Evides PR011466: 10 kV switchgear for Petrusplaat (Levering 10KV verdelers)

Europese Openbare Aanbesteding: Levering 10KV verdelers

Evides N.V., European open tender "Levering 10KV verdelers". Two 7-panel 10 kV boards for the new E-building at Petrusplaat, Werkendam: board A (700/1 to 700/7) and board B (800/7 to 800/1), 14 panels. Tender documents are in Dutch.

Bids due Thu 17 Dec 2026, 10:00 (Mercell)Tender guide p.6Questions closed Fri 20 Nov 2026, 12:00Tender guide p.6Award Lowest price, including commissioningTender guide p.20Scope Design, supply, installation, testing, commissioningTender guide p.7

Seven documents, two drawings, and three typical sheets were read page by page. The single-line and room layout were read directly from the drawings. Every point links to its source page: click a page chip to see the wording on that page.

The question window has closed. Questions were due by 20-11-2026, 12:00; late questions "worden niet in behandeling genomen" (are not handled). The Nota van Inlichtingen of 27-11-2026 is the only formal answer. Guide section 2.9 lets bidders report defects and contradictions until the bid deadline, mainly to keep the right to object; Evides is not obliged to answer. Under Bestek 1.3, the supplier must fill in any data left open in the package, so build the bid to hold without answers. Tender guide p.6Tender guide p.6Tender guide p.8Bestek p.3
97
Pages read
14
Positions on the single-line
13
Where the documents disagree
25
Points to raise
All 25 questions and 13 conflicts, with their pages, in one file.

What matters most for your price

  1. Open datasheet fields are your risk: Bestek 1.3 states that the supplier is deemed to fill in any missing data, and the minimum requirements are knock-out (accept or do not accept each one). Switch type, protection, undervoltage coils, and cable data are open on every panel.Bestek p.3Tender guide p.19Datasheet p.7 · Type schakelaar
  2. Price 14 withdrawable 1250 A vacuum circuit breakers. The single-line shows one in every panel, the Bestek requires withdrawable, interchangeable breakers, and the datasheet specifies withdrawable devices; only its "Type schakelaar" row is left open.Single-line · all 14 panelsBestek p.11Datasheet p.1
  3. Incomers 700/1 and 800/1 are drawn with no CTs, relays, or earthing switch, while the existing incomers have CT 400/1, Ith and ER relays, and an earthing switch. Couplers 700/7 and 800/7 match the existing coupler 200/9 exactly, so their drawing reflects site practice.Single-line · 700/1Single-line · 100/1*Single-line · 200/9
  4. MV cable connections and floor openings are by others in the Bestek. The guide says "turnkey", but its own scope paragraph refers the exact scope to the Bestek. 18 three-core cable ends depend on this.Bestek p.3Tender guide p.7
  5. Do not rely on a deviation list. The Bestek asks for one, but the guide excludes bids with conditions or reservations, and the contract ranks the bid last.Bestek p.7Tender guide p.7Draft contract p.5

What this bid covers

Supplied by the bidder
  • Two 10 kV boards with 7 panels each, one in the HV room on side A and one on side B of the new E-building, including internal transport, installation, and testing. Bestek p.3
  • Design, engineering, supply, installation, testing, commissioning, and ready-for-service handover. Tender guide p.7
  • Transport to site and unloading. There are no lifting facilities on site. Bestek p.4
  • FAT of each complete board at the bidder's own factory in the EU, including travel and accommodation for Evides' witnesses. Bestek p.8
  • Price form: "10kV verdeler 7 velden" × 2, FAT, internal transport, and parameterising, commissioning, and testing. Bestek p.13
  • Per HV room: all operating and maintenance tools with a wall holder, at least two withdrawal trolleys, and one relay test plug. Bestek p.11
  • Documents: arc and pressure-wave calculations, type test report, FAT and SAT protocols, 3D model, and Dutch manuals. Bestek p.8
By others or not stated
  • Connecting the MV cables and making the floor openings are by others. The supplier provides the positions. Bestek p.3
  • Civil works. The supplier provides heat output, dimensions, and weights with the offer. Bestek p.4
  • MV cables 1702.027 to 1702.039 are shown on the single-line; who supplies them is not stated. Single-line
  • New settings on existing feeding panels 100/2 and 200/2 are marked in cyan; who changes them is not stated. Single-line · Veld 100/2
  • The 60 V DC control supply is not assigned. The layout shows batteries "ACCU 15A/BAT1" and "ACCU 15B/BAT1" in the LV rooms. Room layout · ACCU 15A/BAT1
Rated voltage12 kV, 50 Hzp.1Busbar1250 Ap.1Short circuit25 kA / 3 sp.1BreakersWithdrawable vacuum, air-insulated, SF6-freep.2Arc classA-FLR, current and time not statedp.2Control voltage60 V DC (+ to earth), 230 V ACp.1Panel width600 mmp.2

Single-line diagram, read from the image 907-177001-001

Single-line 907-177001-001, rev 39C, 26-10-2026. This is the master single-line of the entire existing 10 kV/3 kV installation in building 17a, with the two new boards added on a cyan background. The sheet has only a relay legend; reading cyan as "new" is our inference. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.

