Mavlon Bid review
BID REVIEW · 24 NOVEMBER 2026

SBB: 15 kV, 16.7 Hz indoor switchgear for substation Zollikofen

16.7 Hz, 15 kV Innenraumschaltanlage Unterwerk Zollikofen

SBB AG, Infrastruktur Energie. Air-insulated single-phase 15 kV railway switchgear: 10 cells and a reserve position, with stainless-steel raised floors and a pressure-relief duct. Open procedure; documents in German.

Offer due Tue 19 Jan 2027, 15:00 (SAP Ariba)Tender conditions p.4Questions due Mon 7 Dec 2026; answers by 14 DecTender conditions p.4Award Price 70%, quality 15%, sustainability 15%Tender conditions p.13Scope Design, supply, installation, site testTender conditions p.3

Thirty-four PDFs, the price sheet, the forms, and six drawings were read page by page. In the two long SBB standards on civil works and earthing, the chapters that apply to the switchgear were read. The single-line diagram was read from the drawing itself. Every point links to its source page: click a page chip to see the wording on that page.

462
Pages read
11
Positions on the single-line
20
Where the documents disagree
27
Questions for the buyer
All 27 questions and 20 conflicts, with their pages, in one file.

What matters most for your price

  1. The price sheet calls for 2 "Hochführung" (riser) cells. No other document shows them: not the spec, the single-line, the floor plan, or the sections.Price sheet (B9) p.2Floor plan, building · Line-up
  2. Reserve position: the spec asks only for a prepared floor frame and the price sheet sets the quantity to 0. However, the building plans show a full-height reserve cell and the single-line shows a fully equipped one, dashed.Project spec p.8Price sheet (B9) p.2Single-line · Reserve
  3. Busbar: the spec states 2 sections, and the price sheet prices 2 busbar earthing switches. The single-line shows 3 sections and 3 earthing switches, with 2090B on a short section that no standard cell type carries.Project spec p.8Single-line · 2090B
  4. Evaluated price: the price sheet marks the total including 40-year upkeep as "VERGABERELEVANT", and its formula adds the material-renewal subtotal a second time on top of the lines it already sums.Price sheet (B9) p.2Price sheet (B9) p.2
  5. The site test is due in week 48 of 2028, but the substation does not go into service until 30.11.2029. The 3-year warranty runs from acceptance, and productive use does not count as acceptance.Contract draft p.6Safety concept p.8 · Phase planSBB terms (AGB-B) p.4

What this bid covers

Supplied by the bidder
  • Room E004: floor frame with prepared reserve positions, about 80 m² of raised floor, the transformer busbar, 2 bus-section cells (one with a circuit breaker, one with a truck only), 2 transformer cells, 5 feeder cells without a test device, and 1 auxiliary-supply cell. Tender conditions p.3
  • Room E001: floor frames for all secondary cabinets (22 at 1000 x 800 mm, 5 at 1200 x 400, 1 at 1200 x 300, and 3 at 600 x 400) and about 110 m² of raised floor. Project spec p.8
  • Both raised floors, including fixings, in stainless steel. Tender conditions p.3
  • Design, manufacture, FAT, transport, unloading, installation, SAT, and full documentation. Tender conditions p.3
  • The pressure-relief duct with its relief flap, manufactured, delivered, and installed. Project spec p.9
  • Commissioning and staff training. Contract draft p.3
  • Installing the SBB-supplied line-test device in the 5 feeder cells. Project spec p.8
  • On-site HV and partial-discharge test by FKH, and bank guarantee costs, as price lines. Price sheet (B9) p.2
  • Mobile earthing and short-circuiting sets: 2 for the busbar and 4 for the cable connections, 150 mm² Cu. SBB-EN 36-105 p.26
By others or not stated
  • The line-test device itself: a Sécheron LTD, supplied by SBB. Project spec p.8
  • Protection and station control in separate control cabinets. Only their floor frames are included in this tender. SBB-EN 36-105 p.25
  • The cable-screen bar under the cells is not in the cell supplier's scope. SBB-EN 36-105 p.12
  • Not stated: who supplies the 15 kV cables, the EB transformer 15000/230 V 25 kVA, the energy meters, and the return-current busbar in the cable cellar. Single-line · EB transformer
Rated voltage17.25 kV; the single-line says 18 kVp.12SystemSingle-phase, 16.7 Hzp.1Feeders2500 A; 2000 A not allowedp.7Short circuit40 kA, 100 kA peak, 0.5 sp.12Arc ratingIAC AFLR 40 kA 0.5 sp.14Cells10, plus a reserve positionp.1

Single-line diagram, read from the image SBB 142-1001.30

Single-line "Generelles Schema" 142-1001.30, version 1.0, dated 02.06.2025, Auflageprojekt (PGV) phase. The upper half of the sheet shows the 132 kV yard, which is not in this tender. Red means new. The dashed reserve cell has no legend entry; only its label says "Reserve". Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.

Matches the other documentsSomething to checkNot in this bidShown below
Single-line diagram

Switchgear, position by position

#PositionEquipment on the drawingFeedsChecksWhere it is written
10211021 · EigenbedarfTruck (hand crank) with fuse; no earthing switch drawnEB transformer 15000/230 V, 25 kVA, 1x 95 mm² cable4 to checkDrawing · 1021
10011001 · Aespli-SchönbühlFeeder: truck and breaker (motor-operated), CT 2000/1+1 A, VT 15000/110 V, earthing switch 1901, arrester, line-test deviceOverhead line Aespli-Schönbühl, 2 cables1 same5 to checkDrawing · 1001
40024002 · Transformer 2Infeed: truck and breaker (motor-operated), CT 2000/1+1 A, VT, earthing switch 4402, busbar earthing switch 2090A, meter boxTransformer 2, 132/16 kV, 21.8 MVA, Cu 2x 630 mm²1 same5 to checkDrawing · 4002
10021002 · GümligenFeeder: truck and breaker (motor-operated), CT 2000/1+1 A, VT 15000/110 V, earthing switch 1902, arrester, line-test deviceOverhead line Gümligen, 2 cables1 same5 to checkDrawing · 1002
20012001 · Längstrennung LSBus section: truck and circuit breaker (motor); no CT drawnJoins sections A and B1 same2 to checkDrawing · 2001
20022002 · Längstrennung TRBus section: truck with fixed link; drive unclearJoins sections B and C1 same1 to checkDrawing · 2002
10031003 · HolligenFeeder: motor-operated truck and breaker, CT 2000/1+1 A, VT 15000/110 V, earthing switch 1903, arrester, line-test deviceOverhead line Holligen, 2 cables1 same5 to checkDrawing · 1003
10041004 · Aespli-GrauholzFeeder: motor-operated truck and breaker, CT 2000/1+1 A, VT 15000/110 V, earthing switch 1904, arrester, line-test deviceOverhead line Aespli-Grauholz, 2 cables1 same5 to checkDrawing · 1004
40034003 · Transformer 3Infeed: truck and breaker (motor-operated), CT 2000/1+1 A, VT, earthing switch 4403, busbar earthing switch 2090C, meter boxTransformer 3, 132/16 kV, 21.8 MVA, Cu 2x 630 mm²1 same5 to checkDrawing · 4003
10051005 · Suberg/LyssFeeder: truck and breaker (motor-operated), CT 2000/1+1 A, VT 15000/110 V, earthing switch 1905, arrester, line-test deviceOverhead line Suberg/Lyss, 2 cables1 same5 to checkDrawing · 1005
RReserveDashed full cell; scope unclear (frame, empty cell, or more)-3 to checkDrawing · R

Where the documents disagree 20

Biggest cost impact first. Each item shows both sides and their page numbers.

