Upgrade of Kophinou 132 kV AIS to GIS substation and supply of ancillary/additional equipment

Electricity Authority of Cyprus, tender 390/2026. A 13-bay 145 kV double-busbar GIS with 4 optional bays, its protection, substation automation, and auxiliaries, plus supply-only transformers and remote-end relays. Tender documents are in English.

Offer due Wed 13 Jan 2027, 14:00Tender (Part A, B, Annex II) p.9Questions open until Sun 3 Jan 2027Tender (Part A, B, Annex II) p.8Estimated value EUR 26.11 million excl. VATTender (Part A, B, Annex II) p.8Contract Turnkey, except civil worksTender (Part A, B, Annex II) p.76

Eleven documents and 35 drawing sheets, 672 pages in total. The tender, price schedules, and forms were read in full. In the 367-page specification, the switchgear chapters were read in full and the rest was searched by keyword. The drawings have no text layer, so every label was read from the image. Every point links to its source page: click a chip to see the wording on the page.

672
Pages read
17
Positions on the single-line
19
Where the documents disagree
29
Questions for the buyer
All 29 questions and 19 conflicts, with their pages, in one file.

What matters most for your price

  1. Short-circuit rating: the single-line and Form 9A state 40 kA for 1 s, while the specification gives 50 kA for 1 s for Kofinou at 132 kV. 40 kA and 50 kA 145 kV GIS are often different platforms.SLD TK37/185 sh.1 · ratingsSpec 14-019 p.17
  2. Breaker technology: the tender prefers switchgear with a GWP below 1, but specification clause 5.7.1 calls for SF6 puffer breakers. The specification allows an alternative gas elsewhere, so the conflict is in the interrupter clause, the SF6-only gas-handling clause, and some SF6-only form lines.Spec 14-019 p.75Tender (Part A, B, Annex II) p.20
  3. Warranty: Part B gives 12 months, while Annex II and the Form 11A spares schedules price 24 months. The Agreement ranks above Annex II, which points to 12.Tender (Part A, B, Annex II) p.38Tender (Part A, B, Annex II) p.76
  4. Who supplies the 132 kV cables and terminations to the two existing transformers? Annex II says the Contractor, the specification says the Purchaser, the drawings show them as by others, and Form 11A has no line for them.Tender (Part A, B, Annex II) p.79Spec 14-019 p.364
  5. Feeder bay rating: 2500 A on the single-line and in the price schedules, but 2000 A on protection drawing TK37-242 sheet 1.SLD TK37/185 sh.1 · ratingsProtection TK37-242 sh.1

What this bid covers

Supplied by the bidder
  • A 13-bay 132 kV GIS in a new building: two busbars, two bus couplers, a bus section on each busbar, three transformer feeders, and six cable feeders with pre-installed female cable terminations. Tender (Part A, B, Annex II) p.76
  • Temporary connection of the two existing 31.5 MVA transformers with outdoor cable terminations and fittings on their air bushings. Tender (Part A, B, Annex II) p.76
  • Surge arresters and steel support structures for the cable terminations of the four overhead lines (Alambra 1 and 2, Mari 1 and 2), excluding the terminations. Tender (Part A, B, Annex II) p.76
  • Substation automation system with a local HMI and an RTU for SCADA, fully installed and set up. Tender (Part A, B, Annex II) p.77
  • Control and protection for all GIS bays, with all auxiliary and communication cables. Tender (Part A, B, Annex II) p.77
  • DC system (batteries, charger, 110 V and 48 V DC boards) and a new LV AC board, including the cable to the old AC board. Tender (Part A, B, Annex II) p.77
  • Option: four more GIS double-chamber cable feeders for the HVDC link to Crete, including their protection and SAS extension. Tender (Part A, B, Annex II) p.77
  • Supply only: remote-end relays for Mari and Alambra, two 40 MVA and three 63 MVA transformers, five earthing transformers, chargers, batteries, LV AC boards, a relay test set, and steel structures. Tender (Part A, B, Annex II) p.78
  • Training at the works for about 4 EAC engineers and IEC 61850 training for up to 8 people. Tender (Part A, B, Annex II) p.78
By others or not stated
  • Civil works: the building, foundations, and cable trenches are under other contracts. The price must cover any layout change needed to fit them. Tender (Part A, B, Annex II) p.81
  • Line cables, conductors, and fibre between Kophinou and the remote substations. Tender (Part A, B, Annex II) p.79
  • Communications and network control equipment, including the multiplexer panel. Tender (Part A, B, Annex II) p.79
  • Installing the remote-end relays in the existing cabinets: by the Purchaser. Tender (Part A, B, Annex II) p.80
  • Fire alarm and fire-fighting panels: by others. Control cables to them are in the contract. Tender (Part A, B, Annex II) p.80
  • Main and check meters on the optional cable bays: supplied by EAC. Protection TK37-242 sh.2
  • Existing to remain: the two ABB 31.5 MVA transformers and the 22-11 kV Siemens NX-PLUS board. Overall SLD TK37-243
Rated voltage145 kV, 50 Hzp.1Insulation650 kV impulse, 275 kV power frequencyp.1BusbarDouble, 3150 Ap.1Short circuit40 kA 1 s on the drawing; 50 kA in the specp.1Bay currentsCouplers 3150 A, feeders 2500 A, transformers 800 Ap.1Control and motors110 V DC; ambient -5 to 50 °Cp.1

Single-line diagram, read from the image TK37/185 sh.1 · TK37/185 sh.2 · TK37/185 sh.3

132 kV single-line diagram TK37/185, sheet 1 of 3, June 2026, no revision letter. The sheet is drawn sideways and shown upright here. Red is new, green is optional, and blue is by others. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.