Matches the other documentsSomething to checkNot in this bidShown below
Single-line diagram

Switchgear, position by position

#PositionEquipment on the drawingFeedsChecksWhere it is written
700/1700/1 · Incomer "Voeding 1"1250 A withdrawable breaker with motor; no CT, relay, or earthing switch drawnFrom existing 100/2; cable 2x(3x150AL+as70)1 same5 to checkDrawing · 700/1
700/2700/2 · 11/121/K1Withdrawable breaker 1250 A, CT 100/1, relay I>, earthing switch11/121/K1, 1320 kVA in the datasheet; cable 3x35+as251 same5 to checkDrawing · 700/2
700/3700/3 · 11/221/K1Withdrawable breaker 1250 A, CT 100/1, relay I>, earthing switch11/221/K1, 1320 kVA in the datasheet; cable 3x35+as251 same5 to checkDrawing · 700/3
700/4700/4 · 11/321/K1Withdrawable breaker 1250 A, CT 100/1, relay I>, earthing switch11/321/K1, 1320 kVA in the datasheet; cable 3x35+as251 same5 to checkDrawing · 700/4
700/5700/5 · 11/421/K1Withdrawable breaker 1250 A, CT 100/1, relay I>, earthing switch11/421/K1, 1320 kVA in the datasheet; cable 3x35+as251 same5 to checkDrawing · 700/5
700/6700/6 · Transformer 15A/-/M1Withdrawable breaker 1250 A, CT 100/1, relays I> and Ith, earthing switchTransformer 15A/-/M1, 500 kVA (datasheet: 500 kVA); cable 3x35+as252 same5 to checkDrawing · 700/6
700/7700/7 · CouplerWithdrawable breaker 1250 A with motor, busbar VT; no CT, relay or earthing switch drawnCable tie 1702.029 to 800/7, 2x(3x150AL+as70)1 same4 to checkDrawing · 700/7
800/7800/7 · CouplerWithdrawable breaker 1250 A with motor, busbar VT; no CT, relay or earthing switch drawnCable tie 1702.029 to 700/7, 2x(3x150AL+as70)1 same4 to checkDrawing · 800/7
800/6800/6 · Transformer 15B/-/M1Withdrawable breaker 1250 A, CT 100/1, relays I> and Ith, earthing switchTransformer 15B/-/M1, 500 kVA (datasheet: 1320 kVA); cable 3x35+as251 same6 to checkDrawing · 800/6
800/5800/5 · 11/821/K1Withdrawable breaker 1250 A, CT 100/1, relay I>, earthing switch11/821/K1, 1320 kVA in the datasheet; cable 3x35+as251 same6 to checkDrawing · 800/5
800/4800/4 · 11/721/K1Withdrawable breaker 1250 A, CT 100/1, relay I>, earthing switch11/721/K1, 1320 kVA in the datasheet; cable 3x35+as251 same6 to checkDrawing · 800/4
800/3800/3 · 11/621/K1Withdrawable breaker 1250 A, CT 100/1, relay I>, earthing switch11/621/K1, 1320 kVA in the datasheet; cable 3x35+as251 same5 to checkDrawing · 800/3
800/2800/2 · 11/521/K1Withdrawable breaker 1250 A, CT 100/1, relay I>, earthing switch11/521/K1, 500 kVA in the datasheet; cable 3x35+as251 same5 to checkDrawing · 800/2
800/1800/1 · Incomer "Voeding 2"1250 A withdrawable breaker with motor; no CT, relay, or earthing switch drawnFrom existing 200/2; cable 2x(3x150AL+as70)1 same5 to checkDrawing · 800/1

Where the documents disagree 13

Biggest cost impact first. Each item shows both sides and their page numbers.

