV points NS02:01/NS02:02 (presumably NS01:01/NS01:02); layout 4001 labels the TS 02 transformer "Tr01:01" and its reserve "Tr01.02" (presumably Tr02:01/Tr02.02); the protection concept draft uses the supply overview number (8500004-12-5000) and needs its own; Teil B page 17 still has the note "noch Trafogrösse ergänzen". Is an extra field intended for the transformer size?
German wording for your offer

Bitte bestätigen bzw. korrigieren Sie folgende Punkte: Im Prinzipschema TS 01 (5103) sind die NS-Trennstellen als NS02:01/NS02:02 bezeichnet (vermutlich NS01:01/NS01:02). In der Disposition 4001-P02 sind der Transformator in TS 02 als «Tr01:01» und der Reserveplatz als «Tr01.02» bezeichnet (vermutlich Tr02:01/Tr02.02). Der Schutzkonzeptentwurf trägt Titel und Nummer des Energieversorgungsschemas (8500004-12-5000) und benötigt eine eigene Plannummer. Zudem enthält Teil B, Seite 17, den Vermerk «noch Trafogrösse ergänzen»: Ist ein zusätzliches Feld für die Trafogrösse vorgesehen?

Single-line TS 01 · LV boardLayout TS 01 / TS 02 · TS 02 transformerProtection concept draft · Title blockOffer forms (Teil B) p.17

Requirements to meet

32 · 9 to clarify
RequirementStatusNotePage
Submit an electronically signed offer via SIMAP, plus 1 paper copy, by 15.01.2027, 12:00 CET. Valid for 6 months; payment 45 days in CHF; no cash discount.RequiredConditions (Teil A) p.5
Variants are allowed only with a complete base offer; no partial offers; no joint ventures; name subcontractors with the offer.RequiredConditions (Teil A) p.7
Award criteria: price 50%, offer quality 35% (including guaranteed transformer losses), bidder quality 15%; price band 50%. No cost shifting between positions.RequiredConditions (Teil A) p.14
Suitability: liability insurance of at least CHF 10 million; average turnover of at least CHF 2 million; 2 references of at least CHF 500,000 each for a complete station including MV switchgear, transformer, and MV ring cables in ducts.RequiredConditions (Teil A) p.10
State guaranteed transformer no-load and load losses; they are scored.RequiredOffer forms (Teil B) p.14
Schedule: contract May 2027; TS 01/02 delivery and installation April 2029; West ready for commissioning March 2030; TS 03 June 2033; East February 2034.RequiredConditions (Teil A) p.17
Escalation: SIA 122 formula with 20% fixed; form B2 is mandatory with the offer.To clarifySIA 123 PKI is selected in the contract; by rank, it likely prevails unless clarified.Conditions (Teil A) p.24
Contract precedence: rank decides between contract components, with the contract deed first. The higher requirement prevails only within a single component containing multiple documents. Unit prices remain fixed regardless of quantity changes (SIA 118 Art. 86 waived).RequiredCorrected reading of C1 18.2.Contract (C1) p.14
Warranty per SIA 118 with a joint surety; periods start for each station upon acceptance.To clarifyThe contract starts them upon acceptance of the entire works unless expressly agreed otherwise.Conditions (Teil A) p.24
Securities: a joint surety is required, but no box is checked in the contract and the forms are missing.To clarifyAsk for type, amount, and duration.Contract (C1) p.8
Liquidated damages: the contract table is blank.To clarifyNot stated in the package.Contract (C1) p.9
Delivery prices include packing, customs, transport, insurance, unloading, placing, and all cranes. A crane swinging over the motorway needs an ASTRA acceptance record.RequiredConditions (Teil A) p.24
State missing items or errors in the bill with the offer; declare ambiguous items, or the site manager's reading is binding.RequiredWindow closed: use the remarks page and the B3 list.Conditions (Teil A) p.22
MV switchgear: 24 kV / 20 kV, 50 Hz; 630 A busbar and feeders; IAC AFLR 20 kA 1 s; LSC 2 / PM; metering panel at least LSC 1.RequiredBill of quantities (B1) p.3
SF6-free insulation and switching medium. C5 also specifies gas-insulated, hermetically sealed, about 200 kg per panel.To clarifyCheck against your SF6-free range.Bill of quantities (B1) p.3
Indoor up to 1000 m, -5 to +40 °C; IP4X outside, IP3X between compartments; extendable, with end panels prepared.RequiredBill of quantities (B1) p.3
48 VDC auxiliary supply; 48 VDC spring-charging motor in all panels; local/remote switch; all auxiliary contacts on terminals; IEC 61850.RequiredBill of quantities (B1) p.4
Digital relays with at least 20 BI and 10 BO each; IEC 61850 over RJ45 to the owner's rack, plus point-to-point fibre for directional comparison; USB service port.RequiredBill of quantities (B1) p.5
The bidder completes the plant-specific protection concept, settings, and network protection tests with the grid operator.RequiredConditions (Teil A) p.28
Type-tested switchgear to IEC 62271-100 and -200; Starkstromverordnung, IEC 62271, IEC 61869, IEC 61439.RequiredBill of quantities (B1) p.3
Every switching panel is drawn as a breaker plus a separate load-break switch with an earthing switch.To clarifyEquivalent alternative configurations are allowed; state a three-position disconnector design in the offer.Bill of quantities (B1) p.3
One MV switchgear type across all stations (C5).To clarifyTS 03 follows in 2033.EMSRL concept (C5) p.20
Three transformers: 1000 kVA, 20 kV, taps 22.2 to 19.8 kV, 3x420/240 V, Dyn5, Cu/Cu, hermetic, synthetic ester, KNAN.RequiredBill of quantities (B1) p.6
LV disconnection points: at least 1500 A and 63 kA peak; TN-C in, TN-S out; one ZEP per station.RequiredBill of quantities (B1) p.7
48 VDC UPS per station, 2 h autonomy at the planned continuous load, with monitoring to the process-control system.To clarifyLoad not given; see the UPS point.Bill of quantities (B1) p.8
MV cables: XKDT-Y / XKDT-YT 3x1x95/25 mm² Cu; ring lengths 20 m, 140 m, and 110 m; no cable ties.RequiredBill of quantities (B1) p.7
Tests per the inspection and test plan (21 checks), with costs included in the unit prices; earthing measurement per SNG 483755.RequiredTest plan (C7) p.1
Documentation in German per station: 2 printed copies and 1 digital copy (searchable PDF plus native files).RequiredConditions (Teil A) p.32
Technical enclosures with the offer (B3), including a list of all deviations or an explicit statement that there are none.RequiredEnclosures list (B3) p.1
Product-neutral tender: equal products and equal alternative switchgear configurations are allowed.RequiredBill of quantities (B1) p.3
Power-quality analyser "z.B. Janiza UMG 512-Pro", per IEC 61000-4-30.To clarifyExample only; quantity and location are unclear.Bill of quantities (B1) p.4
Transformer fluid "MIDEL 7131 oder gleichwertig"; LV cable "Purwil TrafoCable" or equal; "CFW PowerCable" shown on the drawings.RequiredBill of quantities (B1) p.6

Not in the package