1Two "Hochführung" cells: only in the price sheetHigh cost
One document says
  • Price sheet: "Feld Hochführung", quantity 2, with its own sheet (voltage indicator, earthing switch QC10). Price sheet (B9) p.2
  • SBB-EN 36-120 defines a type 16 riser cell with no switching device. SBB-EN 36-120 p.12
Another says
  • Spec and tender conditions: the cell list does not include Hochführung. Tender conditions p.3
  • Single-line: no Hochführung shown. Single-line
  • Floor plan and section G: 11 positions, from EB-Feld 1021 to Reserve; none is a riser. Floor plan, building · Line-up
Why it matters Two extra cells with enclosure, busbar, earthing switch, and LV compartment, and a longer line-up than shown on the room plan. Question 1 ↓
2Reserve: a prepared frame, an empty cell, or a full cell?High cost
One document says
  • Spec: floor frame "inklusive Reservefelder vorbereitet". Project spec p.8
  • Price sheet: "Reserve", quantity 0. Price sheet (B9) p.2
Another says
  • Single-line: a dashed, fully equipped cell (truck, AGP and breaker, CT, VT, arrester, earthing switch). Single-line · Reserve
  • Section G: a "Reserve" cell at the same height as the others. Sections, building · Section G
  • SBB-EN 36-110: reserve cells are fully fitted with a motor truck, without breaker, AGP, instrument transformers, or earthing switch. SBB-EN 36-110 p.21
Why it matters A frame only, an empty cell with a motor truck, or a near-complete cell have very different prices. The busbar end and pressure-relief duct length also depend on it. Question 2 ↓
3Busbar: 2 sections or 3, and 2 earthing switches or 3?Cost
One document says
  • Spec and tender conditions: "Trafosammelschiene mit 2 Abschnitten (A, B)". Project spec p.8
  • Price sheet: busbar earthing switch QC51 "1 Stk / Abschnitt", quantity 2. Price sheet (B9) p.2
Another says
  • Single-line: sections A, B, and C, with 2001 between A and B, 2002 between B and C, and earthing switches 2090A, 2090B, and 2090C. Single-line · Section B
  • SBB-EN 36-120: one busbar earthing switch per section. SBB-EN 36-120 p.7
Why it matters The spec's "2 sections" may mean the two transformer-fed sections, with B as the short section between the bus-section cells. Even so, the third earthing switch is real, and 2090B has no cell: the standard bus-section cell has none, and section B has no feeder. Question 3 ↓
4Evaluated price: which total to use, and a double count in the upkeep sumEvaluation
One document says
  • Tender conditions: price is scored from the completed and signed price sheet (70%, 350 points). The 40-year upkeep cost is not mentioned. Tender conditions p.13
  • Price sheet: "Total Schaltanlage" is marked "Preis (simap-Relevant)". Price sheet (B9) p.2
Another says
  • Price sheet: "Total Anlage inkl. Erhaltungskosten" is marked "VERGABERELEVANT". Price sheet (B9) p.2
  • "Summe Material erneuerung" is a yellow entry cell, and "Total Erhaltungskosten" adds it on top of the nine renewal lines it is meant to sum. Price sheet (B9) p.2
Why it matters Upkeep over 40 years (revision after 20 years, material renewals, energy at CHF 0.35/kWh) can change the ranking. A bidder who fills in the "Summe" line as labeled doubles the material-renewal cost in the evaluated total. On the summary sheet, the upkeep line is also a bidder entry, not a link. Price sheet (B9) p.2Price sheet (B9) p.1Question 4 ↓
5Auxiliary-supply cell 1021: fuse or circuit breaker, with or without earthing switch?Cost
One document says
  • Single-line: a truck with fuse 1021, no earthing switch, and no breaker. Single-line · 1021
  • SBB-EN 36-120 type 17: fuse and earthing switch -QC9, no breaker. SBB-EN 36-120 p.13
Another says
  • Price sheet, EB sheet: "Leistungsschalter -QA1", a voltage indicator, and "Erdtrenner -QC9". Price sheet (B9) p.11
Why it matters A breaker truck costs more than a fuse truck, and the earthing switch changes safety and interlocking. No fuse rating is given anywhere. Question 5 ↓
6Site test in November 2028, substation in service a year laterCost
One document says
  • Contract: raised floor delivered week 38/2028; switchgear week 40/2028; installation, function, and HV test week 48/2028. Contract draft p.6
  • Tender conditions: SAT in November 2028. Tender conditions p.4
Another says
  • Safety concept phase plan: building works until 18.09.2028, fit-out until 29.06.2029, substation commissioning from 30.11.2029. Safety concept p.8 · Phase plan
  • SBB terms: warranty claims expire 3 years after acceptance; productive use does not count as acceptance. SBB terms (AGB-B) p.4
Why it matters If acceptance follows the 2028 site test, about a third of the warranty passes before first energisation. The raised floor arrives in the last week of the building shell works. Nothing states who heats, protects, and guards the installed cells during the fit-out year. SBB terms (AGB-B) p.4Question 7 ↓
7Surge arresters: 7 or 5?Cost
One document says
  • Price sheet: "Überspannungsableiter", quantity 7. Price sheet (B9) p.2
Another says
  • Single-line: arresters on feeders 1001 to 1005 only, none on 4002, 4003, or 1021; one more shown dashed in the reserve. Single-line
  • SBB-EN 36-120: the arrester is optional "gemäss Vorgabe Generelles Schema", so the standard follows the single-line. SBB-EN 36-120 p.7
Why it matters The documents point to 5 (or 6 with the reserve); only the price sheet differs. No arrester rating is given anywhere. Question 8 ↓
8Line-test device: "AGP" on the single-line, Sécheron LTD in the specDesign
One document says
  • Project spec: SBB supplies the Sécheron LTD, and the bidder fits it into the cells. Project spec p.8
  • SBB-EN 36-120 type 12 already allows "AGP (Abzweiggebundene Prüfeinrichtung) oder LTD". SBB-EN 36-120 p.8
Another says
  • Single-line: "AGP" beside the breaker in all five feeders and in the reserve. Single-line · 1001
  • SBB-EN 36-110 and 36-105 describe only the Siemens AGP and its interface. SBB-EN 36-110 p.19
Why it matters The standards allow the LTD, so the choice is settled. An LTD data sheet and interface documents (size, weight, losses, fibre link) are missing, and nothing states who proves the type test and EMC of the cell with the LTD fitted. Question 9 ↓
9Bus section 2001: circuit breaker, but the standard cell shows a load-break switchDesign
One document says
  • Spec: "1x mit Leistungsschalter". The single-line shows breaker 2001 with a motor; the price sheet lists "Leistungsschalter -QA1x". Project spec p.8
Another says
  • SBB-EN 36-120 type 15: "Lastschalter Umleitung-SS" (load-break switch). SBB-EN 36-105 lists both a breaker and a disconnector version. SBB-EN 36-120 p.11
Why it matters There is no standard drawing for the breaker version, and nothing states whether 2001 needs CTs or protection. Question 13 ↓
10Bus section 2002: motor or hand-crank truck?Design
One document says
  • Single-line: device 2002 shows a motor "M" symbol. Single-line · 2002
  • SBB-EN 36-110: busbar disconnection by motor-driven trucks. SBB-EN 36-110 p.10