1Switching device: 14 withdrawable breakers drawn; type left open in the datasheetCost
One document says
  • Single-line: a withdrawable circuit breaker "1250" in all 14 panels, including transformer panels 700/6 and 800/6. Single-line · boards A and B
  • Bestek: "De schakelaars zijn uitrijdbaar" and "onderling uitwisselbaar" (withdrawable, interchangeable). Bestek p.11
  • Datasheet: "Schakelaars uitrijdbaar ja" and "lucht geïsoleerde vacuümschakelaars". Datasheet p.1
Another says
  • Datasheet sheet 7, every panel: "vermogensschakelaar / lastschakelaar / railaarder / geen" with nothing struck out. Datasheet p.7 · Type schakelaar
  • Legend: "** = aan te vullen/controleren door engineer" (for Evides' engineer to complete). Datasheet p.3
Why it matters Taken together, the package points strongly to 14 withdrawable vacuum breakers: a load-break switch would not meet "onderling uitwisselbaar", and the reference criteria call for withdrawable vacuum breakers. So the real price swing is small. Under Bestek 1.3, the open field is for the supplier to fill in. Bestek p.3Tender guide p.17Question 1 ↓
2Incomers 700/1 and 800/1: no CTs, relays, or earthing switch drawnHigh cost
One document says
  • Single-line: 700/1 and 800/1 have a breaker with a motor only; the relay table lists "Voeding 1" and "Voeding 2" with no settings. Single-line · 700/1
  • Datasheet row 35 places the CTs "in LS-compartiment per veld". This states where CTs are mounted; reading it as "every panel has CTs" is an interpretation. Datasheet p.1
Another says
  • Existing incomers 100/1* and 200/1* have CT 400/1, Ith and ER relays, and an earthing switch. Single-line · 100/1*
  • Bestek: relays are mounted in the LV door above the breaker, and "Alle behuizingen" (all housings) have an earthing switch. Bestek p.11
Why it matters Two relays, two CT sets, and two earthing switches with interlocks. The existing incomers point to protected, earthable incomers, and these two panels carry the double 150 mm² ring cables. Bestek p.11Question 2 ↓
3Motor operation: four panels drawn with a motor; datasheet asks for remote ON/OFFCost
One document says
  • Single-line: motor operator (M) only on 700/1, 700/7, 800/7, and 800/1. Single-line · 700/7
Another says
  • Datasheet row 60, hardwired signals: "sturing IN/UIT, status IN/UIT, alarm, trip". Datasheet p.2
  • Reference criteria: breakers "met shunt open/close, spring motor". Tender guide p.17
Why it matters Remote closing on all 14 panels requires closing coils and motor spring charging on every breaker. Existing coupler 200/9 also has M while existing incomers do not, so M marks this site's coupler and auto-switching convention, not a rule. Step 1 of the Bestek switching procedure is a local manual off. Single-line · 200/9Bestek p.11Question 5 ↓
4Couplers 700/7 and 800/7: drawn without an earthing switch; Bestek asks for one in every housingCost
One document says
  • Single-line: the couplers have a breaker, motor, and busbar VT, but no CT, relay, or earthing switch. Their relay cells are blank, not crossed out. Single-line · 700/7
  • Existing coupler 200/9 is drawn the exact same way, and Bestek 1.3 asks for the new boards to be uniform with the existing installation. Single-line · 200/9
Another says
  • Bestek: "Alle behuizingen zijn voorzien van een aardschakelaar". Bestek p.11
  • Datasheet row 32: "Aardingsschakelaar ja". Datasheet p.1
Why it matters For the couplers, having no protection is most likely site practice, not an oversight. The earthing switch still matters: without one, coupler cable 1702.029 cannot be earthed at either end. Bestek p.3Question 3 ↓
5Deviation list requested by the Bestek; reservations excluded by the guideEligibility
One document says
  • Bestek 2.3: put all deviations in one deviation list; 4.2: list deviations and options with description and price. Bestek p.7
  • Bestek 2.1: state the use of standards or deviations from them separately in the offer. Bestek p.6
Another says
  • Guide 2.7: bids must be "onvoorwaardelijk en zonder enig voorbehoud"; conditions or reservations lead to exclusion. Tender guide p.7
  • Guide 5.1: minimum requirements have an "uitsluitend karakter"; each is accepted or not accepted in the Mercell questionnaire. Tender guide p.19
  • Contract 8.4 ranks the bid ("Inschrijving") last, below the Bestek and the purchase terms. Draft contract p.5
Why it matters A deviation list can be read as a reservation and lead to bid exclusion. Even if accepted, it would rank below the Bestek and the purchase terms in the contract. Question 11 ↓
6CT ratio: "400/1" in the datasheet, "100/1" on the single-lineDesign
One document says
  • Datasheet row 36, boards A and B: "5P10 xx VA" and "400/1", both marked "***". Datasheet p.1 · row 36
  • Legend: "*** = aan te vullen/controleren door leverancier" (for the supplier to complete or check). Datasheet p.3
Another says
  • Single-line: "100/1" on all 10 CTs (700/2 to 700/6 and 800/2 to 800/6). The settings I>=66A and I>=45A fit a 100 A primary. Single-line · 700/2
Why it matters 400/1 is not a fixed buyer value. It matches the CTs of existing feeding panels 100/2 and 200/2, so it looks like a carry-over or a value meant for the incomers. The burden is also blank. Single-line · 100/2Question 8 ↓
7Board B: transformer and feeder kVA swapped in the datasheetDesign
One document says
  • Datasheet sheet 7, board B: 800/6 "Trafo 15B/-/M1" = 1320 kVA; 800/2 "FO 11/521/K1" = 500 kVA. Datasheet p.7 · board B kVA
Another says
  • Single-line: "15B/-/M1 10kV/0.4kV Uk=6% P=500kVA" on 800/6; relay table: 800/6 I>=45A, 800/2 I>=66A. Single-line · 800/6
  • Board A in the same datasheet: 700/6 transformer = 500, 700/2 feeder = 1320. Datasheet p.7 · board A kVA
Why it matters The B row looks copied from A without mirroring the panel order. It changes CT, relay, and sizing for 800/2 and 800/6. Question 12 ↓
8Ring load against the upstream settingDesign
One document says
  • Datasheet: 11560 kVA on 700/1, 700/7, 800/7, and 800/1. That is 8 × 1320 + 2 × 500 kVA (both boards fully loaded through one feed), or about 667 A at 10 kV. Datasheet p.7 · board A kVA
Another says
  • Single-line: the new cyan setting on feeding panels 100/2 and 200/2 is "I>=454A t=0,6s" on CT 400/1. Single-line · Veld 100/2
Why it matters Either 11560 kVA is not a real load, or the upstream settings and CTs do not suit single-feed operation. This also affects the CT ratio: 400/1 matches the 100/2 and 200/2 CTs. Single-line · 100/2Question 13 ↓
9Feeder relay pickup below the datasheet feeder ratingDesign
One document says
  • Datasheet: 1320 kVA per outgoing feeder, about 76 A at 10 kV. Datasheet p.7 · board A kVA
Another says
  • Relay table: "I>=66A t=0,3s" on 700/2 to 700/5 and the B feeders. Single-line · relay table A
Why it matters A 66 A definite-time pickup would trip a feeder loaded to its datasheet rating. The relay settings are Evides'. Question 13 ↓
10Undervoltage coils: assumed in the Bestek, left open in the datasheetDesign
One document says
  • Bestek: "De nulspanningsspoelen zijn in de behuizing geplaatst en niet in de schakelaars." Bestek p.11
Another says
  • Datasheet sheet 7, every panel: "Nulspanningsspoel ja / nee". Datasheet p.7
Why it matters Placing coils in the housing rather than in the breaker is unusual. Which panels need them is left open, and the supplier must fill open fields. Question 15 ↓
11Busbar VT: 100 V and 110 V secondaries in one cellDesign
One document says
  • Datasheet row 38 (image only): one winding "Up/√3 / 100/3". Datasheet p.1 · row 38
Another says
  • Same cell: the other winding "Up/√3 / 110/√3"; class "kl. 1", burden "xx VA", marked "**". Datasheet p.1 · row 38
Why it matters There is an inconsistency inside one cell that Evides' engineer was to complete. The drawn VT has three windings (two star, one open delta), which fits two secondaries on one base. Question 16 ↓
12FAT costs: Bestek vs. purchase termsSmall cost
One document says
  • Bestek 3.1: the supplier pays for travel and stay of Evides or its representative; Evides covers the time needed for the FAT. Bestek p.8
Another says
  • AIV 11.1: Evides pays the costs of external experts engaged for an inspection. Purchase terms (AIV) p.7
Why it matters The Bestek overrides the purchase terms. Price the witnesses' travel and stay; Evides pays an independent inspector's fee. Question 21 ↓
13Test stick: excluded in the Bestek, required in the datasheetSmall cost
One document says
  • Bestek: all tools per HV room, "(geen elektrische test- stokken)" (no electrical test sticks). Bestek p.11
Another says
  • Datasheet row 72: "Teststok (geschikt voor Up) ja". Datasheet p.2
Why it matters Low cost, but a definite conflict. Question 20 ↓
Minor errors in the documents (no cost impact)
  • Relay table, board B row: the columns for 800/4 and 800/5 are labeled "Veld 700/4" and "Veld 700/5". Single-line · relay table B
  • Room layout: the transformer in room 15A-FO is labeled "15B/-/M1", while the single-line shows 15A/-/M1. Room layout · 15A-FO
  • Thermal relays (Ith) are drawn on 700/6 and 800/6, but the relay table gives no Ith setting. Single-line · relay table A
  • The datasheet document number is "06021", while the file and footer number is "06032". Datasheet p.1
  • Bestek: the standards table mentions "SF6-vrije RMU's" and the file title has another project number ("PR011876 ... RMU"), but the requested switchgear is withdrawable breaker switchgear. Bestek p.6
  • The Bestek contents lists "3.2.1" twice (offer documents and order documents). Bestek p.8
  • Contract annex numbers: 8.3 attaches the AIV "als Bijlage 5", while 9.1 lists them as Bijlage 4; 8.4 and 9.1 list the Nota van Inlichtingen as Bijlage 6, while the contents page lists it as Bijlage 7 and lists Bijlage 6 as "Inschrijving leverancier". Draft contract p.5
  • Contract: two articles are headed "TARIEVEN" (4 and 5); 5.1 refers to "Bijlage 2 (Tarieven)", 6.2 refers to "Bijlage 3 (Contactpersonen)" although Bijlage 3 is the invoicing procedure, and 7.1 refers to "Bijlage 4 (Facturatieprocedure)" although Bijlage 4 is the AIV. Draft contract p.4
  • Guide: "Bijlage 4: Concept overeenkomst", whereas Bestek Bijlage 4 is the one-line diagram; guide 5.2 is headed "Economisch Meest Voordelige Inschrijving (EMVI)", although the award is on lowest price. Tender guide p.19

