Mavlon Bid review
BID REVIEW · 24 NOVEMBER 2026

Valaliky Industrial Park: 110/22 kV substation ESt Geča, Slovakia

Elektrická stanica ESt 110/22 kV Geča v Strategickom území Valaliky

Valaliky Industrial Park, s. r. o. Turnkey design and build of a new 110/22 kV substation to VSD standards. Switchgear scope: one air-insulated 22 kV board with 34 panels, plus 110 kV equipment for 5 bays. Tender documents are in Slovak.

Offers due Thu 3 Dec 2026, 09:00 (EVO)Deadline extension p.1Answers to questions Due by 27 Nov 2026Tender instructions (SP, update 1) p.9Award Lowest price onlyTender instructions (SP, update 1) p.22Bid bond 500 000 EURTender instructions (SP, update 1) p.11

All 18 files were read page by page, including the 05.10.2026 update, the deadline extension, and every Q&A answer. The 110 kV single-line was read from the drawing. The package has no 22 kV single-line, so the 22 kV board is shown from the non-binding concept sketch and the PS 10 text. Every point links to its source page: click a page chip to see the wording on the page.

Questions are still possible, but barely. The buyer must deliver answers no later than six days before the offer deadline of 03.12.2026 (by 27.11.2026). A question asked too late does not require the buyer to extend the deadline. Questions are sent through the EVO system. Tender instructions (SP, update 1) p.9Tender instructions (SP, update 1) p.9Deadline extension p.1
284
Pages read
10
Positions on the single-line
17
Where the documents disagree
20
Questions for the buyer
All 20 questions and 17 conflicts, with their pages, in one file.

What matters most for your price

  1. Price 34 fully equipped, air-insulated 22 kV panels. The 05.10.2026 update changed the board from eco-gas to air, and the Q&A set the count at 34, not the 39 first written or the sketch's "do 20 ks".Spec 1.1 (update 1) p.4Clarification of 22.09 p.3
  2. Panel width is not settled: one answer says 34 panels "do šírky 1000 mm vrátane" (up to and including 1000 mm), and the next says the feeder width "je 1000 mm". Ask before pricing 1000 mm feeders.Clarification of 22.09 p.3Clarification of 22.09 p.3
  3. Billing metering: it is not stated how many of the 24 feeders need billing CTs and VTs. The Q&A refers to "3 relevantné vývodové polia"; the spec has 4 billing cabinets.Clarification of 22.09 p.4Spec 1.1 (update 1) p.7
  4. Key 22 kV ratings are missing: rated voltage, insulation level, IAC, LSC, IP, and panel currents. The VSD standard that sets them is only given as a link in Príloha 1.2.VSD standards list (1.2) p.1Spec 1.1 (update 1) p.4
  5. The whole EPC price carries strict terms: fixed price with no indexation, uncapped penalties (0,06 % per day of delay plus 10 000 EUR per day per milestone), 10 % retention, and a 10 % performance bond. Award is based on lowest price alone.Works contract (ZoD, update 1) p.117Clarification of 22.09 p.14Clarification of 22.09 p.14

What this bid covers

Supplied by the bidder
  • Turnkey: design, permits, engineering, construction, and commissioning of the new 110/22 kV substation. Tender instructions (SP, update 1) p.35
  • 22 kV: one new air-insulated, metal-enclosed board with a single busbar in 3 sections, 34 fully equipped 1000 mm wide panels, 2000 A, 20 kA/s, and a protection terminal in every panel. Spec 1.1 (update 1) p.4
  • 110 kV: air-insulated single-busbar switchyard, 1250 A, 25 kA/s, with 2 line bays, 2 transformer bays, and busbar sectionalising. Spec 1.1 (update 1) p.2
  • Two 63 MVA transformers, T101 and T102, with neutral resistors R1 and R2. Clarification of 22.09 p.5
  • 22 kV and 110 kV protection, control system (RIS), metering, auxiliary supply, and communication links, each as a lump-sum line in the bill of quantities. Bill of quantities (update 1) p.1
  • BSP building with four 22 kV rooms, cable ducts, earthing, lighting, fencing, and all civil works. BSP floor plan (Príloha 3, p.3)
By others or not stated
  • 110 kV overhead lines V6834 and V6506, towers, and conductors: not in scope. Clarification of 22.09 p.1
  • Protection and links at the remote ends (ES Kechnec, ES Haniska): by the network operators. Clarification of 22.09 p.2
  • Line protection settings and configuration: set by VSD. Tender instructions (SP, update 1) p.36
  • Arc-suppression reactors: space reserve only. The resistors are in scope. Clarification of 22.09 p.1
  • Reactive compensation: connected users' responsibility. The PS 61 dispatch-software item was removed. Clarification of 22.09 p.8
  • The 4th 22 kV section (10 panels), transformers T103/T104, and the reserve 110 kV bays: space only, with no civil preparation. Q&A answers p.4
22 kV board2000 A, 20 kA/sp.422 kV panels34 × 1000 mm, 3 sectionsp.4InsulationAir, single busbarp.422 kV earthingResistor, 300 Ap.6110 kV yard1250 A, 25 kA/sp.2Transformers2 × 63 MVA, 110/23 kVp.2

Single-line diagram, read from the image Príloha 3, obr. 1 · Príloha 4, top · Príloha 4, bottom

The only single-line in the package is "Obrázok 1 ESt Geča, Jednopólová schéma R 110 kV". It has no title block, number, revision, date, or legend. The black frame "PREDMET REALIZACIE" marks the scope; grey items are "PRIESTOROVÁ REZERVA" (space reserve). There is no 22 kV single-line. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.

