Upgrade of Kophinou 132 kV AIS to GIS substation and supply of ancillary/additional equipment
Electricity Authority of Cyprus, tender 390/2026. A 13-bay 145 kV double-busbar GIS with 4 optional bays, its protection, substation automation, and auxiliaries, plus supply-only transformers and remote-end relays. Tender documents are in English.
Eleven documents and 35 drawing sheets, 672 pages in total. The tender, price schedules, and forms were read in full. In the 367-page specification, the switchgear chapters were read in full and the rest was searched by keyword. The drawings have no text layer, so every label was read from the image. Every point links to its source page: click a chip to see the wording on the page.
132 kV single-line diagram TK37/185, sheet 1 of 3, June 2026, no revision letter. The sheet is drawn sideways and shown upright here. Red is new, green is optional, and blue is by others. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.
132 kV single-line diagram TK37/185, sheet 2 of 3: bus couplers, bus sections, and transformer bay E10. Shown upright. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.
132 kV single-line diagram TK37/185, sheet 3 of 3. Shown upright. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.

| # | Position | Equipment on the drawing | Feeds | Checks | Where it is written |
|---|---|---|---|---|---|
| E01 | E01 · Optional | Cable feeder 2500 A; CT 2500/1 with 6 cores; VT (option, Form 11A D5) | Future HVDC link, 2x3-1/C 1200 mm² Cu XLPE | 3 same4 to check | Drawing · E01 |
| E02 | E02 · Optional | Cable feeder 2500 A; CT 2500/1 with 6 cores; VT (option, Form 11A D5) | Future HVDC link, 2x3-1/C 1200 mm² Cu XLPE | 3 same4 to check | Drawing · E02 |
| E03 | E03 · Alambra 1 | Cable feeder 2500 A: breaker, 2 busbar disconnectors, line disconnector, 3 earth switches, high-speed earth switch, CT 2000-2500/1 (4 cores), VT | Alambra 1 overhead line, 2x3-1/C 1200 mm² Cu XLPE to an outdoor sealing end | 2 same5 to check | Drawing · E03 |
| E04 | E04 · Spare | Cable feeder 2500 A, same as the line feeders; CT 2000-2500/1 with 6 cores | None: ends at the GIS cable sealing end chamber | 1 same5 to check | Drawing · E04 |
| E05 | E05 · Mari 1 | Cable feeder 2500 A: breaker, 2 busbar disconnectors, line disconnector, 3 earth switches, high-speed earth switch, CT 2000-2500/1 (4 cores), VT | Mari 1 overhead line, 2x3-1/C 1200 mm² Cu XLPE to an outdoor sealing end | 2 same5 to check | Drawing · E05 |
| E06 | E06 · Transformer No1 | Transformer feeder 800 A: breaker, 2 busbar disconnectors, 2 earth switches and a high-speed earth switch, CT 300/1 (3 cores) | Existing ABB 31.5 MVA 132/11 kV transformer TA1, 3-1/C 300 mm² Cu XLPE | 1 same3 to check | Drawing · E06 |
| # | Position | Equipment on the drawing | Feeds | Checks | Where it is written |
|---|---|---|---|---|---|
| E07 | E07 · Bus coupler 1 | Bus coupler 3150 A: breaker, 2 busbar disconnectors, 2 earth switches, CTs 3150/1 | Couples WA11/WA21 or WA12/WA22 | 1 same2 to check | Drawing · E07 |
| E08 | E08 · Bus section WA21–WA22 | Bus section 3150 A: breaker, 2 disconnectors, 2 earth switches, CTs 3150/1 | Links WA21–WA22 | 1 same3 to check | Drawing · E08 |
| E09 | E09 · Bus section WA11–WA12 | Bus section 3150 A: breaker, 2 disconnectors, 2 earth switches, CTs 3150/1 | Links WA11–WA12 | 1 same3 to check | Drawing · E09 |