Points to raise before the bid deadline 25

The question window closed on 20-11-2026. Guide 2.9 still lets you report defects and contradictions until 17-12-2026, 10:00, but Evides does not have to answer, and pure information requests may get no reply. Largest cost impact first. Each point has Dutch wording ready to paste.

1Switching device in all 14 panelsDatasheet sheet 7 lists all four options under "Type schakelaar" in every panel, with none struck out. The single-line shows a withdrawable 1250 A breaker in all 14 panels, and Bestek Bijlage 1 asks for withdrawable, interchangeable breakers. We are pricing 14 withdrawable 1250 A vacuum circuit breakers, including transformer panels 700/6 and 800/6. Please confirm.
Wording for your offer, in Dutch

Datasheet blad 7 laat per veld "Type schakelaar" (vermogensschakelaar / lastschakelaar / railaarder / geen) open; het lijnschema 907-177001-001 toont in alle 14 velden een uitrijdbare vermogensschakelaar "1250", en Bestek bijlage 1 vraagt uitrijdbare, onderling uitwisselbare schakelaars. Wij gaan uit van 14 uitrijdbare vacuüm-vermogensschakelaars 1250 A, ook in de trafovelden 700/6 en 800/6. Graag bevestigen.

Datasheet p.7 · Type schakelaarSingle-line · all 14 panelsBestek p.11
2Protection in the incomers and couplersThe single-line shows no CT and no relay in incomers 700/1 and 800/1, and the relay table gives no settings for "Voeding 1" and "Voeding 2". Existing incomers 100/1* and 200/1* have CT 400/1 with Ith and ER relays, and the Bestek places the relays in the LV door above the breaker. What protection and CTs are required in 700/1 and 800/1? Couplers 700/7 and 800/7 are drawn exactly like existing coupler 200/9; we offer them without protection, per the uniformity required in Bestek 1.3. Please confirm.
Wording for your offer, in Dutch

In het lijnschema zijn in de voedingsvelden 700/1 en 800/1 geen stroomtransformatoren en geen beveiligingsrelais getekend, en de relaistabel geeft voor "Voeding 1" en "Voeding 2" geen instellingen. De bestaande voedingsvelden 100/1* en 200/1* hebben stroomtransformatoren 400/1 met Ith- en ER-relais, en het bestek plaatst de beveiligingsrelais in de laagspanningsdeur boven de schakelaar. Welke beveiliging en stroomtransformatoren moeten in 700/1 en 800/1 worden geleverd? De koppelvelden 700/7 en 800/7 zijn getekend zoals het bestaande koppelveld 200/9; conform de uniformiteit uit Bestek §1.3 bieden wij deze zonder beveiliging aan. Graag bevestigen.