Matches the other documentsSomething to checkNot in this bidShown below
Single-line diagram

Switchgear, position by position

110 kV single-line

#PositionEquipment on the drawingFeedsChecksWhere it is written
AEA02AEA02 · Line V6834 KechnecLine bay: 3150 A breaker (3 drives), line disconnector with earthing switch, busbar disconnector, combined CT/VTOverhead line V6834 to Kechnec (the line itself is not in scope)3 same3 to checkDrawing · AEA02
AEA03AEA03 · Transformer T101Transformer bay: 3150 A breaker (1 drive), busbar disconnector, 400/1 A CT with 5 coresTransformer T101, 63 MVA, 110/23/(6,3) kV1 same4 to checkDrawing · AEA03
AEA04AEA04 · Busbar sectionalising2 × busbar disconnectors Q7, Q8 with motor drive; future bus coupler drawn in greySplits busbar W1 into W11 and W121 same3 to checkDrawing · AEA04
AEA05AEA05 · Transformer T102Transformer bay: 3150 A breaker (1 drive), busbar disconnector, 400/1 A CT with 5 coresTransformer T102, 63 MVA, 110/23/(6,3) kV1 same4 to checkDrawing · AEA05
AEA06AEA06 · Line V6506 HaniskaLine bay: 3150 A breaker (3 drives), line disconnector with earthing switch, busbar disconnector, combined CT/VTOverhead line V6506 to Haniska (the line itself is not in scope)3 same3 to checkDrawing · AEA06

110/22 kV concept sketch

#PositionEquipment on the drawingFeedsChecksWhere it is written
INCIncomers T101, T102, T103 (3 panels)Incomer: breaker and protection terminal; CT and VT data not statedTransformers T101 and T102 (63 MVA each); T103 is an equipped spare4 to checkDrawing · INC

22 kV principle sketch

#PositionEquipment on the drawingFeedsChecksWhere it is written
FFeeders (24 panels)Feeder: breaker, CT 400/1/1A FS ≤ 5, VT fused on the MV side, protection terminal; billing cores in single-purpose feedersMV lines to users in the park, 8 per section5 to checkDrawing · F
VLAuxiliary-transformer feeders T21, T22 (2 panels)Feeder with billing metering: CT 30/1/1A 0,2s (spec), VT 100/√3 class 0,5, protection terminalAuxiliary transformers T21, T22, 250 kVA each3 to checkDrawing · VL
BCBus couplers with breaker (3 panels)Coupler: breaker and protection terminalLinks the sections; one likely serves the future 4th section3 to checkDrawing · BC
RSBus risers, truck without breaker (2 panels)Riser: withdrawable truck, no breaker; protection terminal per PS 10 wordingCouples a section through the coupler cable1 to checkDrawing · RS

Where the documents disagree 17

Biggest cost impact first. Each item shows both sides and their page numbers.