Another says
  • Single-line footnote: the truck is held by a fixed link and locked; crank out only after 2001 is off and 2090B is closed. Single-line · Footnote
  • Price sheet: "Lasche auf dem Fahrwagen". Price sheet (B9) p.9
Why it matters A motor drive changes the cell drive, control wiring, and interlocking. Question 13 ↓
11Short-time current: 40 kA for 0.5 s or 1 s?Design
One document says
  • SBB-EN 36-110: rated short-circuit duration 0.5 s for main and earthing circuits; arc rating 40 kA / 0.5 s. SBB-EN 36-110 p.12
Another says
  • SBB-EN 36-120, every cell type: earthing connection "(40kA, 1s)". SBB-EN 36-120 p.7
  • SBB-EN 36-110 device tables: "thermisch (1 s)" 40 kA. SBB-EN 36-110 p.23
Why it matters 40 kA for 1 s on the whole cell, including the earthing circuit, is a harder type test than 0.5 s. Question 14 ↓
12Rated voltage: 18 kV or 17.25 kV?Design
One document says
  • Single-line: "Sammelschiene 15 kV (18 kV 1~ / 16.7 Hz)". Single-line · Busbar
Another says
  • SBB-EN 36-110: rated voltage 17.25 kV to EN 50124-1 for all switching devices. SBB-EN 36-110 p.12
Why it matters If 18 kV is a rated-voltage requirement, standard 17.25 kV railway cells would not comply. It may only describe the highest network voltage. Question 14 ↓
13Cell height: 2600 mm on the building section, 2300 mm target in the standardDesign
One document says
  • Section H: "15 kV Schaltanlage" is 2600 mm high, with a separate pressure-relief valve above. Sections, building · Section H
Another says
  • SBB-EN 36-110: 2300 mm including the duct, to be kept "möglichst" (where possible); larger cells require SBB's written consent. SBB-EN 36-110 p.16
Why it matters This is not a hard limit: a taller cell is not excluded, but it needs written consent. The room is 5070 mm high, so room height is not the limit. Question 16 ↓
14Mobile earthing sets: is the price-sheet line additional?Cost
One document says
  • SBB-EN 36-105: 2 busbar sets (instead of 6 in 36-110) and 4 cable sets, 150 mm² Cu. 36-105 takes precedence over 36-110. SBB-EN 36-105 p.26
Another says
  • Price sheet, standard accessories: "2 Stk Y Garnituren inkl. Bedienungstange". Price sheet (B9) p.16
Why it matters The standards specify 2 + 4 sets. The only open point is whether the two "Y" sets are included or extra. Question 21 ↓
15Reference period: 10 years or 5 years?Eligibility
One document says
  • Tender conditions EK2: 2 references in service within the last 10 years, counted back from the offer date. Tender conditions p.8
Another says
  • Form B3: within the last 5 years, counted back from the month of publication. Form B3 p.1
Why it matters A bidder with references from 2017 to 2021 qualifies under one text and fails under the other. Exclusion risk. Question 18 ↓
16Award points do not add up, and the scoring sheet swaps two weightsEvaluation
One document says
  • Tender conditions: sustainability is 75 points, but its sub-criteria total 25 + 25 + 15 = 65; 7% of 500 is 35, not 25. Tender conditions p.13
Another says
  • Form B4: criterion 2.1 (10%) uses the 5% weight of 2.2, and 2.2 uses the 10% weight of 2.1. B4 also scores price as a 0-5 grade, while the conditions use a linear price formula. Form B4 p.1
Why it matters 10 points are unexplained, and the delivered sheet swaps the weights for fault analysis and fault repair. Question 19 ↓
17Spare parts: 10 years or 15 years?Cost
One document says
  • SBB terms: spare parts for ten years from acceptance. SBB terms (AGB-B) p.7
Another says
  • SBB-EN 36-110: at least 15 years (10 for protection and control). SBB-EN 36-905: 40-year life for primary equipment, with 5 years' notice before phase-out. SBB-EN 36-110 p.25
Why it matters The contract ranks the SBB terms above the standards, but the two are not mutually exclusive: 15 years meets both. Question 23 ↓
18Cable cellar is 1.7 m deep; standard requires at least 2 mDesign
One document says
  • Spec: the cellar floor is 1.7 m below the raised floor; section H shows 1700. Project spec p.5
Another says
  • SBB-EN 36-720: requires a cable cellar at least 2 m high and 3 m wide. SBB-EN 36-720 p.30
Why it matters The bidder must state the minimum floor void for its largest cable and bending radius. 630 mm² cables must bend within 1.7 m. Sections, building · Cellar 1700Question 12 ↓
19Single-line is older than the layouts and specDesign
One document says
  • Single-line: version 1.0 dated 02.06.2025, phase Auflageprojekt (PGV), with an empty revision table. Single-line · Title block
Another says
  • Building plans: version 2.0 dated 07.11.2025. Spec: version 1.1 dated 17.08.2026. Floor plan, building · Revision
Why it matters The contract gives precedence to the later document, but spec chapter 5 names the single-line as the basis for execution. The three busbar sections, the AGP labels, and the reserve may reflect an older design state. Contract draft p.3Question 20 ↓
20Delivery route to siteSite
One document says
  • Spec: heavy transport (transformers) enters and exits from Bernstrasse via Lochackerweg, which is about 4 m wide. Project spec p.5
Another says
  • Installation plan: one-way site traffic, entering via Lochackerweg and exiting via Seedorffeldstrasse. Site installation plan · Site access
Why it matters Both agree on the entry; they may cover different traffic. Key delivery details—vehicle size, axle load, and the door into room E004—are not given. Question 22 ↓
Minor errors in the documents (no cost impact)
  • The spec lists its version as 1.0, but its revision list shows 1.1. Project spec p.3
  • The spec places the pressure-relief opening "gemäss Abbildung 2", but there is no figure 2. Page 6 gives the secondary-room size under "für den IRS-Raum". Project spec p.5
  • The spec specifies CT type "15-I2 Var.B2", but SBB-EN 36-620 lists only Var. A, B* and C. SBB-EN 36-620 p.22
  • The contract refers to "Ziffer 4.9.1 Teuerung", but that clause is 4.7.1 in the tender conditions. Contract draft p.4
  • Contract annex 6 is titled "Differenzmanagement Umgang IT-Arbeitsmittel und Daten K920.1", but the file is named K 290.1. Contract draft p.14
  • Form B3, EK4: the heading is environmental management, but the text asks for quality management "(ISO 14001 oder vergleichbar)". Form B3 p.2
  • Form B1 asks for turnover in 2018 and 2019 and offers joint-venture roles, but bidding consortia are excluded. Tender conditions p.6
  • Form B5 must be returned as .docx, but it is supplied as .doc. Section 2.14 of the conditions has a heading but no text. Tender conditions p.19
  • The VT tag is "-BA1" on the single-line and in SBB-EN 36-120, but "BA5" in SBB-EN 36-105 and the price sheet. SBB-EN 36-105 p.24
  • Form B4 grade scales have gaps: exactly 2 days and exactly 12 weeks fit no grade. Form B4 p.1
  • Price sheet: "Sammelschiene Arbeitserde (1 Stk / Abschnitt)" on the small-parts sheet is not linked to the total. The row "Feld Kabelübergabekasten SS1001 und SS1003" pulls from the reserve sheet (quantity 0). Price sheet (B9) p.15