Single-line · 700/1Single-line · 100/1*Single-line · 200/9Bestek p.11
3Earthing switches in the incomers and couplersBestek Bijlage 1 states: "Alle behuizingen zijn voorzien van een aardschakelaar". The single-line shows no earthing switch in 700/1, 700/7, 800/7 and 800/1. Existing incomers have one, while existing coupler 200/9 does not; however, without one, coupler cable 1702.029 cannot be earthed at either end. Must these four panels have a short-circuit-proof cable earthing switch?
Wording for your offer, in Dutch

Bestek bijlage 1: "Alle behuizingen zijn voorzien van een aardschakelaar". In het lijnschema ontbreekt de aardschakelaar in 700/1, 700/7, 800/7 en 800/1. De bestaande voedingsvelden 100/1* en 200/1* hebben er wel een; het bestaande koppelveld 200/9 niet, maar zonder aardschakelaar kan de koppelkabel 1702.029 aan geen van beide zijden worden geaard. Moeten deze vier velden een kortsluitvaste kabelaardschakelaar krijgen?

Bestek p.11Single-line · 700/7Single-line · 200/9
4MV cable connectionGuide 2.3 refers to a "volledige turnkey uitvoering", whereas Bestek 1.2 states "Aansluiten van de MS-kabels en maken van vloersparingen wordt door derden gedaan". Are MV cable terminations and their supply in or out of our scope?
Wording for your offer, in Dutch

Aanbestedingsleidraad §2.3 spreekt van een "volledige turnkey uitvoering"; Bestek §1.2 stelt "Aansluiten van de MS-kabels en maken van vloersparingen wordt door derden gedaan". Vallen het aansluiten van de MS-kabels en de levering van de kabeleindsluitingen binnen of buiten onze scope?

Tender guide p.7Bestek p.3
5Motor operationThe single-line shows a motor operator (M) only in 700/1, 700/7, 800/7 and 800/1, while datasheet row 60 requires hardwired "sturing IN/UIT". In the existing installation, M appears on coupler 200/9 and not on the incomers. Must all 14 breakers have motor spring charging, a closing coil and an opening coil, or only the four panels shown with M?
Wording for your offer, in Dutch

Het lijnschema toont een motoraandrijving (M) alleen in 700/1, 700/7, 800/7 en 800/1; datasheet regel 60 vraagt hardwired "sturing IN/UIT". In de bestaande installatie heeft het koppelveld 200/9 een motoraandrijving en de voedingsvelden niet. Moeten alle 14 vermogensschakelaars een veermotor, inschakelspoel en uitschakelspoel krijgen, of alleen de vier velden met M?

Single-line · 700/7Datasheet p.2Single-line · 200/9
6Internal arc class and pressure-relief ductThe datasheet specifies "Drukafvoer kanaal" and "A-FLR" without a current or time; the Bestek requires pressure relief to the outside; and the reference criteria specify "25kA-1s Interne arc". No duct is drawn on layout 907-157003-001. Which IAC value applies, and is the duct to the outside (route, length, wall passage) in our scope?
Wording for your offer, in Dutch

De datasheet vraagt "Drukafvoer kanaal" en "Vlamboogbescherming A-FLR" zonder stroom en tijd; het bestek vraagt drukontlasting naar buiten; de referentie-eis noemt "25kA-1s Interne arc". Op de ruimte-indeling 907-157003-001 is geen kanaal getekend. Welke IAC-waarde (kA en s) is vereist, en valt het drukafvoerkanaal tot buiten het gebouw (tracé, lengte, muurdoorvoer) in onze scope?

Datasheet p.2Bestek p.11Tender guide p.17Room layout · HV rooms
7Existing installation: make and what must be uniformBestek 1.3 requires compatibility and uniform operation and maintenance with the existing 10 kV installation, but no make or type is named anywhere in the package. What are the make and type of the existing 10 kV switchgear and relays, and what exactly must be uniform? (Information request: it may not be answered.)
Wording for your offer, in Dutch

Bestek §1.3: "Installatie moet compatibel zijn met bestaande 10kV installatie" en "Bediening en onderhoud moet uniform zijn aan de bestaande installatie". Wat zijn fabricaat en type van de bestaande 10 kV-installatie en van de bestaande beveiligingsrelais, en welke aspecten moeten uniform zijn (bediening, uitrijwagen, relais, gereedschap)?

Bestek p.3
8CT ratio, class and burdenDatasheet row 36 lists "5P10 xx VA" and "400/1", both for the supplier to complete. The single-line shows "100/1" in 700/2 to 700/6 and 800/2 to 800/6, which matches the settings I>=66A and I>=45A. We offer 100/1 as drawn. Please confirm the ratio, class and burden per panel, and whether a metering core is required. Does "in LS-compartiment per veld" (row 35) refer to the CT secondary terminals?
Wording for your offer, in Dutch

Datasheet regel 36 vermeldt "5P10 xx VA" en "400/1", beide door de leverancier aan te vullen; het lijnschema toont "100/1" in 700/2 tot en met 700/6 en 800/2 tot en met 800/6, passend bij de instellingen I>=66A en I>=45A. Wij bieden 100/1 aan conform lijnschema. Graag bevestigen welke overzetverhouding, klasse en vermogen (VA) per veld gelden, en of een meetkern gewenst is. Wordt met "in LS-compartiment per veld" (regel 35) de aansluiting van de secundaire klemmen bedoeld?

Datasheet p.1 · row 36Single-line · 700/2Datasheet p.1
960 V DC control supplyDatasheet row 24: control voltage "60 (+ aan massa)" V DC. Does Evides provide the 60 V DC (the layout shows "ACCU 15A/BAT1" and "ACCU 15B/BAT1"), or must we supply the battery and charger? (Information request: this may not be answered.)
Wording for your offer, in Dutch

Datasheet regel 24: stuurspanning "60 (+ aan massa)" Vdc. Wordt de 60 V DC door Evides aangeleverd (op de ruimte-indeling staan "ACCU 15A/BAT1" en "ACCU 15B/BAT1"), of moeten batterij en lader in onze levering worden opgenomen?