Matches the other documentsSomething to checkNot in this bidShown below
Single-line diagram

Switchgear, position by position

Sheet 1: E01 to E06

#PositionEquipment on the drawingFeedsChecksWhere it is written
E01E01 · OptionalCable feeder 2500 A; CT 2500/1 with 6 cores; VT (option, Form 11A D5)Future HVDC link, 2x3-1/C 1200 mm² Cu XLPE3 same4 to checkDrawing · E01
E02E02 · OptionalCable feeder 2500 A; CT 2500/1 with 6 cores; VT (option, Form 11A D5)Future HVDC link, 2x3-1/C 1200 mm² Cu XLPE3 same4 to checkDrawing · E02
E03E03 · Alambra 1Cable feeder 2500 A: breaker, 2 busbar disconnectors, line disconnector, 3 earth switches, high-speed earth switch, CT 2000-2500/1 (4 cores), VTAlambra 1 overhead line, 2x3-1/C 1200 mm² Cu XLPE to an outdoor sealing end2 same5 to checkDrawing · E03
E04E04 · SpareCable feeder 2500 A, same as the line feeders; CT 2000-2500/1 with 6 coresNone: ends at the GIS cable sealing end chamber1 same5 to checkDrawing · E04
E05E05 · Mari 1Cable feeder 2500 A: breaker, 2 busbar disconnectors, line disconnector, 3 earth switches, high-speed earth switch, CT 2000-2500/1 (4 cores), VTMari 1 overhead line, 2x3-1/C 1200 mm² Cu XLPE to an outdoor sealing end2 same5 to checkDrawing · E05
E06E06 · Transformer No1Transformer feeder 800 A: breaker, 2 busbar disconnectors, 2 earth switches and a high-speed earth switch, CT 300/1 (3 cores)Existing ABB 31.5 MVA 132/11 kV transformer TA1, 3-1/C 300 mm² Cu XLPE1 same3 to checkDrawing · E06

Sheet 2: E07 to E11

#PositionEquipment on the drawingFeedsChecksWhere it is written
E07E07 · Bus coupler 1Bus coupler 3150 A: breaker, 2 busbar disconnectors, 2 earth switches, CTs 3150/1Couples WA11/WA21 or WA12/WA221 same2 to checkDrawing · E07
E08E08 · Bus section WA21–WA22Bus section 3150 A: breaker, 2 disconnectors, 2 earth switches, CTs 3150/1Links WA21–WA221 same3 to checkDrawing · E08
E09E09 · Bus section WA11–WA12Bus section 3150 A: breaker, 2 disconnectors, 2 earth switches, CTs 3150/1Links WA11–WA121 same3 to checkDrawing · E09
E10E10 · Transformer No2Transformer feeder 800 A: breaker, 2 busbar disconnectors, 2 earth switches and a high-speed earth switch, CT 300/1 (3 cores)Existing ABB 31.5 MVA 132/11 kV transformer TA2, 3-1/C 300 mm² Cu XLPE1 same4 to checkDrawing · E10
E11E11 · Bus coupler 2Bus coupler 3150 A: breaker, 2 busbar disconnectors, 2 earth switches, CTs 3150/1Couples WA11/WA21 or WA12/WA221 same3 to checkDrawing · E11

Sheet 3: E12 to E17

#PositionEquipment on the drawingFeedsChecksWhere it is written
E12E12 · Alambra 2Cable feeder 2500 A: breaker, 2 busbar disconnectors, line disconnector, 3 earth switches, high-speed earth switch, CT 2000-2500/1 (4 cores), VTAlambra 2 overhead line, 2x3-1/C 1200 mm² Cu XLPE to an outdoor sealing end2 same5 to checkDrawing · E12
E13E13 · SpareCable feeder 2500 A, same as the line feeders; CT 2000-2500/1 with 6 coresNone: ends at the GIS cable sealing end chamber1 same5 to checkDrawing · E13
E14E14 · Transformer No3Transformer feeder 800 A: breaker, 2 busbar disconnectors, 2 earth switches and a high-speed earth switch, CT 300/1 (3 cores)Future 63 MVA transformer (by the Purchaser); termination only1 same4 to checkDrawing · E14
E15E15 · Mari 2Cable feeder 2500 A: breaker, 2 busbar disconnectors, line disconnector, 3 earth switches, high-speed earth switch, CT 2000-2500/1 (4 cores), VTMari 2 overhead line, 2x3-1/C 1200 mm² Cu XLPE to an outdoor sealing end2 same5 to checkDrawing · E15
E16E16 · OptionalCable feeder 2500 A; CT 2500/1 with 6 cores; VT (option, Form 11A D5)Future HVDC link, 2x3-1/C 1200 mm² Cu XLPE3 same4 to checkDrawing · E16
E17E17 · OptionalCable feeder 2500 A; CT 2500/1 with 6 cores; VT (option, Form 11A D5)Future HVDC link, 2x3-1/C 1200 mm² Cu XLPE3 same4 to checkDrawing · E17

Where the documents disagree 19

Biggest cost impact first. Each item shows both sides and their page numbers.