Questions for the buyer 27

Questions close on 07.12.2026, with answers by 14.12.2026. Highest cost impact first. Each has German wording ready to paste.

1Hochführung cellsThe price sheet lists "Feld Hochführung", quantity 2. The spec, single-line 142-1001.30, and building plans do not show a riser cell. Should two Hochführung cells be offered? If so, where in the line-up and for what purpose?
German wording for your offer

Das Preisblatt (Register Anlage) enthält «Feld Hochführung» mit Menge 2. Weder die Anforderungsspezifikation noch das Generelle Schema 142-1001.30 noch die Grundriss- und Schnittpläne Gebäude zeigen Hochführungsfelder. Sind zwei Hochführungsfelder anzubieten? Falls ja, an welcher Position und wofür?

Price sheet (B9) p.2Floor plan, building · Line-up
2Reserve positionThe spec requires a floor frame "inklusive Reservefelder vorbereitet", while the price sheet sets "Reserve" to 0. The building plans show a full reserve cell, and the single-line shows a fully equipped cell in dashed lines. Should only the floor frame be supplied, or a reserve cell per SBB-EN 36-110 5.5.5 or 36-120 type 20? Should the busbar extend into the reserve position?
German wording for your offer

Die Spezifikation nennt «Bodenrahmen (inklusive Reservefelder vorbereitet)», das Preisblatt die Position «Reserve» mit Menge 0. Die Grundriss- und Schnittpläne Gebäude zeigen ein Reservefeld in der Zellenreihe, das Generelle Schema ein voll ausgerüstetes Reservefeld (gestrichelt). Ist für die Reserve nur der Bodenrahmen zu liefern oder eine Reservezelle gemäss SBB-EN 36-110 Kap. 5.5.5 bzw. SBB-EN 36-120 Typ 20? Ist die Sammelschiene bis in die Reserveposition zu führen?

Project spec p.8Price sheet (B9) p.2Single-line · Reserve
3Busbar sections and earthing switchesThe spec and tender conditions specify a transformer busbar "mit 2 Abschnitten (A, B)". The single-line shows sections A, B, and C with bus sections 2001 (A|B) and 2002 (B|C) and three busbar earthing switches 2090A/B/C; the price sheet lists 2 busbar earthing switches. How many sections and busbar earthing switches must be supplied, and in which cell must 2090B be fitted?
German wording for your offer

Die Anforderungsspezifikation (Kap. 5) und die Ausschreibungsbedingungen (Kap. 1.2) nennen eine «Trafosammelschiene mit 2 Abschnitten (A, B)». Das Generelle Schema 142-1001.30 zeigt drei Abschnitte A, B, C mit den Längstrennungen 2001 (A|B) und 2002 (B|C) sowie drei SS-Erdungstrenner 2090A/B/C; das Preisblatt (Pos. «Sammelschiene Erdungstrenner QC51») nennt 2 Stück. Bitte bestätigen Sie die Anzahl Sammelschienenabschnitte und SS-Erdungstrenner und geben Sie an, in welcher Zelle 2090B einzubauen ist.

Project spec p.8Price sheet (B9) p.2Single-line · Section B
4Evaluated price and maintenance costThe price sheet marks "Total Schaltanlage" as "Preis (simap-Relevant)" and "Total Anlage inkl. Erhaltungskosten" as "VERGABERELEVANT". Which total is scored for ZK1? On sheet Anlage, "Total Erhaltungskosten" (F72) adds entry cell "Summe Material erneuerung" (F68) on top of renewal lines F57 to F67. Should F68 be left empty, or will the formula be corrected? Which loads count in the energy line (heating, control, lighting)?
German wording for your offer

Im Preisblatt ist «Total Schaltanlage» als «Preis (simap-Relevant)» und «Total Anlage inkl. Erhaltungskosten» als «VERGABERELEVANT» bezeichnet. Welcher Betrag wird für ZK1 Preis bewertet? Im Register Anlage summiert «Total Erhaltungskosten» (F72) die Eingabezelle «Summe Material erneuerung» (F68) zusätzlich zu den Einzelpositionen F57 bis F67. Ist F68 leer zu lassen, oder wird die Formel korrigiert? Welche Verbraucher sind in den «Energieverbrauch (40 Jahre Dauerbetrieb @ CHF 0.35/kWh)» einzurechnen (Heizung, Steuerung, Beleuchtung)?