Datasheet p.1Room layout · ACCU 15A/BAT1
10Price form lines and missing price sheetThe Inschrijfbiljet (Bestek page 13) lists only "10kV verdeler 7 velden", "FAT", "Intern transport", and "Parametreren, in bedrijf name en testen". Where should installation, transport to site, SAT, documentation, tools, and hourly rates be entered? The guide refers to a "Staat van verrekenprijzen" and an Excel price sheet that are missing from the package. Please provide them.
Wording for your offer, in Dutch

Het inschrijfbiljet (Bestek blz. 13) bevat alleen "10kV verdeler 7 velden", "FAT", "Intern transport" en "Parametreren, in bedrijf name en testen". Waar moeten montage, transport naar locatie, SAT, documentatie, gereedschap en de uurtarieven (Bestek §4.1) worden geprijsd? De Aanbestedingsleidraad noemt een "Staat van verrekenprijzen" en een inschrijfstaat in Excel; deze ontbreken in de stukken. Graag beschikbaar stellen.

Bestek p.13Tender guide p.22Tender guide p.12
11Deviation listBestek 2.3 and 4.2 require all deviations in one priced deviation list, while guide 2.7 excludes bids with conditions or reservations and 5.1 makes minimum requirements knock-out criteria. Will submitting a deviation list cause exclusion?
Wording for your offer, in Dutch

Bestek §2.3 en §4.2 vragen alle afwijkingen in één afwijkingslijst met prijs op te nemen; Aanbestedingsleidraad §2.7 sluit inschrijvingen met voorwaarden of voorbehouden uit, en §5.1 geeft de minimumeisen een "uitsluitend karakter". Leidt het indienen van een afwijkingslijst tot uitsluiting?

Bestek p.7Tender guide p.7Tender guide p.19
12Board B transformer and feeder ratingsOn Datasheet sheet 7, board B lists 800/6 (Trafo 15B/-/M1) as 1320 kVA and 800/2 (FO 11/521/K1) as 500 kVA. The single-line shows 15B/-/M1 as 500 kVA, and board A has the opposite values. Please confirm that 800/6 is 500 kVA and 800/2 is 1320 kVA.
Wording for your offer, in Dutch

Datasheet blad 7, verdeler B: veld 800/6 (Trafo 15B/-/M1) staat op 1320 kVA en veld 800/2 (FO 11/521/K1) op 500 kVA; het lijnschema geeft 15B/-/M1 = 500 kVA en verdeler A geeft de omgekeerde waarden. Graag bevestigen: 800/6 = 500 kVA en 800/2 = 1320 kVA.

Datasheet p.7 · board B kVASingle-line · 800/6
13Protection settings and ring loadThe feeder pickup "I>=66A t=0,3s" is below the 1320 kVA datasheet rating (about 76 A at 10 kV). The 11560 kVA on 700/1, 700/7, 800/7, and 800/1 equals both boards fully loaded through one feed (about 667 A), while feeding panels 100/2 and 200/2 have a new setting of "I>=454A t=0,6s" on CT 400/1. Which values apply, and will Evides provide the final protection settings?
Wording for your offer, in Dutch

De afgaande velden hebben "I>=66A t=0,3s", terwijl de datasheet 1320 kVA per afgaand veld geeft (ca. 76 A bij 10 kV). De 11560 kVA voor 700/1, 700/7, 800/7 en 800/1 komt overeen met beide verdelers volbelast via één voeding (ca. 667 A), terwijl de nieuwe instelling van de voedende velden 100/2 en 200/2 "I>=454A t=0,6s" is, op stroomtransformator 400/1. Welke waarden zijn juist, en levert Evides de definitieve beveiligingsinstellingen aan?

Single-line · relay table ADatasheet p.7 · board A kVASingle-line · Veld 100/2
14Work on existing panelsOn the single-line, the settings for existing panels 100/2 and 200/2 and transformers 17F/-/m1 and 17F/-/m2 on 100/7 and 200/7 are marked cyan, with no legend on the sheet. Is work on existing panels, such as changing relay settings, in our scope ("Parametreren, in bedrijf name en testen")? What does the cyan marking mean?
Wording for your offer, in Dutch

Op het lijnschema zijn de relaisinstellingen van de bestaande velden 100/2 en 200/2, en de trafo's 17F/-/m1 en 17F/-/m2 in 100/7 en 200/7, cyaan gemarkeerd; de tekening heeft geen legenda. Vallen werkzaamheden aan bestaande velden, zoals het aanpassen van relaisinstellingen, in onze scope ("Parametreren, in bedrijf name en testen")? Wat betekent de cyaan markering?

Single-line · Veld 100/2Single-line · 100/7Single-line · legend
15Undervoltage tripsBestek Bijlage 1 specifies undervoltage coils in the housing, but datasheet sheet 7 leaves "Nulspanningsspoel ja / nee" blank for every panel. Which panels require an undervoltage trip?
Wording for your offer, in Dutch

Bestek bijlage 1 stelt dat de nulspanningsspoelen in de behuizing zijn geplaatst; datasheet blad 7 laat "Nulspanningsspoel ja / nee" per veld open. In welke velden is een nulspanningsuitschakeling vereist?