1Short-circuit rating: 40 kA or 50 kA?High cost
One document says
  • Single-line TK37/185, ratings table on all three sheets: short-time withstand 40 kA 1 s, breaking 40 kA. SLD TK37/185 sh.1 · ratings
  • Form 9A derating table: required Isc 40 kA. Form 9A p.1
Another says
  • Spec 3.1.2, row 9: 50 kA for 1 s for Mari and Kofinou at 132 kV. Spec 14-019 p.17
  • Spec 18.2.1(a): the GIS breaker takes its short-circuit rating from clause 3.1.2. Spec 14-019 p.298
Why it matters 40 kA and 50 kA 145 kV GIS often use different platforms or enclosure sizes. The rating also sets the CTs, earth switches, and earthing design. Annex II, which includes the specification, outranks everything except the Agreement, so 50 kA may prevail. Nothing in the package settles this. Tender (Part A, B, Annex II) p.37Question 1 ↓
2Breaker technology: SF6 puffer breaker in the spec, GWP below 1 preferred in the tenderHigh cost
One document says
  • Spec 5.7.1: SF6 circuit breakers with self-generating gas pressure, "e.g., puffer type". Spec 14-019 p.75
  • Spec 5.17: the mobile gas-handling unit covers SF6 only. Form 9 asks for the SF6 leakage rate, and its spares schedule C is headed "132 kV SF6 GIS". Form 9 particulars p.143
Another says
  • Part A 7.4(b): the buyer prefers switchgear with a GWP below 1. Category A, B, or C offers are scored with factors 0.75, 0.85, and 1.00. Tender (Part A, B, Annex II) p.20
  • Part A 7.4(d): an alternative gas must meet "the minimum specifications laid down in Annex II". No such minimum specification exists for 132 kV. Tender (Part A, B, Annex II) p.20
Why it matters The opposite case is strong. The specification's chapter 5 title, clause 5.1, 18.2.1, and 18.2.4 all allow "SF6 ... /Or alternative environmentally ECO-friendly gas". Every Form 9 GIS schedule has a GWP category line, and the Form 11A summary is headed "(SF6/ALTERNATIVE GAS)". So the conflict is narrower: a vacuum or non-puffer interrupter departs from 5.7.1, 5.17, and the SF6-only Form 9 lines. A departure listed in Form 21 risks rejection. Spec 14-019 p.66Spec 14-019 p.298Form 11A price schedules p.1Question 2 ↓
3Warranty and maintenance: 12 months or 24 months?High cost
One document says
  • Part B 2.2 and 2.3: maintenance and guarantee for twelve (12) months from taking-over. Tender (Part A, B, Annex II) p.38
  • Part B Article 35.1: the Defects Liability Period is twelve (12) months. Tender (Part A, B, Annex II) p.49
Another says
  • Annex II 1.1.1: maintenance for twenty four (24) months. Tender (Part A, B, Annex II) p.76
  • Form 11A schedules B3 and B4: spares for the warranty period of twenty four (24) months. Form 11A price schedules p.6
Why it matters This sets the warranty cost, spares, and the duration of the 10% performance bond. Conversely, Part B Article 1 ranks the Agreement above Annex II, pointing to 12 months, whereas Form 11A prices for 24. Tender (Part A, B, Annex II) p.37Question 3 ↓
4132 kV cables and terminations to the existing transformers: Contractor, Purchaser, or others?High cost
One document says
  • Annex II 1.1.1.1(c): supply of cable and terminations for the two existing transformers. Tender (Part A, B, Annex II) p.77
  • Annex II 1.2.1.1: the Contractor provides all 132 kV transformer power cables, terminations, and accessories. 1.2.1.5 states the same for all 132 kV and 22 kV power cables. Tender (Part A, B, Annex II) p.79
Another says
  • Spec 18.11.2(a): the Purchaser supplies all 132 kV cables within the substation, with design details given at award. Spec 14-019 p.364
  • Overall SLD TK37-243 and TK37-242 sheet 3: the 300 mm² cable and transformer-end termination are drawn in blue (by others). Overall SLD TK37-243
  • Form 11A D1 lists only "300 mm2 outdoor supports and supporting structures", 2 sets. There is no line for cable, terminations, or bushing adapters. Form 11A price schedules p.16
Why it matters Two 132 kV cable circuits with 6 outdoor and 6 GIS terminations are a material cost. Annex II states three times that the Contractor supplies them and ranks above the specification. Any omitted price is deemed included in the other prices. Tender (Part A, B, Annex II) p.27Question 4 ↓
5Feeder bay rating: 2500 A or 2000 A?Cost
One document says
  • TK37/185: QB1, QB2, and QA1 are marked "2500A"; the ratings table lists "Line/Cable Feeder 2500A". SLD TK37/185 sh.1 · ratings
  • Form 11A D1 and D5 list "GIS Cable Feeder Bay (2500A) with double cable chamber", 6 and 4 units. Form 11A price schedules p.15
Another says
  • TK37-242 sheet 1, for E03, E04, E05, E12, E13, and E15: QB1, QB2, and QA1 show "2000A". Protection TK37-242 sh.1
  • The Form 11A bay table also defines a "Cable Feeder Bay (2000A)" with no quantity listed anywhere. Form 11A price schedules p.13
Why it matters This changes the bay type and price. Both drawings give the same CT ratio, 2000-2500/1A. Question 5 ↓
