Mavlon Bid review
BID REVIEW · 23 NOVEMBER 2026

Axpo Grid: 24 kV MV switchgear for substations Grynau and Linthal

Ausschreibung für die Beschaffung einer 24-kV-MS-Schaltanlage für das UW Grynau und das UW Linthal

Axpo Grid AG. Air-insulated 24 kV duplex switchgear: 13 panels for Grynau and 7 for Linthal. Tender documents are in German.

Offer due Fri 4 Dec 2026, 23:59 (simap.ch)Conditions (Teil 0) p.7Questions closed Fri 13 Nov 2026Conditions (Teil 0) p.7Award Price 50%, technical 40%, supplier 10%Conditions (Teil 0) p.12Scope Supply, installation supervision, commissioningConditions (Teil 0) p.6

Ten documents, three drawings, and a price sheet were read page by page. Both single-line diagrams were read directly from the drawings. Every point links to its source page. Click a page chip to see the wording on that page.

The question window has closed. Questions were due by 13.11.2026. The points below can now only go into the list of deviations and inconsistencies submitted with the offer. Anything not flagged there counts as accepted, and the bidder bears any extra cost. Technical deviations are not allowed in the base offer. Conditions (Teil 0) p.7Conditions (Teil 0) p.8Conditions (Teil 0) p.16Conditions (Teil 0) p.14
131
Pages read
21
Positions on the single-line
18
Where the documents disagree
19
Points for your offer
All 19 questions and 18 conflicts, with their pages, in one file.

What matters most for your price

  1. Pressure-relief duct: included in the base offer per the specification and data sheet, but listed as an option (2 pieces) in the price sheet and as 1 piece in the contract.Primary spec p.13Price sheet (Teil 3) p.1
  2. Unpriced options count as included in the total. All five option lines must be priced: duct, cable-type CTs, two training sessions, and complete installation.Conditions (Teil 0) p.14Conditions (Teil 0) p.5
  3. Axpo can bill the supplier if the Axpo fitter hours needed differ by more than 15% from the bidder's estimate in price sheet rows 5.1 and 5.2.Contract (Teil 1) p.9Price sheet (Teil 3) p.1
  4. Secondary installation and commissioning are in the supplier's scope, but the price sheet has no line for them, and the data sheet says Axpo performs the on-site function check.Conditions (Teil 0) p.6Data sheet Grynau p.11
  5. Grynau single-line, panel Q10: the first breaker is drawn connected to the second busbar, unlike every other panel. Flag it as a drawing error.Single-line Grynau · Q10

What this bid covers

Supplied by the bidder
  • Design, manufacture, testing, and delivery (including unloading) of air-insulated MV switchgear for both substations, plus installation supervision and commissioning. Conditions (Teil 0) p.6
  • Grynau: 13-panel 24 kV switchgear. Linthal: 7-panel 24 kV switchgear. Double busbar, back-to-back (duplex). Primary spec p.5
  • Secondary installation and commissioning, offered in 2 variants. Conditions (Teil 0) p.6
  • Pressure-relief duct out of the building, with outlet grille and installation. For Linthal, add a right-angle bend and 4 m of length. Primary spec p.13
  • All wiring inside and between the panels. Primary spec p.14
  • On-site training. Primary spec p.17
By others or not stated
  • Axpo provides the staff for primary installation. Complete installation by the bidder is an option. Conditions (Teil 0) p.6
  • Axpo supplies the protection and control devices (Siprotec 5 7SX85), the main and check meters (eRS301), and the power-quality devices. Secondary spec p.17
  • Not in this tender: station control level and auxiliary supply. Secondary spec p.4
  • Raised floor with mounting rails, earthing material, fibre cables, and AC/DC infeed are by Axpo. Primary spec p.13
Rated voltage24 kV, run at 16 kVp.11Grynau busbar2500 A, 25 kA / 3 sp.11Linthal busbar2000 A, 25 kA / 3 sp.11ArrangementDuplex, double busbarp.5Arc ratingIAC AFLR 25 kA 3 sp.7NetworkResonant-earthedp.6

Single-line diagram, read from the image Axpo 101470 · Axpo 102056

Grynau single-line, Axpo 101470, rev 0, 13.07.2026. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.