Bestek p.11Datasheet p.7
16Busbar VTDatasheet row 38 lists both "Up/√3 / 100/3" and "Up/√3 / 110/√3" in one cell. Which secondary base applies (100 V or 110 V), what class and burden apply to each winding, and must the VT be withdrawable and fused as drawn?
Wording for your offer, in Dutch

Datasheet regel 38 vermeldt in één cel "Up/√3 / 100/3" en "Up/√3 / 110/√3". Welke secundaire spanning geldt (100 V of 110 V), welke klasse en welk vermogen (VA) per wikkeling, en moet de spanningstransformator uitrijdbaar en gezekerd zijn, zoals getekend?

Datasheet p.1 · row 38Single-line · 700/7
17Relay communication and interlockingDatasheet row 62 lists "Profibus / Modbus / glasvezel". Which protocol and medium apply, and where does our scope end (relays to PLC 15A/PLC1 and 15B/PLC1)? Remark 2 requires a release to close an incoming panel onto a dead busbar: what interlocking scheme applies between 700/1, 700/7, 800/7, and 800/1, and where does the release come from?
Wording for your offer, in Dutch

Datasheet regel 62: "Profibus / Modbus / glasvezel". Welk protocol en welk medium zijn vereist, en tot waar loopt onze scope (relais tot PLC 15A/PLC1 en 15B/PLC1)? Opmerking 2: "Vrijgave nodig voor inschakelen voedend veld bij spanningsloze rail". Welk vergrendelingsschema is gewenst tussen 700/1, 700/7, 800/7 en 800/1, en waar komt de vrijgave vandaan?

Datasheet p.2Datasheet p.3
18Cable data per panelDatasheet sheet 7 leaves the number of cables, cable type, and conductor blank for every panel. Please confirm that the single-line data apply: 2x(3x150AL+as70) on 700/1, 700/7, 800/7, and 800/1, and 3x35+as25 on the other ten panels.
Wording for your offer, in Dutch

Datasheet blad 7 laat aantal kabels per fase, kabeltype en geleider per veld open. Graag bevestigen dat de kabelgegevens van het lijnschema gelden: 2x(3x150AL+as70) op 700/1, 700/7, 800/7 en 800/1, en 3x35+as25 op de overige tien velden.

Datasheet p.7Single-line · 700/1
19Panel widthDatasheet row 54 specifies a 600 mm panel width, and the layout shows a 4200 mm line-up in a 4800 mm wide room. Is 600 mm mandatory, or is another width allowed if the board meets the clearances in rows 14 and 15 (300 mm rear, 100 mm side)?
Wording for your offer, in Dutch

Datasheet regel 54 geeft een veldbreedte van 600 mm; de ruimte-indeling toont een verdeler van 4200 mm in een ruimte van 4800 mm breed. Is 600 mm een harde eis, of is een andere breedte toegestaan zolang de verdeler past met de afstanden van regel 14 en 15 (300 mm achter, 100 mm zij)?

Datasheet p.2Room layout · HV roomsDatasheet p.1
20Test stickBestek Bijlage 1 says "(geen elektrische test- stokken)", while datasheet row 72 says "Teststok (geschikt voor Up) ja". Must a test stick be supplied?
Wording for your offer, in Dutch

Bestek bijlage 1: "(geen elektrische test- stokken)"; datasheet regel 72: "Teststok (geschikt voor Up) ja". Moet een teststok worden meegeleverd?

Bestek p.11Datasheet p.2
21FAT witnessesBestek 3.1 puts travel and accommodation for Evides' witnesses at the supplier's cost. How many people and days should we price? (Information request: it may not be answered.)
Wording for your offer, in Dutch

Bestek §3.1: reis- en verblijfkosten van de opdrachtgever of zijn gemachtigde bij de FAT zijn voor rekening van de leverancier. Met hoeveel personen en dagen moeten wij rekening houden?

Bestek p.8
22Reference criteria: IP rating and generator panelCore competence 1 asks for references with "IP4X met behuizing dicht", "IP2X met behuizing open", and a "Generatorveld". Do these IP ratings also apply to the supplied boards (the Bestek gives none)? Is a generator panel part of this contract, or only for the reference?
Wording for your offer, in Dutch

Kerncompetentie 1 vraagt referenties met "IP4X met behuizing dicht", "IP2X met behuizing open" en een "Generatorveld". Gelden deze beschermingsgraden ook voor de te leveren verdelers (het bestek noemt geen IP-graad)? Is een generatorveld onderdeel van deze opdracht, of alleen van de referentie-eis?

Tender guide p.17Tender guide p.17
23Enexis requirementsDatasheet row 6: "Eisen netbeheerder Enexis". Which Enexis requirements apply to these boards, and can Evides provide them? (Information request: it may not be answered.)
Wording for your offer, in Dutch

Datasheet regel 6: "Eisen netbeheerder Enexis". Welke Enexis-eisen gelden voor deze verdelers, en kunt u deze documenten beschikbaar stellen?

Datasheet p.1
24Delivery and installation datesBestek 1.10: "Levering in december in jaar 2027". What are the delivery date per board, the installation window, and the energizing date? (Information request: it may not be answered.)
Wording for your offer, in Dutch

Bestek §1.10: "Levering in december in jaar 2027". Graag de gewenste leverdatum per verdeler, de montageperiode en de datum van inbedrijfname.

Bestek p.5
25Clerical pointsPlease confirm the following: in the relay table, row B, "Veld 700/4" and "Veld 700/5" mean 800/4 and 800/5; the transformer in room 15A-FO is 15A/-/M1, not "15B/-/M1"; the Ith settings for 700/6 and 800/6 are missing; datasheet number 06021 versus file 06032; and the contract annex numbers (8.3 versus 9.1; Nota van Inlichtingen annex 6 or 7).
Wording for your offer, in Dutch

Graag bevestigen: in de relaistabel, rij Zeelandkelder B, betekenen "Veld 700/4" en "Veld 700/5" 800/4 en 800/5; de trafo in ruimte 15A-FO is 15A/-/M1 en niet "15B/-/M1"; de Ith-instellingen voor 700/6 en 800/6 ontbreken; datasheet documentnummer 06021 tegenover bestandsnaam 06032; de bijlagenummering van de concept-overeenkomst (art. 8.3 tegenover 9.1; Nota van Inlichtingen bijlage 6 of 7).