6Feeder protection: which two main relays?Cost
One document says
  • Form 11A D1 prices feeder panels under item 18.7.1: a distance first main and a current differential second main. Spec 14-019 p.336
  • Form 11A D3: one distance/differential relay and one line differential relay per remote bay. Form 11A price schedules p.19
Another says
  • TK37-242 sheets 1 and 2: both main 1 and main 2 are "combined current, differential & distance relay" (87L, 21, 21N, 25, 79). Protection TK37-242 sh.1
  • Spec 18.7 Important Note: relays for opposite-end compatibility are shown in the protection drawings, and tenderers "should offer the specified relays". Spec 14-019 p.336
Why it matters The Important Note favors the drawing. However, that drawing labels these bays "O/H LINE BAY", and spec 9.4.1 requires distance first and current differential second for overhead lines, which 18.7.1 prices. Only the relay boxes on the drawing disagree. This changes the relay type and count at Kophinou and the remote ends. Protection TK37-242 sh.1Spec 14-019 p.166Question 6 ↓
7Remote-end relays: 4 bays or 6?Cost
One document says
  • Annex II 1.1.1.3: Mari, two bays; Alambra, two bays. Tender (Part A, B, Annex II) p.78
Another says
  • Form 11A D3: 6 + 6 relays for "Mari 1 & 2, Alambra 1 & 2, and Spare 1 & 2". Form 11A price schedules p.19
Why it matters No remote substation is named for spare bays E04 and E13. Question 7 ↓
863 MVA transformers: 132/23 kV or 132/23-11,5 kV?Cost
One document says
  • Annex II 1.1.1.4: three 63 MVA 132/23 kV transformers. Spec 18.4.1: 63 MVA 132/23kV, LV 22,8 kV. Tender (Part A, B, Annex II) p.78
Another says
  • Form 11A D2: "63MVA 132/23-11,5 kV Power Transformer". Form 11A price schedules p.18
Why it matters A dual-voltage LV winding changes the transformer design and price. Question 8 ↓
9Terminal points name E10 instead of E14Design
One document says
  • Annex II 1.2.1.1: "E10-TRANSFORMER No.2" ends at the GIS cable sealing end chamber. Tender (Part A, B, Annex II) p.79
Another says
  • Overall SLD TK37-243: E10 is cabled to the existing 31.5 MVA transformer TA2, which the Contractor must connect. Overall SLD TK37-243
  • The bay with nothing beyond its termination is E14 (Transformer No3), which TK37-243 labels "E13 TRFR No3". Overall SLD TK37-243
Why it matters This leaves the scope of the Transformer No2 cable connection unclear. Question 9 ↓
10Form 11A summary lists the wrong schedulesCost
One document says
  • Schedule E lists "Additional Equipment- Supply Only" from schedule D4 twice and has no row for D3 (the remote-end relays). Form 11A price schedules p.22
Another says
  • The optional bays row reads "FROM SCHEDULE D4", but the optional bays are in schedule D5. Form 11A price schedules p.22
Why it matters D3 is not carried to the Form 11 total, and it is not stated whether optional bays are included in the evaluated total. Question 10 ↓
11Feeder CT cores: 6 priced, 4 drawnCost
One document says
  • The Form 11A bay table cites CT item 18.3.9 for the cable feeder bays: per 18.3.7, six windings including two class 0,2S metering cores. Spec 14-019 p.302
Another says
  • TK37/185: 4 cores (PX, PX, 5P20, PX) on E03, E05, E12, and E15; 6 cores on the spare and optional bays. SLD TK37/185 sh.3 · E12
  • TK37-242 sheet 1: 4 cores for all six bays it covers. Protection TK37-242 sh.1
Why it matters Partial opposite case: 18.3.9 leaves the CT ratio "according to the relevant drawings", but not the number of cores. Question 11 ↓
12Medium-voltage switchboard: in the project text, not in the scope or priceScope
One document says
  • Annex II 1: the project includes "the medium voltage switchboard". Tender (Part A, B, Annex II) p.76
  • Form 9 has a 22 kV switchgear schedule (B15) and a 22/11 kV autotransformer schedule (B19). Form 9 particulars p.45
Another says
  • No MV board appears in the Annex II scope list or Form 11A; TK37-243 shows the 22-11 kV Siemens NX-PLUS board in black (existing). Overall SLD TK37-243
  • Annex II 1.1.1.1(c): the MV side of the transformers will remain unchanged. Tender (Part A, B, Annex II) p.77
Why it matters The opposite case points to no MV board, but Annex II 1.2.1.5 assigns "All 132 kV and 22 kV power cables" to the Contractor, leaving MV cabling open. Tender (Part A, B, Annex II) p.80Question 14 ↓
13Gas-handling equipment: required, or only for an eco-gas offer?Cost
One document says
  • Spec 18.2.4 calls for a gas-handling trolley for "SF6 gas/Or alternative environmentally friendly gas", a Dilo analyser or similar, and portable gas alarms. Spec 5.17 calls for an SF6 unit. Spec 14-019 p.301
Another says
  • Form 11A D1: "APPLIES ONLY FOR ECO FRIENDLY GAS SUPPLY EQUIPMENT", 1 unit, local work N/A. Form 11A price schedules p.15
Why it matters For an SF6 (Category C) offer, it is unclear whether this equipment is required. Question 15 ↓