1Feeder panel width: exactly 1000 mm or up to 1000 mm?High cost
One document says
  • Answer to question 7: "34 plne vyzbrojených polí do šírky 1000 mm vrátane" (up to and including 1000 mm). Clarification of 22.09 p.3
  • The question quoted VSD 2026TS: feeders at most 800 mm, and 1000 mm only for incomer and coupler panels. Clarification of 22.09 p.3
Another says
  • Answer to question 8: "šírka vývodových skríň je 1000 mm" (the feeder width is 1000 mm). Clarification of 22.09 p.3
  • Spec 1.1 SO 01: one panel will be 1000 mm wide. Spec 1.1 (update 1) p.11
Why it matters Panel width drives board price and room size. A manufacturer with a standard 800 mm feeder could rely on answer 7, while answer 8 says 1000 mm. The standard itself is not in the package. Question 1 ↓
2Billing metering: all user feeders or only single-purpose ones?Cost
One document says
  • Zväzok 3: billing metering in all MV feeders where future users connect, and in the auxiliary-transformer feeders. Tender instructions (SP, update 1) p.36
Another says
  • Spec 1.1 PS 10: billing CT 0,2s and billing VT only in single-purpose feeders; distribution feeders get no billing core. Spec 1.1 (update 1) p.4
  • Answer to question 10: summed metering "pre 3 relevantné vývodové polia". PS 33: 4 AQF billing cabinets. Clarification of 22.09 p.4
Why it matters Changes the CT and VT types in up to 24 panels. The number of single-purpose feeders is not stated anywhere. Zväzok 3 itself ties the billing CT to feeders with "len jeden užívateľ", so part of the conflict is wording. Tender instructions (SP, update 1) p.37Question 2 ↓
322 kV arrangement: single row or two rows?Cost
One document says
  • Spec 1.1 SO 01: four rooms, each for at least 12 air-insulated panels in a single row. Spec 1.1 (update 1) p.11
Another says
  • Answer to question 8: arrangement and room sizes come from the contractor's design "v zmysle štandardov VSD"; the question quoted 2026TS as two rows. Clarification of 22.09 p.3
  • The question quoting 2026TS: "usporiadanie v dvoch radoch". Clarification of 22.09 p.3
Why it matters Changes the busbar and cable links between rooms. The single-row sentence was written for the eco-gas board; the update swapped only the insulation word. The panel split per section is not given either. Question 3 ↓
4Billing VT accuracy: class 0,2 or 0,5?Cost
One document says
  • Zväzok 3: billing VTs 22000/√3//100/√3 V, "trieda presnosti 0,2". Tender instructions (SP, update 1) p.37
Another says
  • Spec 1.1 PS 10: billing VT winding 10 VA, class 0,5, in single-purpose and auxiliary-transformer feeders. Spec 1.1 (update 1) p.5
Why it matters Changes the VT type in every billing feeder. Question 9 asked about both values; the answer settled only the CT ratio, and the update left the VT class unchanged. Clarification of 22.09 p.3Question 6 ↓
522 kV busbar VTs and earthing switches: drawn, but not in the 34 panelsCost
One document says
  • Principle sketch: busbar VTs TV11, TV12 and busbar earthing switches QE11, QE12. 22 kV principle sketch (Príloha 4) · TV11
Another says
  • PS 10: 34 panels (3 incomers, 2 auxiliary feeders, 5 couplers, 24 feeders). No metering panel. Spec 1.1 (update 1) p.4
Why it matters Requires either extra panels or space inside other panels. The sketch is not binding, but busbar metering and earthing must be placed somewhere. Question 7 ↓
6110 kV disconnectors: 2000 A or 2500 A?Cost
One document says
  • Spec 1.1: sectionalising, busbar, and line disconnectors are all 2000 A. Spec 1.1 (update 1) p.3
Another says
  • Single-line: every disconnector is "123kV, 2500A, 50/100kA". 110 kV single-line (Príloha 3, p.1) · AEA02
Why it matters A bidder asked this exact question. The answer only repeated "1250 A, skratový prúd 25 kA/s" for the switchyard and gave no disconnector rating. Q&A answers p.10Question 11 ↓
7110 kV transformer bays: surge arresters not drawnCost
One document says
  • Spec 1.1: the transformer bays include surge arresters. Spec 1.1 (update 1) p.3
Another says
  • Single-line AEA03 and AEA05: no arrester symbol, only earthing points. 110 kV single-line (Príloha 3, p.1) · AEA03
Why it matters This is likely a single-line omission, so price the arresters. The layout appears to show three single-phase devices in front of each transformer (tags unreadable), Príloha 1.2 lists a standard for 110 kV arresters, and the clarification letter quotes VSD arrester standard 2025TS. 110 kV layout (Príloha 3, p.2) · devices before T101VSD standards list (1.2) p.1Clarification of 22.09 p.8Question 12 ↓
8110 kV transformer-bay CTs: 200-400-800 A or 400 A?Design
One document says
  • Spec 1.1: transformer bays list "PTP (200–400-800/1/1/1/1/1 A)". Spec 1.1 (update 1) p.3
Another says
  • Single-line TA1 in AEA03 and AEA05: "CA-123, 400//1/1/1/1/1 A". The line bays show 200-400-800. 110 kV single-line (Príloha 3, p.1) · AEA03
Why it matters A multi-ratio CT costs more than a single-ratio CT; it is in the CT order. Question 14 ↓
9Auxiliary-transformer feeders: CT 30/1/1A or 400/1/1A?Design
One document says
  • Spec 1.1 PS 10: auxiliary-transformer feeders have billing CTs 30/1/1A, class 0,2s. Spec 1.1 (update 1) p.5
Another says
  • Zväzok 3: 400/1/1A CTs in single-user feeders "a v poliach vlastnej spotreby" (and in the auxiliary feeders). Tender instructions (SP, update 1) p.37