Price sheet (B9) p.2Price sheet (B9) p.2
5Auxiliary-supply cell 1021The single-line shows a truck with an HV fuse and no outgoing earthing switch. SBB-EN 36-120 type 17 shows a fuse with earthing switch -QC9. The price sheet (EB sheet) lists "Leistungsschalter -QA1", a voltage indicator, and "Erdtrenner -QC9". Is a fuse or circuit breaker required, with or without -QC9? What is the fuse rating? SBB-EN 36-620 assigns a 15-I3 CT to the auxiliary supply, but none is shown on the drawing. Is a CT required?
German wording for your offer

Eigenbedarfsfeld 1021: Das Generelle Schema zeigt einen Fahrwagen mit HS-Sicherung ohne Abgangserdungstrenner; SBB-EN 36-120 Typ 17 zeigt eine Sicherung mit Erdungstrenner -QC9; das Preisblatt (Register EB-Trafo) nennt «Leistungsschalter -QA1», «Kapazitiver Spannungsanzeiger» und «Erdtrenner -QC9». Bitte bestätigen Sie die Ausführung (Sicherung oder Leistungsschalter, mit oder ohne -QC9) und den Bemessungsstrom der Sicherung. SBB-EN 36-620 sieht für den Eigenbedarf einen Stromwandler 15-I3 vor; im Schema ist keiner dargestellt. Ist ein Stromwandler vorzusehen?

Single-line · 1021Price sheet (B9) p.11SBB-EN 36-620 p.22
615 kV cables and terminationsAre the 15 kV cables, 36 kV indoor terminations, and cable connections in the cells part of this order? Please state the cable quantity, size, and type per cell. The single-line shows 2 cables without a size for the feeders, Cu 2x 630 mm² for the transformers, and 1x 95 mm² for the auxiliary supply. SBB-EN 36-110 requires space for up to 4 cables, whereas the 36-120 cell types allow at most 3 x 630 mm². Which applies?
German wording for your offer

Sind die 15-kV-Kabel, die 36-kV-Innenraum-Endverschlüsse und das Anschliessen der Kabel in den Zellen Bestandteil dieses Auftrags? Bitte geben Sie Anzahl, Querschnitt und Typ der Kabel je Feld an (Schema: Speisepunkte 2 Kabel ohne Querschnitt, Trafofelder Cu 2x 630 mm², Eigenbedarf 1x 95 mm²). SBB-EN 36-110 verlangt Platz für bis zu 4 Kabel, die Zellentypen in SBB-EN 36-120 lassen maximal 3 x 630 mm² zu. Was gilt?

SBB-EN 36-105 p.12SBB-EN 36-110 p.18Single-line
7Acceptance, warranty, and the year before energisationThe contract sets installation, function, and HV testing for week 48/2028, while the safety concept phase plan sets substation commissioning for 30.11.2029. When does acceptance occur under AGB-B section 12, and does the 3-year warranty start at the 2028 site test or at the 2029 commissioning? Who keeps the cells heated, dust-protected, and guarded in the meantime? Will the building be dust-free and lockable when the raised floor arrives in week 38/2028?
German wording for your offer

Gemäss Werkvertrag ist die «Erfolgreiche Montage, Funktionsprüfung und HS-Prüfung» in KW 48/2028 fällig, die Inbetriebnahme des UW gemäss Phasenplan (Sicherheitskonzept, Abb. 2) am 30.11.2029. Wann erfolgt die Abnahme gemäss AGB-B Ziff. 12, und beginnt die Gewährleistung (3 Jahre) mit der SAT 2028 oder mit der Inbetriebnahme 2029? Wer stellt zwischen Montage und Inbetriebnahme Zellenheizung, Staubschutz und Bewachung sicher? Ist das Gebäude bei Lieferung des Doppelbodens (KW 38/2028) staubfrei und verschliessbar?

Contract draft p.6Safety concept p.8 · Phase planSBB terms (AGB-B) p.4
8Surge arrestersThe price sheet lists 7 surge arresters, while the single-line shows them only in the 5 feeders (and dashed in the reserve), not in transformer cells 4002 and 4003. Please confirm the quantity, locations, and ratings (Uc, nominal discharge current, energy class).
German wording for your offer

Das Preisblatt nennt 7 Überspannungsableiter; das Generelle Schema zeigt Ableiter nur in den 5 Speisepunkten (und gestrichelt in der Reserve), nicht in den Trafofeldern 4002/4003. Bitte bestätigen Sie Anzahl, Einbauorte und Bemessungsdaten (Uc, Nennableitstossstrom, Energieklasse) der Ableiter.

Price sheet (B9) p.2Single-line
9Line-test device (LTD)Spec 5.2 names the Sécheron LTD, supplied by SBB, and SBB-EN 36-120 type 12 allows "AGP/ LTD", while the single-line still labels "AGP" in feeders 1001 to 1005. Please confirm the LTD for all 5 feeders and provide its data sheet plus mounting and interface documents (dimensions, weight, losses, fibre communication, and any booster as in the price sheet "Inkl. LWL Booster"). Who provides the type-test and EMC evidence for the cell with the LTD fitted?
German wording for your offer

Gemäss Spezifikation Kap. 5.2 wird die von der SBB beigestellte LTD von Sécheron verwendet, und SBB-EN 36-120 Typ 12 lässt «AGP/ LTD» zu; das Generelle Schema nennt in den Speisepunkten 1001–1005 jedoch «AGP». Bitte bestätigen Sie die LTD für alle 5 Speisepunkte und stellen Sie Datenblatt sowie Einbau- und Schnittstellenunterlagen der LTD zur Verfügung (Abmessungen, Gewicht, Verlustleistung, Kommunikation/LWL, allfälliger Booster gemäss Preisblatt «Inkl. LWL Booster»). Wer erbringt die Typprüf- und EMV-Nachweise für die Kombination Zelle/LTD?

Project spec p.8SBB-EN 36-120 p.8
10Meters, protection and LV equipmentAre the energy meters (WPS/WQS) shown in transformer cells 4002 and 4003, the protection devices, and the bay controllers part of the supply? What equipment goes into each cell's LV compartment, and which control voltage applies (220 VDC or 110 VDC per SBB-EN 36-105)?
German wording for your offer

Gehören die im Schema in den Trafofeldern 4002/4003 dargestellten Energiezähler (WPS/WQS), die Schutzgeräte und die Feldleitgeräte zum Lieferumfang? Welche Ausrüstung ist im Niederspannungsraum jeder Zelle vorzusehen, und welche Steuerspannung gilt (220 VDC oder 110 VDC gemäss SBB-EN 36-105)?

Single-line · 4002SBB-EN 36-105 p.12
11Return busbar, screen bars and earthing conceptWho supplies and installs the return-current busbar in the cable cellar (spec 4.5) and the cable-screen bars under the cells, which SBB-EN 36-105 excludes from the cell supplier's scope? Must the switchgear bidder submit the outline earthing diagram per SBB-EN 36-170 7.1 with the offer?
German wording for your offer

Wer liefert und installiert die Rückleitersammelschiene im Kabelkeller (Spezifikation Kap. 4.5: «Zusätzlich muss darin eine Rückleitersammelschiene installiert werden») und die Kabelschirmschienen unter den Zellen (SBB-EN 36-105 Kap. 5.3: «nicht im Lieferumfang des Zellenlieferanten»)? Ist das einpolige Prinzipschaltbild für die Erdung gemäss SBB-EN 36-170 Kap. 7.1 vom IRS-Anbieter mit dem Angebot einzureichen?