14Sealing-end structures: by the Contractor or by others?Cost
One document says
  • Layout TK37/138 legend: structures for sealing ends are "TO BE SUPPLIED AND INNSTALLED BY CONTRACTOR". Layout TK37/138
  • Form 11A D1: steel supporting structures for sealing ends, 10 sets. Form 11A price schedules p.16
Another says
  • On the same layout, every SE square is drawn in blue, the color for "supplied & installed by others". Layout TK37/138
  • TK37/191-A1 defines blue as supplied and installed by others, "but to be installed by contractor". GIS floor plan TK37/191-A1
Why it matters TK37/138 is revision Λ from May 2016, ten years older than the 2026 single-lines, so its coloring may be outdated. Layout TK37/138Question 16 ↓
15Bus-section relay panels: 2 priced, 1 drawnCost
One document says
  • Form 11A D1: bus-section relay panels per item 18.7.23, 2 pieces. Item 18.7.23 includes a busbar protection central unit. Form 11A price schedules p.15
Another says
  • TK37/138 and TK37/191-A1 relay rows: one panel labeled "E08/E09". GIS floor plan TK37/191-A1
Why it matters Taken literally, 18.7.23 for 2 couplers and 2 sections gives 4 busbar central units, but the protection drawings show one. Question 17 ↓
16Bus-section interlocking typical drawing does not match the single-lineDesign
One document says
  • Interlocking TK/C/27 sheet 6, "Bus Section Bay": disconnectors and earth switches only, with no breaker. It is a 2010 typical drawing for a double busbar. Interlocking TK/C/27 p.7
Another says
  • TK37/185 sheet 2: E08 and E09 each have breaker QA1 3150A and CTs BC1 and BC2. SLD TK37/185 sh.2 · E08/E09
Why it matters The interlocking logic for E08 and E09 must be written or adapted. Question 21 ↓
17Training: included or only if requested?Cost
One document says
  • Annex II 1.1.1.5: the Contractor shall organize works training with cost included, and IEC 61850 training at the manufacturer's academy or training center. Tender (Part A, B, Annex II) p.78
Another says
  • Form 11A schedule C: works training "if requested by the Purchaser"; IEC 61850 training for up to 8 people "on side"; travel paid by the Purchaser. Form 11A price schedules p.8
Why it matters This is minor, but it changes what is in the price and where the IEC 61850 course takes place. Question 25 ↓
18Award criterion: lowest price or price with GWP factors?Commercial
One document says
  • Contract notice 5.1.10: type Price, "Lowest Price". Contract notice p.2
Another says
  • Part A 2.6 and 7.4: most economically advantageous tender on price, adjusted by GWP factors 0.75, 0.85, and 1.00. Bids with GWP 1 or more are excluded if 3 or more Category A manufacturers bid. Tender (Part A, B, Annex II) p.21
Why it matters Both are price-only because the factors only adjust the price, so the practical conflict is small. Question 26 ↓
19Surge arrester low-current withstand: 1000 A or 700 A?Design
One document says
  • Spec 3.1.4: low current 2000 μs, minimum 1000 A crest. Spec 14-019 p.19
Another says
  • Form 9 B7, required data for 132 kV: low current 2000 μs, 700 A crest. Form 9 particulars p.28
Why it matters Small, but it is a declared rating. Question 27 ↓
Minor errors in the documents (no cost impact)
  • The package includes drawing TK52/160 for "ΑΝΑΤΟΛΙΚΟ" (Anatoliko) substation (layout and demolitions) with bays Orites, Polemidhia, Stroumbi, and New Paphos. It is not listed in Appendix A and is not Kophinou. Drawing TK52/160
  • Appendix A lists TK/C/27 as 13 sheets, but the PDF has 14 pages because "Sh.5 of 13" (Bus Coupler Bay) appears twice, on pages 4 and 6. Appendix A also refers to an "Appendix B" that is not in the package. Appendix A drawing list p.3
  • TK/248 (sealing-end structure, 1999) and TK37/248 (twin Rubus drop, 2026) share a number. Appendix A drawing list p.4
  • Arrester tag is "-FA1" on TK37-243, but "-FA2" on TK37/185 and TK37-242. Overall SLD TK37-243
  • Bus coupler 2 is labelled "E011" on TK37/185 sheet 2. SLD TK37/185 sh.2
  • TK37-242 sheet 2 shows the metering cores as "CLASS 2S" and the VT primary as "132.000/3" without the √. Protection TK37-242 sh.2
  • Transformer CT is 300/1A on TK37/185 versus 200-300/1A on TK37-242 sheet 3. Protection TK37-242 sh.3
  • Template text "BUS_COUPLER/BUS_SECTION BAY_NO" is left on TK37/185 sheet 2, and busbars WA11/WA21 at E07 and WA12/WA22 at E12 to E15 are drawn in grey, not red. SLD TK37/185 sh.2
  • Form 11A D4 cites "18.12" for the DC equipment (18.13 elsewhere) and "181.6.3.3"; Schedule B2 cites "Annex III - Contract Requirements" (Annex II). Form 11A price schedules p.20
  • CPV: Part A gives 31214000; the contract notice adds 31212400 "Miniature circuit breakers". Contract notice p.1
  • "Crete Islant" in Annex II 1.1.1.2. Tender (Part A, B, Annex II) p.77
  • Layout TK37/138 is revision Λ (Greek lambda), May 2016, not "rev A". Layout TK37/138