Why it matters Two panels. The feeders supply 2 × 250 kVA (about 6.6 A at 22 kV), so only 30/1/1A gives billing accuracy. The Zväzok 3 text stayed unchanged when the update only changed 5 A to 1 A. The bid can assume 30/1/1A, though the question is still worth sending. Spec 1.1 (update 1) p.8Question 15 ↓
10Neutral resistor: 300 A / 30 s or 600 A / 6 s?Design
One document says
  • Spec 1.1: resistors R1 and R2 are "NER 300/30/22". Answer 14 c): highest earth-fault current is 300 A. Spec 1.1 (update 1) p.2
Another says
  • Question 22 quoted VSD 2024TS: 600 A for 6 s. The answer left it to the contractor's design. Clarification of 22.09 p.8
Why it matters This determines the 22 kV earth-fault protection and the CTs in the resistor-protection cabinet; the resistor itself is not switchgear. Clarification of 22.09 p.6Question 16 ↓
11Units "L1" and "L2" beside the transformers: in scope or reserve?Scope
One document says
  • 110 kV layout: enclosed grey units "L1" beside T101 and "L2" beside T102, each linked to its transformer. Not on the single-line. 110 kV layout (Príloha 3, p.2) · L1
Another says
  • Reactors are reserve only (answer 2), and SO 04 reserves space for three reactor positions, not two. Spec 1.1 (update 1) p.16
Why it matters One enclosed unit linked to each transformer also matches the in-scope neutral resistors R1 and R2. So this is a scope question, not just a drawing error. Clarification of 22.09 p.1Question 17 ↓
12110 kV sectionalisers: two in AEA04, or one per line bay?Cost
One document says
  • Spec 1.1 p.3 lists "odpájač pozdĺžneho delenia prípojnice 2000 A (paralelný)" under the two line bays. Spec 1.1 (update 1) p.3
Another says
  • Spec 1.1 PS 09 and the single-line: W1 is split by Q7 and Q8 in AEA04 only. Spec 1.1 (update 1) p.3
Why it matters Read literally, the line-bay list could mean 2 more disconnectors. The single-line shows 2 in total. Question 19 ↓
13Resolved: 34 panels, not 39 or the 20 on the sketchResolved
One document says
  • Original Spec 1.1: "39 plne vyzbrojených" panels. Concept sketch: "do 20 ks" plus 20 reserve. Spec 1.1 (original) p.4
  • The sketch caption. 22 kV principle sketch (Príloha 4) · caption
Another says
  • Answer to question 7: the correct count is 34 fully equipped panels in three sections; Príloha 4 is not binding. Update 1 now says 34. Clarification of 22.09 p.3
  • Spec 1.1 update 1: "34 plne vyzbrojených VN polí o šírke 1000 mm" (3 + 2 + 5 + 24). Spec 1.1 (update 1) p.4
Why it matters Price 34 panels. The same answer states the width as "do šírky 1000 mm vrátane", which is still open (see the first point). Question 1 ↓
14Resolved: the 22 kV board is air-insulated, not eco-gasResolved
One document says
  • Original Spec 1.1: "VN rozvádzač bude ekologickým plynom izolovaný". Spec 1.1 (original) p.4
Another says
  • Spec 1.1 update 1: "VN rozvádzač bude vzduchom izolovaný", and the room text was updated to match. Answer 23: "Platí príloha č. 1.2." Spec 1.1 (update 1) p.4
Why it matters Bidders who priced a gas-insulated board before 05.10.2026 must re-price. Clarification point 43 still says eco-gas, but that is the bidder's own text from before the update. Whether SF6 is prohibited at 22 kV is still open. Clarification of 22.09 p.8Clarification of 22.09 p.17Question 5 ↓
15Resolved: billing CT secondary is 1 A, not 5 AResolved
One document says
  • Question 9 quoted the original Zväzok 3: billing CTs "400A/5A/5A". Clarification of 22.09 p.3
Another says
  • Answer to question 9: the Zväzok 3 value was wrong; "Platí hodnota 400/1/1A". Updated Zväzok 3 now reads 400/1/1A. Clarification of 22.09 p.3
Why it matters The same answer did not settle the billing VT class. Question 6 ↓
16Resolved: the bill of quantities sets the work packages, including "Ochrany 22kV"Resolved
One document says
  • Spec 1.1 has no separate package for 22 kV protection. Spec 1.1 (update 1) p.4
Another says
  • Answer 29: the valid package list is in the bill of quantities, which has "Rozvodňa 22kV" and "Ochrany 22kV" as separate lines. Clarification of 22.09 p.11
Why it matters The 22 kV relays therefore go in one of two price lines, but which one is not stated. Bill of quantities (update 1) p.1Question 8 ↓
17Resolved: 110 kV short-circuit level is 25 kAResolved
One document says
  • Single-line: breakers "3150A/40kA", disconnectors "50/100kA". 110 kV single-line (Príloha 3, p.1) · AEA02
Another says
  • Spec 1.1: 25 kA/s. Q&A answer: the switchyard is rated "1250 A, skratový prúd 25 kA/s". Q&A answers p.10
Why it matters The drawing values are higher than required. The disconnector current remains open. Question 11 ↓
Minor errors in the documents (no cost impact)
  • Zväzok 3 still says the station is built "len pre polovičný výkon 63 MVA", but the answers settle it: two transformers of 63 MVA each. Tender instructions (SP, update 1) p.35
  • 110 kV layout: the last two bays are both tagged "AEA04" (AEA08 and AEA09 on the single-line), AEA06 reads "V6?70" (V6506 elsewhere), and the axes run 1-7, 2, 3, 3. 110 kV layout (Príloha 3, p.2) · bay tags
  • Single-line header "In= 1200 A" is blurred; Spec 1.1 says 1250 A. This may not be a real difference. 110 kV single-line (Príloha 3, p.1) · header
  • The concept sketch shows Q8 on the left and Q7 on the right; the single-line has Q7 on the left and Q8 on the right. The sketch is not binding. Concept sketch 110/22 kV (Príloha 4) · Q8 / Q7
  • Spec 1.1 update 1 states "IEC608705-101"; the original said IEC60870-5-101. Spec 1.1 (update 1) p.6
  • None of the drawings have a title block, drawing number, revision, date, or legend. 110 kV single-line (Príloha 3, p.1)