| E10 | E10 · Transformer No2 | Transformer feeder 800 A: breaker, 2 busbar disconnectors, 2 earth switches and a high-speed earth switch, CT 300/1 (3 cores) | Existing ABB 31.5 MVA 132/11 kV transformer TA2, 3-1/C 300 mm² Cu XLPE | 1 same4 to check | Drawing · E10 |
| E11 | E11 · Bus coupler 2 | Bus coupler 3150 A: breaker, 2 busbar disconnectors, 2 earth switches, CTs 3150/1 | Couples WA11/WA21 or WA12/WA22 | 1 same3 to check | Drawing · E11 |
| # | Position | Equipment on the drawing | Feeds | Checks | Where it is written |
|---|---|---|---|---|---|
| E12 | E12 · Alambra 2 | Cable feeder 2500 A: breaker, 2 busbar disconnectors, line disconnector, 3 earth switches, high-speed earth switch, CT 2000-2500/1 (4 cores), VT | Alambra 2 overhead line, 2x3-1/C 1200 mm² Cu XLPE to an outdoor sealing end | 2 same5 to check | Drawing · E12 |
| E13 | E13 · Spare | Cable feeder 2500 A, same as the line feeders; CT 2000-2500/1 with 6 cores | None: ends at the GIS cable sealing end chamber | 1 same5 to check | Drawing · E13 |
| E14 | E14 · Transformer No3 | Transformer feeder 800 A: breaker, 2 busbar disconnectors, 2 earth switches and a high-speed earth switch, CT 300/1 (3 cores) | Future 63 MVA transformer (by the Purchaser); termination only | 1 same4 to check | Drawing · E14 |
| E15 | E15 · Mari 2 | Cable feeder 2500 A: breaker, 2 busbar disconnectors, line disconnector, 3 earth switches, high-speed earth switch, CT 2000-2500/1 (4 cores), VT | Mari 2 overhead line, 2x3-1/C 1200 mm² Cu XLPE to an outdoor sealing end | 2 same5 to check | Drawing · E15 |
| E16 | E16 · Optional | Cable feeder 2500 A; CT 2500/1 with 6 cores; VT (option, Form 11A D5) | Future HVDC link, 2x3-1/C 1200 mm² Cu XLPE | 3 same4 to check | Drawing · E16 |
| E17 | E17 · Optional | Cable feeder 2500 A; CT 2500/1 with 6 cores; VT (option, Form 11A D5) | Future HVDC link, 2x3-1/C 1200 mm² Cu XLPE | 3 same4 to check | Drawing · E17 |
Biggest cost impact first. Each item shows both sides and their page numbers.
Ready to send. Biggest cost impact first.
| Requirement | Status | Note | Page |
|---|---|---|---|
| Submit the offer through the Cyprus eProcurement system by 13 January 2027, 14:00. Validity is 4 months. Questions are due by 03.01.2027; answers by 07.01.2027. | Required | Tender (Part A, B, Annex II) p.9 | |
| Tender guarantee is EUR 200,000, valid for one month beyond tender validity. | Required | Tender (Part A, B, Annex II) p.9 | |
| Tenders for part of the scope are not accepted. | Required | Tender (Part A, B, Annex II) p.22 | |
| Tenders with terms contrary to the tender documents may be rejected. | To clarify | Any departure from spec 5.7.1 for a Category A offer must be listed in Form 21. | Tender (Part A, B, Annex II) p.10 |
| Any price omitted from the financial form is deemed included in the other prices. | To clarify | Watch for items with no Form 11A line: transformer cables and AVR panel. | Tender (Part A, B, Annex II) p.27 |
| Tick one GWP category per form set (Form 20). Offers in several categories need a full set of forms for each. Evaluation factors: 0.75 / 0.85 / 1.00. | Required | Form 20 variants p.1 | |
| Performance guarantee: 10% of the contract price. | Required | Tender (Part A, B, Annex II) p.32 | |
| 20% advance payment against an advance payment guarantee. | Required | Tender (Part A, B, Annex II) p.39 | |
| Delay penalty: 0.2% of the contract value per week. The buyer may terminate when penalties reach 5%. | Required | Tender (Part A, B, Annex II) p.42 | |
| Liability is capped at the contract price. | Required | Tender (Part A, B, Annex II) p.51 | |