Matches the other documentsSomething to checkNot in this bidShown below
Single-line diagram

Switchgear, position by position

Grynau, 13 panels

#PositionEquipment on the drawingFeedsChecksWhere it is written
Q01Q01 · Reserve SAK ALine feeder: 2 × 1250 A breakers, CTs 800/5 (×2) + 800/1, VT set, earthing switch, arrester, cable-type CTNo cable size on the drawing3 same2 to checkDrawing · Q01
Q02Q02 · Grynau PumpwerkLine feeder: 2 × 1250 A breakers, CTs 800/5 (×2) + 800/1, VT set, earthing switch, arrester, cable-type CT2x3x(1x400 mm²) Alu4 same1 to checkDrawing · Q02
Q03Q03 · Eigenbedarf BAuxiliary feeder: 2 × 1250 A breakers, 400/1 CTs (metering and relay), VT set, earthing switch, arresterStation transformer -TA71, 400 kVA3 same2 to checkDrawing · Q03
Q04Q04 · Transformator 12Transformer feeder: 2 × 2000 A breakers, 1500/1 CTs (metering and relay), VT set, earthing switch, arrester-TA12, 40 MVA, cable 3x3x(1x400 mm²) Cu2 same5 to checkDrawing · Q04
Q05Q05 · SS KressizopfLine feeder: 2 × 1250 A breakers, CTs 800/5 (×2) + 800/1, VT set, earthing switch, arrester, cable-type CT2x3x(1x400 mm²) Alu4 same1 to checkDrawing · Q05
Q06Q06 · Uznach PumpwerkLine feeder: 2 × 1250 A breakers, CTs 800/5 (×2) + 800/1, VT set, earthing switch, arrester, cable-type CT2x3x(1x400 mm²) Alu4 same1 to checkDrawing · Q06
Q07Q07 · Eigenbedarf AAuxiliary feeder: 2 × 1250 A breakers, 400/1 CTs (metering and relay), VT set, earthing switch, arresterStation transformer -TA72, 400 kVA3 same2 to checkDrawing · Q07
Q08Q08 · Transformator 11Transformer feeder: 2 × 2000 A breakers, 1500/1 CTs (metering and relay), VT set, earthing switch, arrester-TA11, 40 MVA, cable 3x3x(1x400 mm²) Cu2 same5 to checkDrawing · Q08
Q09Q09 · EschenbachLine feeder: 2 × 1250 A breakers, CTs 800/5 (×2) + 800/1, VT set, earthing switch, arrester, cable-type CT2x3x(1x400 mm²) Alu4 same1 to checkDrawing · Q09
Q10Q10 · BenkenLine feeder: 2 × 1250 A breakers, CTs 800/5 (×2) + 800/1, VT set, earthing switch, arrester, cable-type CT1x3x(1x240 mm²) Cu3 same3 to checkDrawing · Q10
Q11Q11 · UznachLine feeder: 2 × 1250 A breakers, CTs 800/5 (×2) + 800/1, VT set, earthing switch, arrester, cable-type CT2x3x(1x400 mm²) Alu4 same1 to checkDrawing · Q11
Q12Q12 · AuholzLine feeder: 2 × 1250 A breakers, CTs 800/5 (×2) + 800/1, VT set, earthing switch, arrester, cable-type CT2x3x(1x400 mm²) Alu4 same1 to checkDrawing · Q12
Q13Q13 · Reserve SAK BLine feeder: 2 × 1250 A breakers, CTs 800/5 (×2) + 800/1, VT set, earthing switch, arrester, cable-type CTNo cable size on the drawing3 same2 to checkDrawing · Q13

Linthal, 7 panels

#PositionEquipment on the drawingFeedsChecksWhere it is written
Q01Q01 · Eigenbedarf AAuxiliary feeder: 2 × 1250 A breakers, 400/1 CTs, VT set, earthing switch, arrester1x1x(3x95mm2) Al1 same3 to checkDrawing · Q01
Q02Q02 · Trafo 11Transformer feeder: 2 × 1250 A breakers, 1000/1 CTs, VT set, earthing switch, arrester2x1x(3x300mm2) Cu1 same3 to checkDrawing · Q02
Q03Q03 · TS-14 MattLine feeder: 2 × 1250 A breakers, CTs 800/5 (×2) + 800/1, VT set, earthing switch, arrester, cable-type CT1x1x(3x240mm2) Al3 to checkDrawing · Q03
Q04Q04 · Eigenbedarf BAuxiliary feeder: 2 × 1250 A breakers, 400/1 CTs, VT set, earthing switch, arrester1x1x(3x95mm2) Al1 same2 to checkDrawing · Q04
Q05Q05 · Trafo 12Transformer feeder: 2 × 1250 A breakers, 1000/1 CTs, VT set, earthing switch, arrester2x3x(1x400mm2) Cu4 to checkDrawing · Q05
Q06Q06 · ReserveLine feeder (reserve): 2 × 1250 A breakers, 800/5 (×2) + 800/1 CTs, VT set, earthing switch, arrester, cable-type CTNo cable size on the drawing4 to checkDrawing · Q06
Q07Q07 · TS-51 HofLine feeder: 2 × 1250 A breakers, CTs 800/5 (×2) + 800/1, VT set, earthing switch, arrester, cable-type CT1x1x(3x240mm2) Al3 to checkDrawing · Q07
Q08Q08 · (label only)Nothing drawn; "Nicht ausgebaut"-1 sameDrawing · Q08