Project spec p.5SBB-EN 36-105 p.12SBB-EN 36-170 p.68
12Raised floorsPlease confirm the raised-floor heights (switchgear room over a 1.7 m cable cellar; secondary room 0.4 m), the load rating (SBB-EN 36-720: at least 10 kN/m²), stainless steel for pedestals, frames, and panels, and that the switchgear-room floor is a raised structure over the cellar. Is the 1.7 m cellar (2 m in SBB-EN 36-720) accepted for the bending radius of 1x 630 mm² cables?
German wording for your offer

Doppelboden: Bitte bestätigen Sie die Höhe (IRS-Raum über einem Kabelkeller von 1,7 m; Sekundärraum 0,4 m), die Nutzlast (SBB-EN 36-720: mindestens 10 kN/m²), die Ausführung in rostfreiem Stahl auch für Ständer, Rahmen und Platten sowie die aufgeständerte Konstruktion über dem Kabelkeller im IRS-Raum. Ist der Kabelkeller mit 1,7 m Höhe (statt 2 m gemäss SBB-EN 36-720 Kap. 6.4.1) für die Biegeradien von 1x 630 mm²-Kabeln freigegeben?

Project spec p.8SBB-EN 36-720 p.31SBB-EN 36-720 p.30
13Bus-section cells 2001 and 2002Cell 2001: Are CTs or protection needed for breaker 2001 (none shown)? Is a vacuum circuit breaker per SBB-EN 36-105 5.6 (2500 A) required instead of the load-break switch in SBB-EN 36-120 type 15? Cell 2002: Is the truck motor-driven ("M" at device 2002) or manual only (footnote: "Fahrwagen mit Lasche festgesetzt und verriegelt")?
German wording for your offer

Längstrennung 2001: Sind für den Leistungsschalter 2001 Stromwandler bzw. Schutz vorzusehen (im Schema nicht dargestellt)? Gilt für 2001 ein Vakuum-Leistungsschalter gemäss SBB-EN 36-105 Kap. 5.6 (2500 A) anstelle des Lastschalters in SBB-EN 36-120 Typ 15? Längstrennung 2002: Ist der Fahrwagen motorisch verfahrbar (Symbol «M» am Gerät 2002) oder nur manuell («Fahrwagen mit Lasche festgesetzt und verriegelt», Kurbelsymbol bei 2002W)?

SBB-EN 36-120 p.11Single-line · 2002Single-line · Footnote
14RatingsPlease confirm the switchgear ratings: Ur 17.25 kV (SBB-EN 36-110) or 18 kV (single-line: "Sammelschiene 15 kV (18 kV 1~ / 16.7 Hz)"); rated short-time current 40 kA for 0.5 s (SBB-EN 36-110) or 1 s (SBB-EN 36-120: "(40kA, 1s)"); busbar 2500 A; and transformer cells 2000 A or 2500 A.
German wording for your offer

Bitte bestätigen Sie die Bemessungsdaten der Schaltanlage: Ur = 17,25 kV (SBB-EN 36-110) oder 18 kV (Generelles Schema «Sammelschiene 15 kV (18 kV 1~ / 16.7 Hz)»); Bemessungs-Kurzzeitstrom 40 kA mit tk = 0,5 s (SBB-EN 36-110) oder 1 s (SBB-EN 36-120 «Erdungsanschluss Zelle ... (40kA, 1s)»); Sammelschiene 2500 A; Trafofelder 2000 A oder 2500 A.

SBB-EN 36-110 p.12SBB-EN 36-120 p.7Single-line · Busbar
15CT typeSpec 5.1 lists CT type "15-I2 Var.B2", while SBB-EN 36-620 table 6 lists only 15-I2 Var. A, B*, and C. Please confirm Var. B* (2000/1 A, thermal factor 125%) for transformer cells and feeders.
German wording for your offer

Die Spezifikation (Kap. 5.1) nennt für die Stromwandler «15-I2 Var.B2». SBB-EN 36-620 Tabelle 6 kennt nur 15-I2 Var. A, B* und C. Bitte bestätigen Sie Var. B* (2000/1 A, thermischer Dauergrenzstromfaktor 125 %) für Trafofelder und Speisepunkte.

Project spec p.8SBB-EN 36-620 p.22
16Cell height and pressure reliefSection H shows the 15 kV switchgear at 2600 mm high with a separate pressure-relief valve. SBB-EN 36-110 5.1 requests 2300 mm including the duct where possible, with larger sizes requiring written consent. Is a cell height above 2300 mm accepted, and up to what limit? Spec 4.5 locates the relief opening "gemäss Abbildung 2", which is missing from the spec. Please provide the position and size of the facade opening and the relief flap.
German wording for your offer

Der Schnittplan Gebäude (Schnitt H) zeigt die 15-kV-Schaltanlage mit 2600 mm Höhe und separatem Druckentlastungsventil. SBB-EN 36-110 Kap. 5.1 nennt eine möglichst einzuhaltende Höhe von 2300 mm inkl. Druckentlastungskanal; grössere Abmessungen bedürfen der schriftlichen Zustimmung. Wird eine Zellenhöhe über 2300 mm akzeptiert, und bis zu welcher Höhe? Die Spezifikation (Kap. 4.5) verweist für die Druckentlastungsöffnung auf «Abbildung 2», die nicht vorhanden ist. Bitte geben Sie Lage und Abmessungen der Fassadenöffnung und der Druckentlastungsklappe an.

Sections, building · Section HSBB-EN 36-110 p.16Project spec p.5
17FAT and SAT checklists, FKH testPlease provide the SBB FAT and SAT checklists referenced in SBB-EN 36-105 2.5 and spec chapter 7. Is the "HS + TE Prüfung und Abnahme durch FKH" in the price sheet performed on site on the installed switchgear, and who contracts FKH?
German wording for your offer

Bitte stellen Sie die in SBB-EN 36-105 Kap. 2.5 und Spezifikation Kap. 7 genannten SBB-Checklisten für FAT und SAT zur Verfügung. Ist die «HS + TE Prüfung und Abnahme durch FKH» (Preisblatt) vor Ort an der montierten Anlage durchzuführen, und wer beauftragt die FKH?

Project spec p.9Price sheet (B9) p.2
18Reference periodEK2: The tender conditions require references "in den vergangenen 10 Jahren, rückwirkend ab dem Datum des Angebotseingangs", while form B3 requires "in den vergangenen 5 Jahren, rückwirkend ab dem Monat der Publikation". Which period applies?
German wording for your offer

EK2: Die Ausschreibungsbedingungen verlangen Referenzen «in den vergangenen 10 Jahren, rückwirkend ab dem Datum des Angebotseingangs», das Formular B3 «in den vergangenen 5 Jahren, rückwirkend ab dem Monat der Publikation». Welche Frist gilt?