| Defects liability is 12 months in Part B. | To clarify | Annex II and Form 11A say 24 months. | Tender (Part A, B, Annex II) p.49 |
| Average annual turnover of at least EUR 20 million. | Required | Tender (Part A, B, Annex II) p.16 | |
| Tenderer: at least 5 turnkey GIS transmission substations completed in 2015-2025, including 2 automated. | To clarify | Favours EPC partners or local contractors. | Tender (Part A, B, Annex II) p.17 |
| GIS manufacturer: 10 years of 132 kV GIS experience (3 indoor), 10 GIS sold abroad in 2015-2025, and 3 years of satisfactory service for the proposed equipment at 3 utilities. | To clarify | Hard for new eco-gas platforms. | Form 8A-1 p.1 |
| Entities and products from Turkey may not participate. Famagusta, Kyrenia and Karavostasi are prohibited ports. | Required | Tender (Part A, B, Annex II) p.14 | |
| Programme: civil foundation drawings by month 1, final data by month 5, site erection in month 14, first circuit energised in month 20, and transformers delivered in month 14. Site access may slip by 3 months. | Required | Form 10 programme p.1 | |
| 145 kV double-busbar GIS, 3150 A busbars, 650 kV / 275 kV insulation, and 110 V DC control. | Required | SLD TK37/185 sh.1 | |
| Aluminium enclosures. | To clarify | Excludes steel-enclosure designs. | Spec 14-019 p.68 |
| Gas loss must not exceed 1.0% per year per compartment, with at least 15 years between gas treatments and no auxiliary gas heating. | To clarify | Check the 15-year interval and the no-heating rule at -5 °C for alternative gas mixtures. | Spec 14-019 p.71 |
| Breaker: at least 3 years of commercial service for the type and rating; two separate trip coils; spring recharge within 30 s. | Required | Spec 14-019 p.75 | |
| Breaker cable-charging breaking current: at least 160 A, restrike-free. | Required | Spec 14-019 p.75 | |
| Fault clearance within 100 ms; two main protections plus one backup per 132 kV feeder. | Required | Spec 14-019 p.166 | |
| Site conditions: -5 °C to 50 °C, 100% humidity. Seismic: modified Mercalli 8, importance factor 1.4. | Required | Spec 14-019 p.22 | |
| Type tests from a recognized testing body such as KEMA or CESI; T100a reports for the derating curve (Form 9A). | Required | Tender (Part A, B, Annex II) p.27 | |
| Site AC withstand test on all HV circuits; one-month reliability run before takeover. | Required | Spec 14-019 p.286 | |
| Fixed GIS hall, 29.6 m by 10 m, for 17 bays; spare space on the drawings must not be reduced. | To clarify | Wide 2500 A double-busbar bays may not fit. | Spec 14-019 p.66 |
| Protection IEDs: ABB, Siemens, GE-Alstom, or Schneider Electric only. | To clarify | Closed list; no "or equal". | Spec 14-019 p.161 |
| SAS, RTU, and HMI: the same four makers. | To clarify | Closed list. | Spec 14-019 p.118 |
| Voltage-regulating relays: Maschinenfabrik Reinhausen, Eberle, or ABB. | Required | Closed list. | Spec 14-019 p.139 |
| Gas analyzer: Dilo 3-038R-R302 V0 "or similar". | Required | Spec 14-019 p.301 | |
| Relay test set: Omicron CMC 500 with P0008404 pack. | Required | Named product; no alternate. | Tender (Part A, B, Annex II) p.78 |
| Moisture-in-oil kits: Vaisala INDIGO80 with MMP8, 4 sets. | Required | Named product; no alternate. | Form 11A price schedules p.20 |
Want a review like this for a bid you are pricing? Book a call.
Excel sheet
All 29 questions and 19 conflicts, each with its document, page and exact words. Ready to paste into your clarification list.