Questions for the buyer 29

Ready to send. Biggest cost impact first.

1Short-circuit ratingDrawing TK37/185 (all sheets) specifies a rated short-time withstand current of 40 kA 1 s and a breaking current of 40 kA. Form 9A also requires 40 kA. However, EAC Spec 14-019 clause 3.1.2 row 9 gives 50 kA for 1 s for Kofinou S/S at 132 kV, and clause 18.2.1(a) refers to 3.1.2. Please confirm the rated short-circuit current and duration for the 132 kV GIS and all primary equipment: 40 kA or 50 kA, 1 s.SLD TK37/185 sh.1 · ratingsSpec 14-019 p.17
2Breaker and gas technologySpec 14-019 chapter 5, clause 5.1, and clauses 18.1.1, 18.2.1, and 18.2.4 allow "SF6 ... /Or alternative environmentally ECO-friendly gas". However, clause 5.7.1 requires circuit breakers "of the SF6 type ... e.g., puffer type", clause 5.17 covers SF6 only, and several Form 9 lines are SF6-specific. Part A 7.4 seeks Category A equipment (GWP < 1). Please confirm: (a) whether a Category A or B offer using vacuum interrupters or another non-puffer principle is acceptable without listing 5.7.1, 5.17, and the SF6-specific Form 9 entries as departures in Form 21; (b) where the "minimum specifications laid down in Annex II" for an alternative gas (Part A 7.4(d)) are located, since no such clause appears in Annex II or Spec 14-019; and (c) whether the gas-density requirements of 5.4.5 (no auxiliary gas heating, minimum -5 °C) apply unchanged to alternative gases.Spec 14-019 p.75Spec 14-019 p.66Tender (Part A, B, Annex II) p.20
3Warranty periodPart B articles 2.2, 2.3, and 35.1 specify a 12-month maintenance and defects liability period. Annex II 1.1.1 and Form 11A schedules B3 and B4 specify 24 months. Please confirm which warranty (defects liability) period to price.Tender (Part A, B, Annex II) p.38Tender (Part A, B, Annex II) p.76Form 11A price schedules p.6
4Transformer cables and terminationsAnnex II 1.1.1.1(c), 1.2.1.1, and 1.2.1.5 assign the 132 kV transformer power cables and terminations to the Contractor. Spec 18.11.2(a) states the Purchaser supplies these cables. Drawings TK37-243 and TK37-242 sheet 3 show the 3-1/C 300 mm² cable and transformer-side terminations in blue (supplied and installed by others). Form 11A D1 lists only "300 mm2 outdoor supports and supporting structures". Please confirm who supplies the 132 kV 300 mm² cables, the outdoor terminations at the existing transformer air bushings, and the adapter fittings. If the Contractor supplies them, please confirm where to price them and what route length to assume.Tender (Part A, B, Annex II) p.79Spec 14-019 p.364Form 11A price schedules p.16
5Feeder bay rated currentDrawing TK37-242 sheet 1 (E03, E04, E05, E12, E13, E15) rates QB1, QB2, and QA1 at 2000 A. Drawing TK37/185 and Form 11A D1/D5 specify 2500 A cable feeder bays, while the Form 11A bay table also lists a 2000 A cable feeder bay with no quantity. Please confirm the rated current for each cable feeder bay (E01 to E05, E12, E13, E15 to E17).Protection TK37-242 sh.1Form 11A price schedules p.15
6Feeder main protectionForm 11A D1 prices the feeder relay panels under item 18.7.1 (distance main 1 and current differential main 2). Drawing TK37-242 sheets 1 and 2 show both main 1 and main 2 as combined current differential and distance relays, while sheet 1 classifies these bays as "132kV O/H LINE BAY", for which Spec 9.4.1 requires distance main 1 and current differential main 2. The Spec 18.7 Important Note asks tenderers to offer the relays specified in the protection drawings. Please confirm the main 1 / main 2 relay principle for the Kophinou feeder bays and matching remote-end relays (Form 11A D3), and state the make and type of the existing relays at Mari and Alambra requiring compatibility.Form 11A price schedules p.15Protection TK37-242 sh.1Spec 14-019 p.336
7Remote-end relay quantityAnnex II 1.1.1.3 lists four remote-end bays (Mari 2, Alambra 2), while Form 11A D3 requests 6 + 6 relays for "Mari 1 & 2, Alambra 1 & 2, and Spare 1 & 2". Please confirm the remote-end relay quantity and identify the remote substations for spare bays E04 and E13.Tender (Part A, B, Annex II) p.78Form 11A price schedules p.19
863 MVA transformer ratioForm 11A D2 lists the 63 MVA transformers as 132/23-11,5 kV, while Annex II and Spec 18.4.1 specify 132/23 kV. Please confirm the voltage ratio.Form 11A price schedules p.18Tender (Part A, B, Annex II) p.78
9Transformer bay terminal pointsAnnex II 1.2.1.1 lists "E10-TRANSFORMER No.2" as a circuit where responsibility ends at the GIS cable sealing end chamber. Per TK37-243, E10 connects to existing 31.5 MVA Transformer No.2, which the Contractor must connect by cable. Please confirm that the intended bay is E14 (Transformer No.3), supplied with a pre-installed female termination only, and that "E13 TRFR No3" on TK37-243 should read E14.Tender (Part A, B, Annex II) p.79Overall SLD TK37-243
10Form 11A summaryForm 11A schedule E lists schedule D4 twice, omits D3 (Remote End Substations), and labels the optional bays "FROM SCHEDULE D4". Please issue a corrected schedule E and confirm whether the optional D5 total is included in the Form 11 total used for evaluation.Form 11A price schedules p.22
11Feeder CT coresForm 11A specifies CT item 18.3.9 (six windings, including two 0.2S metering cores) for all six cable feeder bays. Drawing TK37/185 shows four cores on E03, E05, E12, and E15, while TK37-242 sheet 1 shows four cores on all six bays. Please confirm the CT core arrangement per feeder bay and the transformer bay CT ratio (300/1A per TK37/185 or 200-300/1A per TK37-242 sheet 3).Spec 14-019 p.302Protection TK37-242 sh.1
12Busbar voltage transformersTK37-243 and TK37/185 show no busbar voltage transformers. Spec 18.7.23(g) requires busbar voltage selection and synchronising, and TK37-242 shows "bus voltage simulation". Please confirm that no busbar VTs are required and that busbar voltage for synchronising and check-zone use is derived from the feeder VTs.Spec 14-019 p.340Protection TK37-242 sh.1
13Crane and GIS hallDrawings TK37/191-A5 and A6 (section C-C) show an overhead travelling crane in the GIS hall with rail level +188.22 (5.2 m above finished floor +183.02) and 7.35 m clear height. Spec 5.1 states overall sizes "should be kept as per the specification drawings". Confirm whether the building contract supplies the crane, its safe working load and hook height, and that the GIS hall dimensions on TK37/191-A1 (29.6 m inner length, 10 m width, 2.7 m front aisle) are fixed.GIS sections TK37/191-A6GIS floor plan TK37/191-A1Spec 14-019 p.66