Single-line · relay table BRoom layout · 15A-FODraft contract p.5

Requirements to meet

35 · 12 to clarify
RequirementStatusNotePage
Submit your bid on Mercell by 17-12-2026, 10:00. Late bids will not be assessed.RequiredTender guide p.6
Bids must be unconditional and without reservations, or the bidder will be excluded.To clarifyThe Bestek asks for a deviation list, which may count as a reservation.Tender guide p.7
Minimum requirements are knock-out criteria: accept or reject each one in the Mercell questionnaire.RequiredTender guide p.19
Where the Bestek gives no data, the supplier is expected to fill it in.To clarifyEvery open datasheet field is your risk.Bestek p.3
Award is based on lowest price, including commissioning.RequiredTender guide p.20
Price form: 2 × "10kV verdeler 7 velden", FAT, internal transport, parameterizing, and commissioning. The price sheet is also required in Excel.To clarifyThere are no lines for installation, transport to site, documents, or tools; the Excel sheet and "Staat van verrekenprijzen" are not in the package.Bestek p.13
Include hourly rates for technical support, installation, and commissioning, and a proposal for payment terms, with the offer.RequiredBestek p.10
Bid is valid for 60 days.RequiredARN 2016 p.9
Prices are fixed for the whole contract with no indexation. Delivery is in December 2027.To clarifyDelivery is about a year from award at a fixed price.Draft contract p.4
Delivery is DDP site. Payment is within 30 days. Evides may ask for a bank guarantee before a payment.RequiredPurchase terms (AIV) p.4
The penalty is 0.2% of the price per day, up to 5%, plus damages.RequiredPurchase terms (AIV) p.7
The warranty is at least 2 years from successful installation and acceptance on site, with spares for at least 25 years.RequiredBestek p.10
Liability is capped at €2,500,000 per order. Liability insurance (AVB) must be at least €2,500,000 per event.RequiredPurchase terms (AIV) p.10
One reference per core competence from the last 3 years: 12 kV boards with outside arc venting, 25 kA 1 s internal arc, IP4X/IP2X, 1250 A, 25 kA 3 s, withdrawable vacuum breakers, coupler, generator panel, and Profibus DP or Modbus.To clarifyThe generator-panel reference narrows the field; this bid has no generator panel.Tender guide p.17
FAT must be in the bidder's own factory inside the EU (minimum requirement).RequiredTender guide p.19
ISO 9001 or equivalent, VCA** or VCA-VOL for all site staff, and an RI&E work plan are required.RequiredBestek p.4
Submit the Russia sanctions declaration with the bid; the winner signs the sustainability code.RequiredTender guide p.11
Witnessed FAT is required for each complete board. Assistance, equipment, and the witnesses' travel and stay are at the supplier's cost.RequiredBestek p.8
Ratings: 12 kV, 50 Hz, 1250 A busbar, 25 kA 3 s, left phase rotation, and 230 V AC auxiliary.RequiredDatasheet p.1
Control voltage is 60 V DC with positive to earth.To clarifyCheck that coils, motors, and relays are available for 60 V DC, positive earthed.Datasheet p.1
NEN applies first, then IEC (62271-1, -200, -100, -102, and others). CE marking of the complete installation is required after installation.RequiredBestek p.6
Air-insulated, SF6-free vacuum breakers: withdrawable and interchangeable, with an isolating position.RequiredBestek p.11
Short-circuit proof with outside pressure relief; IAC A-FLR, with current and time not stated.To clarifyThe reference criteria ask for 25 kA 1 s; there is no duct on the layout.Bestek p.11
Earthing switch in every housing, hand-operated and lockable in both positions.RequiredBestek p.11
Undervoltage coils in the housing, not in the breakers.To clarifyUnusual arrangement; check with each manufacturer.Bestek p.11
Relays in the LV door above the breaker; current injection from outside the LV door with a test plug, one plug per room.To clarifyTest-block make not specified.Bestek p.11
Mimic with three-state position indicators: horizontal, vertical, and "diagonaal of uit".To clarifyCheck with each manufacturer.Bestek p.11
Panel width 600 mm; 4200 mm line-up in a 4800 mm room; 300 mm to the rear wall and 100 mm to the side wall.To clarifyTight for 1250 A panels with two 3x150 mm² cables.Datasheet p.2
Three compartments: LV at the top, breaker in the middle with viewing window and emergency operation, and cable compartment with earthing switch at the bottom.RequiredBestek p.11
With the offer: schedule with lead time, datasheets, layout and opening sketches, sample test protocol, heat output, dimensions, and weights.RequiredBestek p.8
After order: control schematics, arc and pressure-wave calculations, type test report, FAT and SAT protocols, and 3D model in .stp; Dutch manuals at handover.RequiredBestek p.8
Site: Monday to Friday 07:30-16:30; permits required; operations continue during installation; heavy transport may not use the Werkendam ferry.RequiredBestek p.3
Wiring colours per the Evides typical: 60 V DC positive red, negative transparent, switched yellow; CT secondary wiring 2.5 mm².RequiredWiring colours p.1
No brand is named; any brand or type reference reads "of gelijkwaardig" (or equal).RequiredTender guide p.9
Compatible with the existing 10 kV installation (make not named), and operated and maintained the same way.To clarifyMay favour the make already on site.Bestek p.3

Not in the package