Where the documents disagree 18

Biggest cost impact first. Each item shows both sides and their page numbers.

1Pressure-relief duct: base offer or option, and 2 pieces or 1?High cost
One document says
  • Primary spec: a pressure-relief duct out of the building must be offered, including the outlet grille and its installation. Primary spec p.13
  • Data sheet: the duct "muss im Angebot enthalten sein", with "in jedem Fall" (in every case) ticked. Data sheet Grynau p.1
  • The Grynau layout shows the duct. Layout Grynau
Another says
  • Price sheet: "Druckentlastungskanal inklusive Klappen" under optional items, quantity 2. Price sheet (Teil 3) p.1
  • Contract price table: duct as an option, quantity 1. Contract (Teil 1) p.10
Why it matters If a required item is priced as an option, base prices are not comparable, and 2 versus 1 changes the price. Unpriced options count as included in the total. For Linthal, the duct also needs a bend and 4 m of length, with no Linthal layout to design it from. Conditions (Teil 0) p.14Primary spec p.13Question 1 ↓
2Secondary installation and commissioning: in scope, but no price lineHigh cost
One document says
  • Conditions: secondary installation and commissioning are done by the supplier. Conditions (Teil 0) p.6
  • Primary spec: planning, execution, and management of primary and secondary commissioning are the supplier's responsibility. Primary spec p.17
Another says
  • Price sheet: only installation supervision (2.1) and primary commissioning (2.2). No line for secondary work. Price sheet (Teil 3) p.1
  • Data sheet: the function check of all devices is "Ausführung durch den Besteller" (done by Axpo). Data sheet Grynau p.11
Why it matters Secondary commissioning of 20 duplex panels is a large labour item. The "2 variants" requested in the conditions most likely mean Axpo fitters (price sheet rows 5.1 and 5.2) or complete installation by the bidder (option 3.5); secondary work still has no separate line. Primary spec p.17Question 2 ↓
3Surge arresters: supplied by the bidder or by Axpo?Cost
One document says
  • Data sheet 1.2.7: delivery "Anbieter" (bidder) is ticked. Data sheet Grynau p.7 · item 1.2.7
  • Primary spec: all outgoing panels have surge arresters. Both single-lines show -FA1 in every panel. Primary spec p.9
Another says
  • Data sheet 1.2.8 (also ticked): Axpo supplies and fits arresters and earthing disconnectors for cable-sheath earthing. Data sheet Grynau p.7
  • Primary spec: cable compartments must allow arresters to be fitted, which reads as space only. Primary spec p.14
Why it matters 20 panels × 3 arresters = 60 arresters plus mounting. On the data sheet, fitting "pro Phase bei den Endverschlüssen" is also ticked, which suggests item 1.2.8 covers only the sheath-earthing devices. This is worth one line in the offer. Data sheet Grynau p.7Question 3 ↓
4Transformer feeder metering core: 5 VA or 1-15 VA?Design
One document says
  • Primary spec: 1500 / 1 A (Grynau) and 1000 / 1 A (Linthal), 5 VA. Primary spec p.11
Another says
  • Single-lines: 1500A / 1A and 1000/1A, 1-15VA. Single-line Grynau · Q04
Why it matters The data sheet refers to the specification for CT data, so its x/5 A values do not apply and 1 A is settled. Only the burden differs. FS5 is printed on Grynau Q07, but not on Q03. Data sheet Grynau p.4Question 4 ↓
5Cable-type CTs: all panels or line feeders only?Cost
One document says
  • Price sheet and contract: cable-type CTs "in allen Feldern" (in all panels) per the single-line. Price sheet (Teil 3) p.1
Another says
  • Single-lines: -BC91 on line feeders only (9 in Grynau, 3 in Linthal). Single-line Grynau
  • Primary spec and data sheet: cable-type CTs in the line feeder. Data sheet Grynau p.5
Why it matters 12 versus 20 CT sets in the option price. The words "gemäss einpoligem Schema" (per the single-line) point to 12. Question 5 ↓
6Grynau Q10 cable: 2 runs or 1?Design
One document says
  • Primary spec table: "Leitungsfeld Q10 2x 3x (1x240 mm2)". Primary spec p.14
Another says
  • Single-line: "1x3x(1x240 mm²) Cu". Single-line Grynau · Q10
Why it matters This affects the number of terminations and arresters in the cable compartment. The specification table is marked "voraussichtlich" (provisional). Question 6 ↓
7Linthal Q05 cable: three-core or single-core?Design
One document says
  • Primary spec table: "Transformatorfeld Q05 2x 1x (3x400 mm2)". Primary spec p.14
Another says
  • Single-line: "2x3x(1x400mm2) Cu". Single-line Linthal · Q05
Why it matters Two three-core cables need different terminations and space than six single-core cables. The specification table is marked provisional. Question 6 ↓
8Grynau Q10: first breaker drawn connected to the second busbarDrawing
One document says
  • Single-line, Q10 Benken: the -QA1 riser has a junction dot on -WA1 and a break between the two busbars. Single-line Grynau · Q10
Another says
  • Every other panel, such as Q09, shows a plain crossing with no dot. Single-line Grynau · Q09
Why it matters As drawn, either QA1 is on the wrong busbar or the two busbars are tied. This is almost certainly a drawing error, but it should be on the deviation list. Question 10 ↓