Questions for the buyer 20

Ready to send through EVO, highest cost impact first. Each includes Slovak wording ready to paste.

1Feeder panel widthThe answer to question 7 (22.09.2026) states 34 panels "do šírky 1000 mm vrátane" (up to and including 1000 mm). The answer to question 8 states the feeder width "je 1000 mm", as does Spec 1.1 SO 01. May the 24 feeder panels be offered at 800 mm wide (the feeder width reportedly set by VSD standard 2026TS), or must every panel be 1000 mm?
Wording for the buyer, in Slovak

Odpoveď na otázku č. 7 (žiadosť z 22.09.2026) uvádza „34 plne vyzbrojených polí do šírky 1000 mm vrátane“, odpoveď na otázku č. 8 uvádza „šírka vývodových skríň je 1000 mm“ a Príloha 1.1 (SO 01, s. 11) „Šírka jedného poľa VN rozvádzača bude 1000 mm“. Je prípustné ponúknuť vývodové polia so šírkou 800 mm podľa štandardu VSD 2026TS (bod 3.2.4.1), alebo musia mať všetky polia šírku 1000 mm?

Clarification of 22.09 p.3Clarification of 22.09 p.3Spec 1.1 (update 1) p.11
2Feeders with billing meteringHow many of the 24 feeders are single-purpose (billing CT 0,2s and billing VT), how many are distribution feeders (no billing core), and in which sections? Zväzok 3 requires billing metering in all feeders with future users; Spec 1.1 (PS 10, p.4-5) requires it only in single-purpose feeders; the answer to question 10 refers to "3 relevantné vývodové polia"; PS 33 has 4 AQF billing cabinets.
Wording for the buyer, in Slovak

Koľko z 24 vývodových VN polí rozvádzača R 22 kV je „jednoúčelových“ (s fakturačným meraním PTP 0,2s a PTN pre fakturáciu) a koľko „distribučných“ (bez fakturačného jadra), a v ktorých sekciách? Zväzok 3 požaduje fakturačné meranie „vo všetkých VN poliach, v ktorých budú pripojení budúci užívatelia“, Príloha 1.1 (PS 10, s. 4-5) ho predpisuje len pre jednoúčelové vývody a odpoveď na otázku č. 10 (žiadosť z 22.09.2026) uvádza „3 relevantné vývodové polia“.

Tender instructions (SP, update 1) p.36Spec 1.1 (update 1) p.4Clarification of 22.09 p.4Spec 1.1 (update 1) p.7
3Arrangement and section splitIs the 22 kV board single-row per Spec 1.1 SO 01 ("min. 12 polí ... v jednoradovom usporiadaní"), or two-row per VSD 2026TS, cited in the answer to question 8? Provide the panel types per section for the 34 panels. The 5 couplers (3 with breaker, 2 with truck) for 3 sections suggest one breaker coupler serves the future 4th section; please confirm. Are the sections in separate rooms 1.01-1.03 coupled by cable?
Wording for the buyer, in Slovak

Požaduje sa rozvádzač R 22 kV v jednoradovom usporiadaní podľa Prílohy 1.1 (SO 01, s. 11: „min. 12 polí ... v jednoradovom usporiadaní“), alebo dvojradové usporiadanie podľa štandardu VSD 2026TS, na ktorý odkazuje odpoveď na otázku č. 8? Prosíme o rozdelenie 34 polí do troch sekcií (typ poľa po sekciách). Päť polí spínača prípojníc (3x s vypínačom, 2x s vozíkom bez vypínača) pre tri sekcie naznačuje, že jedno pole s vypínačom slúži budúcej štvrtej sekcii; prosíme o potvrdenie. Potvrdzujete, že spojenie sekcií v samostatných miestnostiach 1.01-1.03 sa rieši káblom?

Spec 1.1 (update 1) p.11Clarification of 22.09 p.3Spec 1.1 (update 1) p.4BSP floor plan (Príloha 3, p.3)
4Missing 22 kV ratingsSpecify the missing 22 kV board ratings: rated voltage (Ur), insulation level, internal arc classification (IAC, current and time), LSC category, partition class, IP degree, and rated currents for incomer, coupler, and feeder panels. The answer to question 11 quotes VSD 2026TS (Ith min. 20 kA, Ip min. 50 kA). If 2026TS governs the remaining ratings, please attach it, as Príloha 1.2 contains only a link.
Wording for the buyer, in Slovak

Prosíme o doplnenie parametrov rozvádzača R 22 kV, ktoré nie sú uvedené v súťažných podkladoch: menovité napätie (Ur) a izolačná hladina, klasifikácia odolnosti voči vnútornému oblúku (IAC, prúd a čas), kategória LSC a trieda prepážok, stupeň krytia IP a menovité prúdy prívodných, spínacích a vývodových polí. Ak platia hodnoty zo štandardu VSD 2026TS (odpoveď na otázku č. 11 z neho cituje Ith min. 20 kA a Ip min. 50 kA), prosíme o jeho priloženie, keďže Príloha 1.2 obsahuje iba odkaz.

VSD standards list (1.2) p.1Clarification of 22.09 p.4
5SF6 at 22 kVSpec 1.1 requires 110 kV breakers "s ekologickou izoláciou (bez SF6)". Does this SF6-free requirement also apply to the breakers and switches in the 22 kV board?
Wording for the buyer, in Slovak

Príloha 1.1 požaduje pre vypínače 110 kV „ekologickú izoláciu (bez SF6)“. Platí obmedzenie použitia SF6 aj pre vypínače a odpínače v rozvádzači R 22 kV?

Spec 1.1 (update 1) p.3
6Billing VT accuracy classWhich accuracy class applies to the billing winding of the 22 kV VTs: 0,2 per Zväzok 3, or 0,5 per Spec 1.1 (PS 10, p.4-5)? The answer to question 9 confirmed only the CT ratio.
Wording for the buyer, in Slovak

Akú triedu presnosti má mať fakturačné vinutie PTN na 22 kV: 0,2 podľa Zväzku 3, alebo 0,5 podľa Prílohy 1.1 (PS 10, s. 4-5)? Odpoveď na otázku č. 9 (žiadosť z 22.09.2026) upravila len prevod PTP.