14Medium-voltage switchboardAnnex II 1 states the project includes "the medium voltage switchboard". However, no MV switchboard appears in Annex II 1.1.1.1, Form 11A, or as new equipment on TK37-243, and Annex II 1.1.1.1(c) states the transformer MV side stays as is. Annex II 1.2.1.5 assigns all 132 kV and 22 kV power cables to the Contractor, and Form 9 includes schedules B15 (22 kV switchgear) and B19 (22/11 kV autotransformers). Confirm whether any MV switchgear, MV cabling, or autotransformer is in this contract.Tender (Part A, B, Annex II) p.76Tender (Part A, B, Annex II) p.80Form 9 particulars p.45
15Gas-handling equipmentForm 11A D1 states the gas-handling equipment item "APPLIES ONLY FOR ECO FRIENDLY GAS SUPPLY EQUIPMENT". Confirm whether a gas-handling trolley, analyser, and gas alarm units per Spec 5.17 and 18.2.4 are required for a Category C (SF6) offer, and where to price them.Form 11A price schedules p.15Spec 14-019 p.301
16Sealing-end structuresDrawing TK37/138 shows sealing-end structures (SE) in blue (by others), but its legend and Form 11A D1 (10 sets) assign supply and installation to the Contractor. Confirm that the Contractor supplies and installs all 10 sets, and whether these 10 sets include the PT1 and PT2 structures for the transformer cable terminations.Layout TK37/138Form 11A price schedules p.16
17Bus-section relay panelsForm 11A D1 prices two bus-section relay panels (item 18.7.23) and two bus-coupler panels (18.7.23), while the relay room layout (TK37/138, TK37/191-A1) shows one panel for E08/E09. Confirm the panel count and that the substation requires only one busbar protection central unit.Form 11A price schedules p.15GIS floor plan TK37/191-A1
18AVR panelDrawings TK37/138 and TK37/191-A1 show a new "AVR PANEL" in the relay room, and Form 11A B1 lists a "Voltage Regulator Relay" spare. However, Form 11A D1 prices no AVR panel, and Spec 7.11.2.1 places voltage regulating relays at the 22 kV incoming cubicles. Confirm whether an AVR panel for the three 132 kV transformers is in scope and where to price it.GIS floor plan TK37/191-A1Form 11A price schedules p.3Spec 14-019 p.139
19LV AC boardThe provided LVAC drawing (ACPNL132REV3, 1999) is from another project (its file path names the Vasilikos West GIS substation) and shows three 150 kVA earthing-transformer incomers with 100 A MCCBs. Annex II 1.1.1.1(g) states the existing board temporarily feeds the new AC board; Spec 18.11.7 requires a minimum 3x185 mm² Al cable, while TK37/138 shows "LV CABLE 3CX120mm2 XLPE+N" between the buildings. Confirm the incomer count and rating for the Kophinou LVAC board and the interconnecting cable size.LVAC drawing ACPNL132REV3Spec 14-019 p.365Layout TK37/138
20Optional bay cable connectionsThe optional bays have double cable chambers with 2x3 1200 mm² cables (TK37-243, TK37/185). However, Form 11A D5 prices "4 sets" of 1200 mm² cable connections and supports, and TK37-242 shows a single "3-1/C1200mm2" cable on its feeder sheets. Confirm whether each bay requires one or two sets of three, and whether the optional cable terminations are SF6 sealing ends per 18.11.1.2(5).Form 11A price schedules p.21Protection TK37-242 sh.1
21Bus-section interlockingInterlocking drawing TK/C/27 sheet 6 (Bus Section Bay) shows a disconnector-type bus section, while the single-line shows bus sections E08/E09 with circuit breakers. Confirm the interlocking logic for E08/E09 and whether the Contractor must adapt TK/C/27.Interlocking TK/C/27 p.7SLD TK37/185 sh.2 · E08/E09
22Maintenance earth-switch drivesOn TK37/185, TK37-243, and TK37-242, maintenance earth switches QC1, QC2, and QC8 have no motor symbol, whereas QB1, QB2, QB8, QA1, QC9, and the busbar earth switches do. The TK37/185 ratings table lists a 110 V DC motor voltage for isolators and earthing switches. Confirm whether QC1, QC2, and QC8 must be motor-operated.SLD TK37/185 sh.1SLD TK37/185 sh.1 · E03
23Manufacturer experience for Category AForm 8A-1 requires three years of satisfactory service of "the proposed equipment". Part A 7.4(g) allows manufacturer experience based on SF6 GIS. Please confirm that the manufacturer's SF6 GIS references meet the Form 8A-1 satisfactory-service and sales requirements for a Category A offer.Form 8A-1 p.1Tender (Part A, B, Annex II) p.20
24Approved relay makersSpec 7.4.2 and 9.2.1 limit protection IEDs and SAS to ABB, Siemens, GE-Alstom, and Schneider Electric. Please confirm that their successor entities (for example, Hitachi Energy for ABB grid products and GE Vernova for GE-Alstom) are accepted.Spec 14-019 p.161Spec 14-019 p.118
25TrainingPlease confirm whether works training and IEC 61850 training are mandatory and included in the contract price (Annex II 1.1.1.5) or optional on request (Form 11A schedule C), and where IEC 61850 training takes place.Tender (Part A, B, Annex II) p.78Form 11A price schedules p.8
26Award criterionThe contract notice lists "Lowest Price" as the award criterion. Part A 2.6 and 7.4 specify evaluation with GWP adjustment factors. Please confirm that Part A 7.4 governs.Contract notice p.2Tender (Part A, B, Annex II) p.21
27Surge arrester low-current withstandPlease confirm the required low-current (2000 μs) withstand for the 132 kV surge arresters: 1000 A (Spec 3.1.4) or 700 A (Form 9 B7).Spec 14-019 p.19Form 9 particulars p.28
28Drawing TK52/160The package includes drawing TK52/160, "ΥΠΟΣΤΑΘΜΟΣ "ΑΝΑΤΟΛΙΚΟ"" (Anatoliko substation layout and LTM demolitions), which is not listed in Appendix A. Please confirm that it is not part of this tender and whether a Kophinou demolition or existing-equipment removal drawing should have been included.Drawing TK52/160Appendix A drawing list p.3
29Clerical pointsPlease confirm: (a) TK/C/27 has 13 sheets and the duplicate sheet 5 has identical content; (b) "TK248" on TK37/138 refers to TK/248 (sealing-end structure); (c) the Spec references in Form 11A D4 ("18.12" for DC equipment, "181.6.3.3"); (d) the CPV in the contract notice (31212400) should read 31214000.Appendix A drawing list p.3Interlocking TK/C/27 p.4Interlocking TK/C/27 p.6Form 11A price schedules p.20