9Warranty: from provisional acceptance or from entering service?Cost
One document says
  • Contract: 2 years from provisional acceptance. Contract (Teil 1) p.18
Another says
  • Data sheet: 24 months from entering service, at most 36 months from ready-to-ship. Data sheet Grynau p.12
Why it matters The contract takes precedence over the data sheet, so 2 years from provisional acceptance applies. One line in the offer settles it. Question 16 ↓
10Panel interlocking: in hardware or in the protection device?Design
One document says
  • Secondary spec: panel interlocks are implemented in the control and protection device, together with electrical interlocks. Secondary spec p.8
Another says
  • Data sheet (ticked): internal panel interlocking is done in hardware. Data sheet Grynau p.8
Why it matters This changes the wiring and auxiliary contacts in every panel. Question 8 ↓
11Extension by two panels per side in a room with about 1 m to spareDesign
One document says
  • Primary spec: the switchgear must be easy to extend later by two panels on each side. Primary spec p.7
  • Data sheet: extension "beidseitig" (both sides) is ticked. Data sheet Grynau p.3
Another says
  • Grynau layout: only 990 mm and 1004 mm between the end panels and the walls, and the duct is at the Q01 end. Layout Grynau
Why it matters Two 800 mm panels per side do not fit in the room as drawn. It is not stated whether "extendable" means designed for extension or keeping space free. Question 9 ↓
12Linthal supply concept written for Grynau panelsDesign
One document says
  • Secondary spec: one 230 VAC infeed each on panels =Q01 and =Q13 (same for 110 VDC A and B). Secondary spec p.9
Another says
  • Linthal has panels Q01 to Q07 only. Single-line Linthal
Why it matters The Linthal infeed panels are not defined. Question 11 ↓
13Training: base offer or option?Cost
One document says
  • Conditions list training in the scope; the primary spec and contract require it. Conditions (Teil 0) p.6
  • Contract: the supplier agrees to carry out training. Contract (Teil 1) p.17
Another says
  • Price sheet: installation training (3.3) and operating staff training (3.4) are optional items. Price sheet (Teil 3) p.1
Why it matters Unpriced options count as included in the total. Question 17 ↓
14Power-quality devices: two panels, or four panels with 2 each?Design
One document says
  • Secondary spec text: devices are currently planned for "zweit Felder" (two panels). Secondary spec p.18
Another says
  • Same page: Grynau Q04 and Q08, and Linthal Q02 and Q05 (four panels). Table: 2 per panel in Grynau, 1 in Linthal. Secondary spec p.16 · Panel table
Why it matters Space and wiring for the free-issue devices. Question 14 ↓
15References: identical type, or as close as possible?Eligibility
One document says
  • Conditions: references should come as close as possible to the offered design. Conditions (Teil 0) p.11
Another says
  • Company form: "Identischer Anlagentyp gemäss dieser Ausschreibung" (identical switchgear type). Company form (Teil 5) p.9
Why it matters Determines which reference projects qualify. Question 18 ↓
16Trip-coil voltage toleranceDesign
One document says
  • Primary spec: 110 VDC +10 / -30 %. Primary spec p.6
Another says
  • Data sheet: 110 VDC +15% / -30%. Data sheet Grynau p.2
Why it matters Small, but it is a declared rating. Question 15 ↓
17Control wiring size and test socketsDesign
One document says
  • Secondary spec: control and signal circuits 1.5 mm²; CT terminals with test sockets on both sides, VT terminals on one side. Secondary spec p.6
Another says
  • Data sheet: control circuits at least 1.0 mm²; CT and VT terminals with test sockets on both sides. Data sheet Grynau p.10
Why it matters Small, but it changes the wiring standard. Question 15 ↓
18Relay-core class: "Kl.1 5P20" or "5P20"?Design
One document says
  • Primary spec and Grynau line feeders: "30 VA; Kl.1 5P20". Primary spec p.11
Another says
  • Data sheet, Linthal single-line and Grynau transformer feeders: "30VA 5P20". Data sheet Grynau p.5 · CT data
Why it matters Small, but it is in the CT order. Question 15 ↓
Minor errors in the documents (no cost impact)
  • Incoterms: the conditions and contract say DDP Incoterms 2020; the data sheet says "Incoterms 2010". Data sheet Grynau p.11
  • Price sheet: the options subtotal formula adds only item 3.1 and leaves out 3.2 to 3.5. The "**" footnote on delivery times has no text. Price sheet (Teil 3) p.1
  • The company form asks for an installation concept for "Unterwerk Beznau", the wrong substation. Company form (Teil 5) p.15
  • The company form offers a joint venture option, but joint ventures are not allowed. Conditions (Teil 0) p.14
  • Data sheet item 2.6 stops mid-sentence: "Es gelten die". Data sheet Grynau p.12
  • The secondary spec refers to section 8.1.2, which does not exist. Secondary spec p.7
  • The station name is spelled "SS Kressizopf" on the single-line and "SS Kressinzopf" on the layout. Layout Grynau