Tender instructions (SP, update 1) p.37Spec 1.1 (update 1) p.5Clarification of 22.09 p.3
722 kV busbar VTs and earthing switchesThe 22 kV principle sketch (Príloha 4) shows busbar VTs TV11/TV12 and busbar earthing switches QE11/QE12, but the PS 10 list of 34 panels includes no metering panel. In which panels are the busbar VTs and earthing switches installed, and are they included in the 34 panels?
Wording for the buyer, in Slovak

Principiálna schéma R 22 kV (Príloha č. 4) obsahuje prípojnicové meracie transformátory napätia TV11/TV12 a uzemňovače prípojníc QE11/QE12. Rozpis 34 polí v PS 10 samostatné meracie polia neobsahuje. V ktorých poliach majú byť prípojnicové PTN a uzemňovače prípojníc umiestnené, a sú zahrnuté v počte 34?

22 kV principle sketch (Príloha 4) · TV11Spec 1.1 (update 1) p.4
822 kV relays: pricing lineAre the protection terminals for the 34 panels priced under BoQ line "Rozvodňa 22kV" or "Ochrany 22kV"? Is a terminal needed in the two riser panels without a breaker, since PS 10 states every panel gets one? Which protection functions are required for each panel type?
Wording for the buyer, in Slovak

Terminály polí s ochranami pre 34 polí R 22 kV: majú byť ocenené v položke VV „PS D+M Rozvodňa 22kV“ alebo v položke „PS D+M Ochrany 22kV“? Prosíme tiež o potvrdenie, či sa terminál s ochranou požaduje aj v dvoch poliach spínača prípojníc „s vozíkom bez vypínača“ (PS 10: „Všetky VN polia budú vybavené terminálom poľa s elektrickou ochranou“), a o určenie požadovaných ochranných funkcií pre jednotlivé typy polí.

Bill of quantities (update 1) p.1Spec 1.1 (update 1) p.4
9CT and VT data for incomers and couplersProvide the CT and VT ratios, accuracy classes, and burdens for transformer incomers T101/T102/T103 and the coupler panels, plus the protection-core classes for the feeders. Spec 1.1 gives only the overcurrent factor of the billing core.
Wording for the buyer, in Slovak

Prosíme o určenie prevodov, tried presnosti a výkonov PTP a PTN v prívodných poliach transformátorov T101/T102/T103 a v poliach spínača prípojníc, ako aj tried presnosti ochranných jadier PTP vo vývodových poliach (Príloha 1.1 uvádza len nadprúdové číslo fakturačného jadra).

Spec 1.1 (update 1) p.4
10Equipped spare incomer T103What scope is required for the "equipped spare" incomer for T103: breaker, CTs, VTs, protection terminal, and cable terminations, or without cables and terminations since transformer T103 is out of scope?
Wording for the buyer, in Slovak

Rozsah „vyzbrojenej rezervy pre T103“: má byť prívodné pole T103 dodané kompletne vrátane vypínača, PTP, PTN, terminálu s ochranou a káblových koncoviek, alebo bez káblov a koncoviek, keďže transformátor T103 nie je predmetom zákazky?

Spec 1.1 (update 1) p.4
11110 kV disconnector ratingWhich rated current applies to the 110 kV disconnectors: 2000 A per Spec 1.1 (p.3), or 2500 A per the single-line in Príloha 3? The answer dated 23.09.2026 (poradové č. 2) confirmed only 1250 A / 25 kA/s for the switchyard.
Wording for the buyer, in Slovak

Aký menovitý prúd platí pre odpájače 110 kV: 2000 A podľa Prílohy 1.1 (s. 3), alebo 2500 A podľa jednopólovej schémy v Prílohe č. 3? Odpoveď na otázku zo dňa 23.09.2026 (poradové č. 2) potvrdila len 1250 A / 25 kA/s pre rozvodňu.

Spec 1.1 (update 1) p.3110 kV single-line (Príloha 3, p.1) · AEA02Q&A answers p.10
12110 kV surge arrestersWe will price surge arresters in the 110 kV transformer bays per Spec 1.1 (p.3) and treat their absence on the single-line as an omission; the layout seems to show three devices in front of each transformer. Please confirm. Are surge arresters also needed on the 22 kV side of the transformers?
Wording for the buyer, in Slovak

Obmedzovače prepätia v poliach transformátorov 110 kV (Príloha 1.1, s. 3) oceníme ako súčasť dodávky, hoci ich jednopólová schéma v Prílohe č. 3 nezobrazuje; vo výkrese dispozície sú pred každým transformátorom zakreslené tri jednofázové prístroje. Prosíme o potvrdenie. Požadujú sa aj obmedzovače prepätia na strane 22 kV transformátorov?

Spec 1.1 (update 1) p.3110 kV single-line (Príloha 3, p.1) · AEA03110 kV layout (Príloha 3, p.2) · devices before T101VSD standards list (1.2) p.1
13110 kV breaker type on the single-lineThe single-line lists the 110 kV breaker type "LTB145D1/B ... 3150A/40kA". Is this for reference only, with the Spec 1.1 requirement for a 3150 A breaker "s ekologickou izoláciou (bez SF6)" binding? It is not stated whether that type is SF6-free.
Wording for the buyer, in Slovak

Jednopólová schéma uvádza pre vypínače 110 kV typ „LTB145D1/B ... 3150A/40kA“. Potvrdzujete, že ide len o referenčné označenie a že záväzná je požiadavka Prílohy 1.1 na vypínač 3150 A „s ekologickou izoláciou (bez SF6)“?