Tender conditions p.8Form B3 p.1
19Award pointsZK3 is allocated 75 points, but its sub-criteria total 65 (3.1: 7% is shown as 25 points). In form B4, cells I10 and I11 swap the weights of 2.1 and 2.2, and price is scored as a 0-5 grade while the conditions use a linear formula. Please confirm the points per sub-criterion and the price formula.
German wording for your offer

Zuschlagskriterien: ZK3 ist mit 75 Punkten angegeben; die Subkriterien ergeben 65 Punkte (3.1: 7 % = 25 Punkte?). In der Excel-Datei B4 sind in I10/I11 die Gewichte von 2.1 und 2.2 vertauscht, und der Preis wird als Note 0–5 bewertet, während die Ausschreibungsbedingungen eine lineare Preisformel vorsehen. Bitte bestätigen Sie die massgebenden Punktzahlen je Subkriterium und die Preisformel.

Tender conditions p.13Form B4 p.1
20Single-line versionSingle-line 142-1001.30 is version 1.0 dated 02.06.2025 (Auflageprojekt PGV); the building plans are version 2.0 dated 07.11.2025. Is the single-line the valid basis for the offer?
German wording for your offer

Das Generelle Schema 142-1001.30 hat die Version 1.0 vom 02.06.2025 (Auflageprojekt PGV), die Grundriss- und Schnittpläne Gebäude die Version 2.0 vom 07.11.2025. Ist das Generelle Schema der gültige Stand für das Angebot?

Single-line · Title blockFloor plan, building · Revision
21Mobile earthing setsSBB-EN 36-105 chapter 8 requires 2 busbar and 4 cable earthing and short-circuiting sets. Are the "2 Stk Y Garnituren inkl. Bedienungstange" on the price sheet part of these, or additional?
German wording for your offer

SBB-EN 36-105 Kap. 8 verlangt 2 mobile Erdungs- und Kurzschliesseinrichtungen für die Sammelschiene und 4 für die Kabelanschlüsse. Sind die im Preisblatt (Standardzubehör) aufgeführten «2 Stk Y Garnituren inkl. Bedienungstange» darin enthalten oder zusätzlich zu liefern?

SBB-EN 36-105 p.26Price sheet (B9) p.16
22Delivery and accessSpec 4.2 (entry and exit via Lochackerweg) and the installation plan (one-way, exit via Seedorffeldstrasse) differ. What maximum vehicle length and axle load are allowed, what door opening (width x height) is available to move the cells into room E004, and may the "300 m² für Primärtechnik" on the installation plan be used for storage?
German wording for your offer

Anlieferung: Spezifikation Kap. 4.2 (Zu- und Wegfahrt über den Lochackerweg) und Installationsplan (Einbahnregime, Wegfahrt über die Seedorffeldstrasse) weichen voneinander ab. Welche maximale Fahrzeuglänge und Achslast sind zulässig? Welche Türöffnung (Breite x Höhe) steht für die Einbringung der Zellen in Raum E004 zur Verfügung, und kann die Fläche «300 m² für Primärtechnik» (Installationsplan) als Lagerfläche genutzt werden?

Project spec p.5Site installation plan · Site accessSite installation plan · Laydown area
23Spare parts and trainingWhich spare-parts period applies: ten years per the SBB terms or 15 years per SBB-EN 36-110? How many trainees and training sessions must be planned (SBB-EN 36-105 chapter 10: at least two sessions, paper documents per participant)?
German wording for your offer

Bitte bestätigen Sie die massgebende Ersatzteil-Lieferdauer (AGB-B: 10 Jahre; SBB-EN 36-110: 15 Jahre). Wie viele Schulungsteilnehmer und Schulungssequenzen sind vorzusehen (SBB-EN 36-105 Kap. 10: mindestens zwei Sequenzen, Papierunterlagen pro Teilnehmer)?

SBB terms (AGB-B) p.7SBB-EN 36-110 p.25SBB-EN 36-105 p.28
24Helicopter landing siteSafety concept 7.4.3 requires contractors to set up and maintain helicopter rescue landing sites. Does this apply to the switchgear supplier, or does SBB or overall site management provide a shared landing site?
German wording for your offer

Sicherheitskonzept Kap. 7.4.3 (S. 30): «Zu Rettungszwecken sind von den Auftragnehmern Helikopterlandeplätze einzurichten und vorzuhalten.» Gilt dies auch für den IRS-Lieferanten, oder stellt die SBB bzw. die Gesamtbauleitung einen gemeinsamen Landeplatz?

Safety concept p.30
25EB transformerWho supplies the 15000/230 V, 25 kVA auxiliary transformer (single-line "01", floor plan "16.7 Hz EB-Trafo") and its 1x 95 mm² cable? It is located in room E004 but is missing from the scope list.
German wording for your offer

Wer liefert den EB-Transformator 15000/230 V, 25 kVA (Schema «01», Grundriss «16.7 Hz EB-Trafo») und das Verbindungskabel 1x 95 mm²? Der Transformator steht im IRS-Raum E004, ist aber nicht im Lieferumfang aufgeführt.

Single-line · EB transformerFloor plan, building · EB-Trafo
26Missing referenced documentsThe following documents referenced in the tender are missing from the package: SBB-EN 36-906 (cell labelling), 36-111/36-112 (test devices), 36-526/36-527 (supply voltage), 36-505/36-506/36-605 (local control, protection), 20-001 (dimensioning), 30-001 (AKS), 36-910 (categories), RTE 27900 (earthing handbook), the AGP annexes to 36-110, and the project AKS lists. Please provide them or confirm they do not affect the offer.
German wording for your offer

Folgende in den Ausschreibungsunterlagen referenzierten Dokumente fehlen: SBB-EN 36-906 (Zellenbeschriftung), 36-111/36-112 (Prüfeinrichtungen), 36-526/36-527 (Spannungsversorgung), 36-505/36-506/36-605 (Lokalsteuerung, Schutz), 20-001 (Dimensionierung), 30-001 (AKS), 36-910 (Kategorisierung), RTE 27900 (Erdungshandbuch), die AGP-Anlagen zu SBB-EN 36-110 sowie die projektspezifischen AKS-Listen. Bitte stellen Sie diese zur Verfügung oder bestätigen Sie, dass sie für das Angebot nicht massgebend sind.