Points for the deviation list in your offer 19

The question window closed on 13.11.2026, so these points go into the list required by the conditions with the offer. Largest cost impact first. Each includes ready-to-paste German wording.

1Pressure-relief ductThe duct is base scope in the primary spec (7.1) and data sheet (1.1.3, "in jedem Fall"), but an option in the price sheet (3.1, 2 pieces) and the contract (1 piece). Should it be priced in the base offer or as an option, and how many per substation, including the Linthal bend and 4 m?
German wording for your offer

Gemäss Teil 2 (Primärtechnik 7.1; Datenblatt 1.1.3 «in jedem Fall») ist der Druckentlastungskanal im Grundangebot enthalten, in Teil 3 jedoch als Option 3.1 (2 Stück) und im Werkvertrag 7.3/7.4 als Option (1 Stück) aufgeführt. Ist der Kanal (inkl. Klappen, Auslassgitter sowie für Linthal Winkel und 4 m Länge) im Grundpreis oder als Option zu offerieren und in welcher Stückzahl pro Anlage?

Primary spec p.13Price sheet (Teil 3) p.1
2Secondary installation and commissioningTeil 0, 6.2 assigns secondary installation and commissioning to the supplier and asks for 2 variants "per Teil 3". We read the variants as Axpo fitters (rows 5.1 and 5.2) or complete installation (option 3.5). Where should secondary installation and commissioning be priced? Who performs the on-site function check? Data sheet 2.2.4 says Axpo, while primary spec chapter 10 says the supplier.
German wording for your offer

Teil 0, Ziffer 6.2, weist Sekundärmontage und Inbetriebsetzung dem Lieferanten zu und verlangt «2 Varianten (gemäss Teil 3)». Wir verstehen die Varianten als Beistellung von Axpo-Monteuren (Pos. 5.1/5.2) oder Gesamtmontage (Option 3.5). In welcher Position sind Sekundärmontage und Inbetriebsetzung zu bepreisen? Wer führt die Funktionskontrolle vor Ort durch (Datenblatt 2.2.4 «Ausführung durch den Besteller» gegenüber Primärtechnik Kap. 10)?