Requirements to meet

32 · 10 to clarify
RequirementStatusNotePage
Submit the offer through the Cyprus eProcurement system by 13 January 2027, 14:00. Validity is 4 months. Questions are due by 03.01.2027; answers by 07.01.2027.RequiredTender (Part A, B, Annex II) p.9
Tender guarantee is EUR 200,000, valid for one month beyond tender validity.RequiredTender (Part A, B, Annex II) p.9
Tenders for part of the scope are not accepted.RequiredTender (Part A, B, Annex II) p.22
Tenders with terms contrary to the tender documents may be rejected.To clarifyAny departure from spec 5.7.1 for a Category A offer must be listed in Form 21.Tender (Part A, B, Annex II) p.10
Any price omitted from the financial form is deemed included in the other prices.To clarifyWatch for items with no Form 11A line: transformer cables and AVR panel.Tender (Part A, B, Annex II) p.27
Tick one GWP category per form set (Form 20). Offers in several categories need a full set of forms for each. Evaluation factors: 0.75 / 0.85 / 1.00.RequiredForm 20 variants p.1
Performance guarantee: 10% of the contract price.RequiredTender (Part A, B, Annex II) p.32
20% advance payment against an advance payment guarantee.RequiredTender (Part A, B, Annex II) p.39
Delay penalty: 0.2% of the contract value per week. The buyer may terminate when penalties reach 5%.RequiredTender (Part A, B, Annex II) p.42
Liability is capped at the contract price.RequiredTender (Part A, B, Annex II) p.51
Defects liability is 12 months in Part B.To clarifyAnnex II and Form 11A say 24 months.Tender (Part A, B, Annex II) p.49
Average annual turnover of at least EUR 20 million.RequiredTender (Part A, B, Annex II) p.16
Tenderer: at least 5 turnkey GIS transmission substations completed in 2015-2025, including 2 automated.To clarifyFavours EPC partners or local contractors.Tender (Part A, B, Annex II) p.17
GIS manufacturer: 10 years of 132 kV GIS experience (3 indoor), 10 GIS sold abroad in 2015-2025, and 3 years of satisfactory service for the proposed equipment at 3 utilities.To clarifyHard for new eco-gas platforms.Form 8A-1 p.1
Entities and products from Turkey may not participate. Famagusta, Kyrenia and Karavostasi are prohibited ports.RequiredTender (Part A, B, Annex II) p.14
Programme: civil foundation drawings by month 1, final data by month 5, site erection in month 14, first circuit energised in month 20, and transformers delivered in month 14. Site access may slip by 3 months.RequiredForm 10 programme p.1
145 kV double-busbar GIS, 3150 A busbars, 650 kV / 275 kV insulation, and 110 V DC control.RequiredSLD TK37/185 sh.1
Aluminium enclosures.To clarifyExcludes steel-enclosure designs.Spec 14-019 p.68
Gas loss must not exceed 1.0% per year per compartment, with at least 15 years between gas treatments and no auxiliary gas heating.To clarifyCheck the 15-year interval and the no-heating rule at -5 °C for alternative gas mixtures.Spec 14-019 p.71
Breaker: at least 3 years of commercial service for the type and rating; two separate trip coils; spring recharge within 30 s.RequiredSpec 14-019 p.75
Breaker cable-charging breaking current: at least 160 A, restrike-free.RequiredSpec 14-019 p.75
Fault clearance within 100 ms; two main protections plus one backup per 132 kV feeder.RequiredSpec 14-019 p.166
Site conditions: -5 °C to 50 °C, 100% humidity. Seismic: modified Mercalli 8, importance factor 1.4.RequiredSpec 14-019 p.22
Type tests from a recognized testing body such as KEMA or CESI; T100a reports for the derating curve (Form 9A).RequiredTender (Part A, B, Annex II) p.27
Site AC withstand test on all HV circuits; one-month reliability run before takeover.RequiredSpec 14-019 p.286
Fixed GIS hall, 29.6 m by 10 m, for 17 bays; spare space on the drawings must not be reduced.To clarifyWide 2500 A double-busbar bays may not fit.Spec 14-019 p.66
Protection IEDs: ABB, Siemens, GE-Alstom, or Schneider Electric only.To clarifyClosed list; no "or equal".Spec 14-019 p.161
SAS, RTU, and HMI: the same four makers.To clarifyClosed list.Spec 14-019 p.118
Voltage-regulating relays: Maschinenfabrik Reinhausen, Eberle, or ABB.RequiredClosed list.Spec 14-019 p.139
Gas analyzer: Dilo 3-038R-R302 V0 "or similar".RequiredSpec 14-019 p.301
Relay test set: Omicron CMC 500 with P0008404 pack.RequiredNamed product; no alternate.Tender (Part A, B, Annex II) p.78
Moisture-in-oil kits: Vaisala INDIGO80 with MMP8, 4 sets.RequiredNamed product; no alternate.Form 11A price schedules p.20

Not in the package