SBB-EN 36-105 p.4SBB-EN 36-105 p.14
27Clerical pointsPlease confirm or correct: spec version 1.0 or 1.1; missing "Abbildung 2"; secondary-room size labelled "für den IRS-Raum"; contract 3.2 citing "Ziffer 4.9.1" (should be 4.7.1); contract annex 6 name (K920.1 vs. file K 290.1); form B3 EK4 listing quality management for ISO 14001; form B1 requesting 2018/2019 turnover and joint-venture roles even though consortia are excluded (which years apply?); B5 supplied as .doc but requested as .docx; section 2.14 of the conditions is empty; VT tag BA1 or BA5; grading gaps in B4 at 2 days and 12 weeks.
German wording for your offer

Bitte bestätigen bzw. korrigieren Sie folgende Punkte: Spezifikation Version 1.0 oder 1.1; fehlende «Abbildung 2»; Masse des Sekundärtechnikraums als «für den IRS-Raum» bezeichnet; Werkvertrag Ziff. 3.2 verweist auf «Ziffer 4.9.1» (gemeint: 4.7.1); Bezeichnung Anhang 6 (K920.1 gegenüber Datei K 290.1); Formular B3 EK4 spricht von Qualitätsmanagement bei ISO 14001; Formular B1 fragt Umsätze 2018/2019 und ARGE-Rollen ab, obwohl Bietergemeinschaften ausgeschlossen sind (welche Geschäftsjahre gelten?); B5 liegt als .doc vor, verlangt ist .docx; Ziff. 2.14 der Ausschreibungsbedingungen ist leer; Bezeichnung Spannungswandler BA1 oder BA5; Notenlücken in B4 bei 2 Kalendertagen und 12 Wochen.

Project spec p.3Contract draft p.4Form B3 p.2Tender conditions p.19

Requirements to meet

31 · 11 to clarify
RequirementStatusNotePage
Submit offer on SAP Ariba by 19.01.2027, 15:00. Valid for 6 months. Prices DDP Unterwerk Zollikofen in CHF, EUR, or USD.RequiredTender conditions p.4
No reservations to the draft contract or SBB terms are allowed; any reservation excludes the offer.To clarifyCovers penalties, liability, and guarantees on first demand.Tender conditions p.17
Bidding consortia are excluded; subcontractors are allowed.RequiredTender conditions p.6
Award criteria: price 70% (350 points), fault-analysis time 10%, fault-repair time 5%, transport CO2 7%, renewable energy 5%, sustainable manufacturing 3%.To clarifyPoints do not add up; see the award question.Tender conditions p.13
Qualification EK1 to EK7: ISO 9001 via SAP Ariba, 2 references for 16.7 Hz indoor switchgear in service, guarantor confirmation, ISO 14001 or comparable, staff and capacity, service organization, and supply-chain table.To clarifyReference period is disputed (10 or 5 years).Tender conditions p.8
Signed acceptance of the project spec and SBB-EN 36-105.RequiredTender conditions p.11
Average fault analysis: at most 22 calendar days; average fault repair: at most 25 weeks. Both are also scored.RequiredTender conditions p.11
Contract order of precedence: contract deed, SBB terms, clarification results, offer, and tender with spec; within a group, the later document prevails.RequiredSets the documentation copies (2 paper + 1 USB) and ranks SBB terms above the standards.Contract draft p.3
Dates: execution drawings week 44/2027, FAT week 35/2028, raised floor DDP week 38/2028, switchgear DDP week 40/2028, installation and HV test week 48/2028, and final documents week 05/2029.RequiredContract draft p.6
Delay penalties are 2.5% per week: engineering up to 10% of the engineering fee; delivery up to 5%; installation up to 5% (10% if no delivery penalty was charged).To clarifyCommercial risk to include in the price.Contract draft p.6
Payment: engineering 100% after document approval; plant 20% at order (with down-payment guarantee), 30% after FAT, 30% after site acceptance, and 20% at final acceptance.RequiredContract draft p.5
Guarantees: down payment 100%; performance guarantee valid for 3 years plus 6 months after acceptance; guarantor rated at least A (S&P) or A2 (Moody's); guarantee costs must be shown separately.RequiredTender conditions p.6
Warranty: 3 years from acceptance; spare parts for 10 years.To clarifySBB-EN 36-110 asks for 15 years for spares.SBB terms (AGB-B) p.4
EcoVadis rating within 6 months at your own cost; PFAS limits per form B11.RequiredContract draft p.13
Include with the offer: exact scope, data sheets, dimension drawings, weights, layouts (.pdf and .dwg), spare-parts and special-tool lists, schedule, training, day rates, form B5, and all operation-relevant components with delivery times and prices.RequiredTender conditions p.18
SBB-EN 36-105 ranks above 36-110; cell types per SBB-EN 36-120; instrument transformers per SBB-EN 36-620.RequiredSBB-EN 36-105 p.6
Ur 17.25 kV, Ik 40 kA, Ip 100 kA, 0.5 s; busbar 2500 A; infeed 2000 A; IAC AFLR 40 kA 0.5 s; LSC2B, PM.To clarifyThe single-line states 18 kV; 36-120 states 1 s.SBB-EN 36-110 p.12
Feeders: 2500 A ("2000A ist nicht zulässig"); vacuum breakers: 2500 A, EN 50152-1 class 3, over 10,000 operations.RequiredSBB-EN 36-105 p.7
Keep cell size where possible: 2300 mm height including the duct; larger sizes require SBB's written consent.To clarifyThe building section shows 2600 mm.SBB-EN 36-110 p.16
Pressure-relief duct from the entire switchgear to the facade, with spring flap and grille, is in the supplier's scope.RequiredSBB-EN 36-105 p.9
Stainless-steel raised floors including fixings; at least 10 kN/m², earthed, and seismically braced.To clarifyBuilt over a 1.7 m cellar.SBB-EN 36-720 p.31
Earthing switches operated by hand crank only; motor-driven trucks; 48-pole Harting plug; electronic control only with SIL 2.RequiredSBB-EN 36-105 p.15
CT 15-I2 and VT 15-U1 per SBB-EN 36-620; instrument-transformer type-test reports from an independent lab submitted with the offer.To clarifyThe spec says "Var.B2", which does not exist.SBB-EN 36-620 p.26
FAT at the factory; SAT and final acceptance on site per SBB checklist, with SBB staff present.To clarifyChecklists are not in the package.Project spec p.9
Type tests at 16.7 Hz in an independent accredited lab; reports in English and German.RequiredSBB-EN 36-110 p.25
Climate: +5 to +40 °C; seismic zone 1b per SIA 261; halogen-free plastics; 40-year design life.RequiredProject spec p.7
Documentation in German per SBB-EN 36-915: 2 paper copies and 1 USB stick per document type.RequiredProject spec p.9
Training: at least two sessions in German.RequiredSBB-EN 36-105 p.28
Line-test device: Sécheron LTD, supplied by SBB and installed by the bidder.To clarifyNo LTD data is in the package.Project spec p.8
Terminals and plugs: Harting 48-pole; terminals "z.B." Phoenix or WAGO (examples only).RequiredSBB-EN 36-105 p.9
HV and partial-discharge test by FKH as a price line.RequiredPrice sheet (B9) p.2

Not in the package

Want a review like this for a bid you are pricing? Book a call.