Conditions (Teil 0) p.6Data sheet Grynau p.11
3Surge arrestersData sheet 1.2.7 "Lieferung: Anbieter" and 1.2.8 "bauseits geliefert und montiert" are both ticked. Are the -FA1 arresters in all outgoing panels supplied and fitted by the bidder? Does 1.2.8 cover only the cable-sheath earthing devices?
German wording for your offer

Im Datenblatt sind sowohl 1.2.7 «Lieferung: Anbieter» als auch 1.2.8 «... werden bauseits geliefert und montiert» angekreuzt. Sind die Ableiter -FA1 (Uc 19 kV bzw. 19.2 kV laut Schema) in allen Abgangsfeldern vom Anbieter zu liefern und zu montieren? Bezieht sich 1.2.8 nur auf die Ableiter und Erdungstrenner der Kabelmantelerdung?

Data sheet Grynau p.7
4Metering-core burdenWe use the CT data from the specification, as data sheet page 4 directs (x/1 A). For the transformer feeders (Grynau 1500 A, Linthal 1000 A), the specification gives 5 VA and the single-lines give 1-15 VA. Which applies? FS5 is shown on Grynau Q07 but not on Q03. Is FS5 required on both?
German wording for your offer

Wir übernehmen die Wandlerdaten gemäss Datenblatt Seite 4 aus der technischen Spezifikation (x/1 A). Für die Transformatorfelder (Grynau 1500 A, Linthal 1000 A) nennt die Spezifikation 5 VA, das Schema 1-15 VA. Welche Bürde gilt? FS5 ist im Schema Grynau bei Q07, nicht aber bei Q03 angegeben: Gilt FS5 für beide?

Primary spec p.11Data sheet Grynau p.4
5Cable-type CTsDoes option 3.2 apply "in allen Feldern" (all panels) or only to the line feeders shown on the single-lines (Grynau 9, Linthal 3)?
German wording for your offer

Gilt Option 3.2 «in allen Feldern» oder nur für die Leitungsfelder gemäss Schema (Grynau 9, Linthal 3)?

Price sheet (Teil 3) p.1
6Cable sizesGrynau Q10: specification "2x 3x (1x240 mm2)", single-line "1x3x(1x240 mm²) Cu". Linthal Q05: specification "2x 1x (3x400 mm2)", single-line "2x3x(1x400mm2) Cu". Which apply? The single-lines give no cable for reserve panels Grynau Q01, Q13, and Linthal Q06. Do the specification values apply?
German wording for your offer

Grynau Q10: Spezifikation 7.2 «2x 3x (1x240 mm2)», Schema «1x3x(1x240 mm²) Cu». Linthal Q05: Spezifikation «2x 1x (3x400 mm2)», Schema «2x3x(1x400mm2) Cu». Welche Angaben gelten? Für die Reservefelder Grynau Q01, Q13 und Linthal Q06 ist im Schema kein Kabel angegeben; gelten die Werte der Spezifikation 7.2?

Primary spec p.14Single-line Grynau · Q10Single-line Linthal · Q05
7Cable terminations, GrynauGrynau data sheet 1.2.8 marks a minimum of "3 x 500 mm2" terminations per phase, while the single-line and specification show at most 3x(1x400 mm²). Is 3 x 500 mm² per phase required in every panel or only in the transformer feeders?
German wording for your offer

Im Datenblatt Grynau 1.2.8 ist «Minimale Anzahl Endverschlüsse pro Phase und Querschnitt: 3 x 500 mm2» angekreuzt, während Schema und Spezifikation maximal 3x(1x400 mm²) zeigen. Ist 3 x 500 mm² pro Phase in allen Feldern oder nur in den Transformatorfeldern vorzusehen?

Data sheet Grynau p.7
8InterlockingSecondary spec 3.4 puts panel interlocks in the control and protection device. Data sheet 1.3.4 states that interlocking inside the panel is "hardwaremässig" (in hardware). Which applies?
German wording for your offer

Sekundärspezifikation 3.4: Feldverriegelungen im Steuer-/Schutzgerät; Datenblatt 1.3.4: feldinterne Verriegelung «hardwaremässig». Welche Ausführung gilt?

Secondary spec p.8Data sheet Grynau p.8
9ExtensionPrimary spec 4.3 requires extension by two panels on each side. Layout Axpo 100358 leaves only 990 mm and 1004 mm to the walls. Is a design for extension enough, or must space be kept in the room?
German wording for your offer

Primärtechnik 4.3 verlangt die Erweiterbarkeit um zwei Felder auf jeder Seite. Im Layout Axpo 100358 bleiben nur 990 mm bzw. 1004 mm bis zur Wand. Genügt die konstruktive Erweiterbarkeit, oder ist Platz im Raum vorzusehen?