110 kV single-line (Príloha 3, p.1) · AEA02Spec 1.1 (update 1) p.3
14110 kV transformer-bay CT ratioShould the transformer-bay CTs be 200-400-800/1/1/1/1/1 A per Spec 1.1 (p.3), or 400/1/1/1/1/1 A per the single-line (TA1 in AEA03/AEA05)?
Wording for the buyer, in Slovak

Prevod PTP v poliach transformátorov 110 kV: 200-400-800/1/1/1/1/1 A podľa Prílohy 1.1 (s. 3), alebo 400/1/1/1/1/1 A podľa schémy (TA1 v AEA03/AEA05)?

Spec 1.1 (update 1) p.3110 kV single-line (Príloha 3, p.1) · AEA03
15CT ratio for auxiliary-transformer feedersWhich CT ratio applies to auxiliary-transformer feeders T21/T22: 30/1/1A per Spec 1.1 (PS 10, p.5), or 400/1/1A per Zväzok 3 ("... a v poliach vlastnej spotreby")? We plan to use 30/1/1A, since 2 x 250 kVA at 22 kV is about 6.6 A.
Wording for the buyer, in Slovak

Aký prevod PTP platí pre vývodové polia transformátorov vlastnej spotreby T21/T22: 30/1/1A podľa Prílohy 1.1 (PS 10, s. 5), alebo 400/1/1A podľa Zväzku 3 („... a v poliach vlastnej spotreby ESt 110/22 kV Geča“)? Pri výkone 2 x 250 kVA (cca 6,6 A pri 22 kV) uvažujeme s prevodom 30/1/1A.

Spec 1.1 (update 1) p.5Tender instructions (SP, update 1) p.37
16Neutral resistor ratingWhich neutral-resistor rating is binding: 300 A / 30 s per Spec 1.1 ("NER 300/30/22"), or 600 A / 6 s per VSD 2024TS as quoted in question 22? This determines the 22 kV earth-fault protection and the CTs in cabinet AXT01.
Wording for the buyer, in Slovak

Prosíme o záväzné parametre uzlového odporníka (menovitý prúd a doba zaťaženia): 300 A / 30 s podľa Prílohy 1.1 („NER 300/30/22“), alebo 600 A / 6 s podľa štandardu VSD 2024TS citovaného v otázke č. 22? Od toho závisí nastavenie zemných ochrán 22 kV a PTP v rozvádzači AXT01.

Spec 1.1 (update 1) p.2Clarification of 22.09 p.8
17Units "L1" and "L2" on the 110 kV layoutWhat are the enclosed units tagged "L1" and "L2" beside T101 and T102 on the 110 kV layout? Are they the in-scope neutral resistors R1 and R2, or reserved for reactors (SO 04 reserves three reactor positions)?
Wording for the buyer, in Slovak

Čo predstavujú zariadenia označené „L1“ a „L2“ pri stanovištiach T101/T102 vo výkrese Dispozícia R 110 kV (Príloha č. 3, s. 2)? Ide o uzlové odporníky R1 a R2, ktoré sú predmetom zákazky, alebo o rezervu pre tlmivky (SO 04 uvádza rezervu pre tri stanovištia tlmiviek)?

110 kV layout (Príloha 3, p.2) · L1Spec 1.1 (update 1) p.16Clarification of 22.09 p.1
18110 kV busbar VTsThe busbar VTs TV1/TV2 (bay AEA01A) are shown in grey as reserve. Please confirm that the 110 kV busbar VTs are out of scope, even though the switchyard requires busbar differential protection.
Wording for the buyer, in Slovak

Prípojnicové PTN TV1/TV2 (pole AEA01A) sú v schéme zakreslené sivou farbou ako rezerva. Potvrdzujete, že prípojnicové PTN 110 kV nie sú predmetom zákazky, napriek požiadavke na rozdielovú ochranu prípojníc?

110 kV single-line (Príloha 3, p.1) · AEA01ASpec 1.1 (update 1) p.6
19Number of 110 kV sectionalisersSpec 1.1 (p.3) lists "odpájač pozdĺžneho delenia prípojnice 2000 A (paralelný)" under the line bays. Please confirm that the busbar is sectionalised only by the two disconnectors Q7 and Q8 in AEA04, as shown on the single-line, with no additional ones in the line bays.
Wording for the buyer, in Slovak

Príloha 1.1 (s. 3) uvádza pri poliach vedení „odpájač pozdĺžneho delenia prípojnice 2000 A (paralelný)“. Potvrdzujete, že pozdĺžne delenie tvoria iba dva odpájače Q7 a Q8 v poli AEA04 podľa schémy, a nie ďalšie odpájače v poliach vedení?

Spec 1.1 (update 1) p.3110 kV single-line (Príloha 3, p.1) · AEA04
20Clerical pointsPlease correct or confirm these items: on the 110 kV layout (Príloha 3, p.2), the last two bays are both tagged "AEA04" (AEA08/AEA09 on the single-line), bay AEA06 has the line label "V6?70" (V6506 on the single-line), and the axes run 1-7, 2, 3, 3; the single-line header reads "In= 1200 A" (hard to read), while Spec 1.1 specifies 1250 A; Spec 1.1 update 1 (p.6) writes "IEC608705-101" for IEC 60870-5-101.
Wording for the buyer, in Slovak

Prosíme o opravu alebo potvrdenie: vo výkrese Dispozícia R 110 kV (Príloha 3, s. 2) sú posledné dve polia označené „AEA04“ a „AEA04“ (podľa schémy AEA08/AEA09), pole AEA06 má označenie vedenia „V6?70“ (podľa schémy V6506) a osi sú číslované 1-7, 2, 3, 3; hlavička schémy R 110 kV uvádza „In= 1200 A“ (zle čitateľné), Príloha 1.1 uvádza 1250 A; Príloha 1.1 Aktualizácia 1 (s. 6) uvádza „IEC608705-101“ namiesto IEC 60870-5-101.