Primary spec p.7Layout Grynau
10Grynau Q10 busbar connectionOn the Grynau single-line, the -QA1 riser of Q10 Benken has a junction dot on -WA1 and a break between the busbars, unlike all other panels. We assume this is a drawing error and offer Q10 like the other line feeders, with QA1 on WA2 and QA2 on WA1. Please confirm.
German wording for your offer

Im Schema Grynau weist die Abzweigung von -QA1 im Feld Q10 Benken – anders als in allen übrigen Feldern – einen Verbindungspunkt auf -WA1 und eine Unterbrechung zwischen den Sammelschienen auf. Wir gehen von einem Zeichnungsfehler aus und offerieren Q10 wie die übrigen Leitungsfelder (QA1 an WA2, QA2 an WA1). Bitte bestätigen.

Single-line Grynau · Q10
11Linthal infeedsThe infeeds are defined on "=Q01 and =Q13". Which Linthal panels receive the 230 VAC and 110 VDC A/B infeeds?
German wording for your offer

Die Einspeisungen sind auf «=Q01 und =Q13» definiert. Auf welche Felder erfolgen die Einspeisungen 230 VAC und 110 VDC A/B in Linthal?

Secondary spec p.9
12Indicating instrumentsData sheet 1.3.2 requires "Strom in Phase L2" and a voltmeter with a 7-position switch in the transformer feeders, while secondary spec 3.1 puts local operation only in the control and protection device. Are separate analog instruments required? What is meant by busbar voltage metering panels, since none appear on the single-line?
German wording for your offer

Datenblatt 1.3.2 verlangt im Transformatorfeld «Strom in Phase L2» und «Spannung L1-L2-L3 mit 7-st. Voltmeterumschalter». Die Sekundärspezifikation 3.1 sieht die Vor-Ort-Bedienung ausschliesslich über das Steuer-/Schutzgerät vor. Sind separate analoge Instrumente zu liefern? Was ist mit «SS-Spannungsmessfelder» gemeint, da im Schema kein solches Feld vorhanden ist?

Data sheet Grynau p.8
13Crane and accessData sheet 2.3 marks an unloading crane on site as "ja" with no capacity given, and 2.4 marks a crane for installation as "nein". What capacity is available? Does layout Axpo 100358 (door 2235 mm) also apply to Linthal? There is no Linthal layout.
German wording for your offer

Datenblatt 2.3: «Kran zum Abladen bauseits vorhanden: ja (Tragkraft: ___ kg)» ohne Angabe; 2.4: Kran zur Montage «nein». Welche Tragkraft steht zur Verfügung, und gilt das Layout Axpo 100358 (Türe 2235 mm) auch für Linthal? Für Linthal liegt kein Layout vor.

Data sheet Grynau p.11Layout Grynau
14Power-quality devicesHow many power-quality devices are required per transformer panel? The table on page 16 shows 2 each in Grynau, while the text in 8.4 says "two panels".
German wording for your offer

Wie viele Netzqualitätsgeräte pro Transformatorfeld sind vorzusehen (Tabelle S. 16: Grynau je 2; Text 8.4: «zwei Felder»)?

Secondary spec p.18Secondary spec p.16 · Panel table
15Minor technical pointsPlease confirm: are trip coils 110 VDC +10/-30 % or +15/-30 %? Is control wiring at least 1.5 mm² (secondary spec) or 1.0 mm² (data sheet)? Are VT terminal test sockets on one side or both? Are relay cores "Kl.1 5P20" or "5P20"?
German wording for your offer

Bitte klären bzw. bestätigen: Ausschaltspulen 110 VDC +10/-30 % oder +15/-30 %? Steuerleitungen mindestens 1.5 mm² (Sekundärspezifikation) statt 1.0 mm² (Datenblatt)? Prüfbuchsen an Spannungswandlerklemmen ein- oder beidseitig? Relaiskerne «Kl.1 5P20» oder «5P20»?

Primary spec p.6Data sheet Grynau p.2Secondary spec p.6
16WarrantyDoes the warranty follow contract 17.1 (2 years from provisional acceptance) or data sheet 2.7 (24 months from entering service, up to 36 months from ready-to-ship)?
German wording for your offer

Gilt die Garantiedauer gemäss Werkvertrag 17.1 (2 Jahre ab provisorischer Abnahme) oder gemäss Datenblatt 2.7 (24 Monate ab Netzbetrieb, max. 36 Monate ab Versandbereitschaft)?