110 kV layout (Príloha 3, p.2) · bay tags110 kV single-line (Príloha 3, p.1) · headerSpec 1.1 (update 1) p.6

Requirements to meet

28 · 8 to clarify
RequirementStatusNotePage
Offers via EVO are due by 03.12.2026, 09:00; opening is at 10:00.RequiredThe deadline was moved from 06.11.2026.Deadline extension p.1
Award is based on lowest price only, in EUR excluding VAT.RequiredTender instructions (SP, update 1) p.22
Bid bond is 500 000,00 EUR; offer validity is 12 months from the deadline.RequiredTender instructions (SP, update 1) p.11
Estimated contract value is 24 776 403,00 EUR excluding VAT.RequiredCovers the whole EPC, not just the switchgear.Tender instructions (SP, update 1) p.6
Fixed price for the full 36 months, with no price-index clause.To clarifyA request for indexation was refused.Clarification of 22.09 p.14
Penalties: 0,06 % of the price per day of delay; 10 000 EUR per day per late milestone; 0,06 % per day per open defect; 0,1 % per day for an urgent defect; 100 000 EUR per subcontractor breach. No overall cap.To clarifyA request for a cap was refused.Works contract (ZoD, update 1) p.117
Retention: 10 % of each invoice (2 × 5 %); performance bank guarantee: 10 %.RequiredWorks contract (ZoD, update 1) p.96
Warranty: 60 months from defect-free acceptance; 18 months for a repaired or replaced part.RequiredWorks contract (ZoD, update 1) p.115
Design, engineering, and final permits within 18 months; handover with the occupancy certificate within 36 months after the contract takes effect.RequiredTender instructions (SP, update 1) p.39
Equipment installation in the BSP building, including the MV switchgear: 4 months in the informative schedule.RequiredThe schedule is informative; the bidder prepares the binding schedule.Spec 1.1 (update 1) p.19
All materials and equipment require prior VSD approval.To clarifyCheck that your 22 kV board and 110 kV breaker are acceptable to VSD.Works contract (ZoD, update 1) p.46
Only materials from the VSD catalogue of permitted materials may be used.To clarifyThe catalogue is not included in the package.Tender instructions (SP, update 1) p.35
Equivalent products are allowed if they meet VSD standards and are approved by VSD.RequiredClarification of 22.09 p.12
22 kV board: air-insulated, metal-enclosed, single busbar, 3 sections, 34 panels (1000 mm wide), 2000 A, 20 kA/s.RequiredReading "20 kA/s" as 1 s follows answer 14 d), which was given for the earthing values.Spec 1.1 (update 1) p.4
A protection terminal in every 22 kV panel.To clarifyIf read literally, this includes the risers.Spec 1.1 (update 1) p.4
22 kV design short-circuit current: 20 kA; no permanent parallel operation of the transformers; earth-fault current: 300 A.RequiredClarification of 22.09 p.4
Billing CTs: 400/1/1A, non-switchable ratio, class 0,2s, maximum overcurrent factor 5, with metrological verification valid in Slovakia.RequiredTender instructions (SP, update 1) p.37
110 kV: 1250 A, 25 kA/s; 3150 A SF6-free breakers with motor drives.To clarifyFew SF6-free 145 kV breaker ranges exist.Spec 1.1 (update 1) p.3
Pollution class IV for all outdoor insulation.RequiredClarification of 22.09 p.9
110 kV earth-fault current Ik1'' = 12,52 kA.RequiredClarification of 22.09 p.6
IEC 61850 with GOOSE interlocking; two independent links, one to the main and one to the backup dispatch center.RequiredClarification of 22.09 p.6
Routine test reports, a 72-hour complex run, manuals in Slovak, certificates, and declarations of conformity.RequiredSpec 1.1 (update 1) p.23
Design documents produced in Ruplan and checked through eDSO.RequiredSpec 1.1 (update 1) p.20
VSD technical rules TP 400.18, TP 400.04, TP 400.08, and others apply.To clarifyNone of them are in the package; the answer points to the VSD website.Spec 1.1 (update 1) p.26
Ruggedcom switches RSG910C and RSG908C.RequiredEquivalents allowed.Spec 1.1 (update 1) p.6
Schneider Electric iEM3250 meters and PASS600 data logger.RequiredEquivalents allowed.Spec 1.1 (update 1) p.9
Voltage indicator CAPDIS-S1+R4.5 + C2M-M ER3563-00.RequiredEquivalents allowed.Spec 1.1 (update 1) p.8
Types named only on the 110 kV single-line: breaker "LTB145D1/B", CT "CA-123", CT/VT "KA-123", and disconnectors "CB-N2.K" and "CBe-N2".To clarifyIt is not stated whether the breaker type is SF6-free.110 kV single-line (Príloha 3, p.1) · AEA02

Not in the package

Want a review like this for a bid you are pricing? Book a call.