Contract (Teil 1) p.18Data sheet Grynau p.12
17TrainingIs training part of the base offer (Teil 0, 6.2; contract 13) or an option (Teil 3, 3.3 and 3.4)?
German wording for your offer

Sind die Schulungen Teil des Grundangebots (Teil 0, 6.2; Werkvertrag 13) oder Optionen (Teil 3, 3.3/3.4)?

Conditions (Teil 0) p.6Price sheet (Teil 3) p.1
18ReferencesTeil 0 asks for references as close as possible to the offered design; Teil 5 asks for an "identical switchgear type". Which rule applies?
German wording for your offer

Teil 0 verlangt Referenzen, die der angebotenen Anlage möglichst nahekommen; Teil 5 verlangt: «Identischer Anlagentyp». Welche Anforderung gilt?

Conditions (Teil 0) p.11Company form (Teil 5) p.9
19Clerical pointsPlease confirm: Incoterms 2020 apply, not 2010; the Teil 3 options subtotal should sum all options 3.1 to 3.5, and the price sheet has no grand total cell; Teil 5 chapter 7 refers to Grynau and Linthal, not Beznau; joint ventures are not allowed; data sheet 2.6 "Es gelten die ..." is incomplete.
German wording for your offer

Bitte bestätigen: Incoterms 2020 (nicht 2010); Formel F14 in Teil 3 soll alle Optionen 3.1–3.5 summieren, und das Preisblatt enthält keine Gesamtsumme; Teil 5, Kap. 7, bezieht sich auf UW Grynau/Linthal (nicht Beznau); eine ARGE ist nicht zulässig (Teil 0, 28); Datenblatt 2.6 «Es gelten die ...» ist unvollständig.

Data sheet Grynau p.11Company form (Teil 5) p.15Data sheet Grynau p.12

Requirements to meet

19 · 7 to clarify
RequirementStatusNotePage
Submit the offer on simap.ch by 04.12.2026, 23:59. Valid for 120 days.RequiredConditions (Teil 0) p.13
No technical deviations in the base offer. Submit deviations only in a separate contractor variant.RequiredKey rule: flag every inconsistency in the offer list.Conditions (Teil 0) p.14
Unpriced options and deviations count as included in the total price.To clarifyPrice every option, including the duct and training.Conditions (Teil 0) p.14
Joint ventures are not allowed.RequiredConditions (Teil 0) p.14
Options must be offered: an option is defined as extra work the bidder must offer.RequiredConditions (Teil 0) p.5
State the earliest possible delivery date and its latest order date in the cover letter. Guaranteed delivery time is scored.RequiredConditions (Teil 0) p.16
Estimate Axpo fitters and hours (price sheet rows 5.1 and 5.2). Axpo may bill the supplier for deviations over 15%.To clarifyEstimate carefully: it carries a charge-back.Contract (Teil 1) p.9
Award criteria: price 50%, technical 40%, supplier 10%.RequiredConditions (Teil 0) p.12
Must-haves: 24 kV rated; Grynau busbar 2500 A, Linthal busbar 2000 A; 25 kA / 3 s; duplex; type-tested.RequiredConditions (Teil 0) p.11
Delay penalty: 2% per started week, doubling from week 4, capped at 15%.To clarifyHigher than the general purchase terms (1% per full week, max 10%); the contract takes precedence.Contract (Teil 1) p.16
FAT and ready to ship: Grynau 15.01.2028, Linthal 15.01.2029.RequiredContract (Teil 1) p.8
Warranty: 2 years from provisional acceptance.To clarifyThe data sheet says otherwise.Contract (Teil 1) p.18
IAC AFLR 25 kA 3 s, with two separate cable compartments per duplex panel.To clarifyCheck that your type-test certificate covers this exact design.Primary spec p.7
Class 0.2 metering cores calibrated by a lab accredited to IEC 17025, witnessed by Axpo.RequiredPrimary spec p.10
Seismic qualification to IEC 62271-210, severity 1.RequiredData sheet Grynau p.1
VT ferroresonance protection: VT Guard Pro or technically equal.RequiredPrimary spec p.12
Terminals: Phoenix Contact types specified; other types only by agreement.To clarifyNamed product without an "or equal".Secondary spec p.5
VT protection breaker: Siemens 3RV1611-1DG14.To clarifyNamed product without an "or equal".Secondary spec p.7
Protection and control: Siprotec 5 7SX85, free issue from Axpo.RequiredSecondary spec p.17

Not in the package