VA 36C24426R0088: Upgrade Substation Bldg 2, Phase I, Philadelphia VA Medical Center

US Department of Veterans Affairs, solicitation 36C24426R0088, project 642-22-104. This construction contract is set aside for service-disabled veteran-owned small businesses. It includes three new 1500 kVA, 13.2 kV to 480Y/277 V dry-type unit substations, each with a duplex 15 kV fused load-interrupter switch and a 2500 A switchboard. Documents are in English.

Offer due Mon 7 Dec 2026, 4:00 PM ESTAmendment 0004 p.1Questions closed No RFIs after Amendment 0004Amendment 0004 p.1Magnitude $5,000,000 to $10,000,000Solicitation p.1Period 1,000 calendar days from notice to proceedAmendment 0003 p.1

42 files and 1,350 pages total, counting Word files converted to PDF. The 25 drawings, four amendments, both sets of RFI answers, statement of work, and solicitation were read in full. The 597-page specification was read in full for Division 26 and relevant Division 01 parts, and the medical-center safety policies were searched by keyword. Single-lines and schedules were read from the drawing image. Every point links to its source page: click a chip to see the wording on the page.

The question window has closed. Amendment 0004, effective 20 Nov 2026, states that no more RFIs will be accepted, and the package lists no other way to ask questions before the 7 Dec deadline. Settle the points below with the general contractor you are quoting, or state them as assumptions with your price. Where the drawings and specification conflict, the statement of work states that the specification governs, followed by the authority having jurisdiction. Amendment 0004 p.1Statement of work p.2
1350
Pages read
21
Positions on the single-line
8
Where the documents disagree
22
Points for your quote
All 22 questions and 8 conflicts, with their pages, in one file.

What matters most for your price

  1. Transformer construction: Specification 26 11 16 requires a cast-coil transformer in one paragraph and a VPI transformer in the next, both using "Provide". For three 1500 kVA units, this creates a major difference in price and lead time, and nothing in the package resolves it.Specification p.472Specification p.472
  2. LV main breaker: The specification describes only a molded-case main, while E-107 shows all three 2500 A mains as drawout breakers. A drawout main above 1600 A must also be electrically operated.Specification p.495E-001 symbols and legend
  3. Short-circuit ratings: The MV switch requires 61 kA momentary and 48 kA 2-second ratings, while the 2023 study shows about 6.3 to 6.6 kA at 13.2 kV. The specification also calls the substations "metal-clad", even though the switch section is a metal-enclosed fused interrupter.Specification p.481Campus 13.2 kV one-line, 2023 studySpecification p.471
  4. Equipment origin: The solicitation includes both Buy American clause 52.225-9 and trade-agreements clause 52.225-11. Which clause applies determines whether non-US switchgear and transformers are acceptable.Solicitation p.35Solicitation p.39
  5. Substation T switchboard: E-107 shows 20 spare feeders, while E-108 schedules 17. E-108 includes a frame for every Substation #2 load moving to T and is the schedule referenced by other sheets. Price E-108 plus the one 100 A to 150 A change from RFI 1; only the plug ratings differ.E-108 schedules and elevations · plugsRFI 1 answers p.5

What this bid covers

Supplied by the bidder
  • Two new 480/277 V substations, each with a 1500 kVA transformer, replacing existing Substations 1 and 2. Statement of work p.1
  • A third, temporary 1500 kVA substation "T" that carries loads during construction and remains as a spare: price Option 2 only, with a permanent wall (RFI 2 Q10). RFI 2 answers p.1
  • All three units purchased by the contractor and stored off-site in conditioned, insured space before construction. RFI 1 answers p.18
  • Per substation: a duplex 15 kV load-interrupter fusible switch with key interlocks, a 13.2 kV delta to 480Y/277 V transformer, a 2500 A main breaker, a digital meter, and a 400 kA type 2 surge protector. E-107 single-line, new work · note 2
  • Duplex selector switches on all three substations in the base bid, with no optional pricing. RFI 1 answers p.7
  • New 15 kV cables and tap boxes on existing feeders #12 and #19, with Eaton Cleer load-break connectors. E-105 MV conduit routing
  • Short-circuit, coordination, and arc-flash study prepared by the equipment manufacturer, with trip settings applied by the switchboard manufacturer. Specification p.459
  • Return of all existing breakers from Substations 1 and 2 to the VA. Statement of work p.1
By others or not stated
  • The existing PECO 15 kV service switchgear in Building 6 remains; feeders FDR12 and FDR19 supply the new substations. E-107 single-line, new work
  • All panelboards in the work area are existing. Specification p.501
  • Commissioning agent: hired by the VA under a separate contract. Specification p.162
  • Materials testing laboratory: retained by the VA. Specification p.108
  • Opening and closing the existing MV switches: the VA electric shop and the contractor. RFI 1 answers p.10
  • Utility demarcation is at Building 6. RFI 1 answers p.7
  • Existing ATS #1 is relocated, not replaced. E-107 single-line, new work
Supply13.2 kV, 3 phase, from Building 6 feeders #12 or #19p.1Transformer1500 kVA dry type, delta / 480Y/277 Vp.1MV switch15 kV, 600 A duplex selector, one 90E fusep.1MV ratings in the spec61 kA momentary, 48 kA 2 sp.481Switchboard480Y/277 V, 2500 A, 50 kAIC, free standingp.1Surge protector400 kA, type 2p.1

Single-line diagram, read from the image E-107 · E-108 · E-106

Drawing E-107, "Single line risers - Substations #1, #2 and "T" - new work", bid documents dated 21 Oct 2024. The PDF sheet is sideways; it is shown upright here. (E) is existing, (ER) is relocated, and (N) is new to match existing. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.

Matches the other documentsSomething to checkNot in this bidShown below
Single-line diagram

Switchgear, position by position

Substations #1, #2, and "T", new work

#PositionEquipment on the drawingFeedsChecksWhere it is written
1MSubstation #1 MV2 x 15 kV, 600 A load-interrupter switch, key-interlocked, 1 x 90E fuseSubstation #1 transformer, 1500 kVA1 same5 to checkDrawing · 1M
1TSubstation #1 transformer1500 kVA dry type, 13.2 kV delta / 480Y/277 VSubstation #1 switchboard3 to checkDrawing · 1T
1LSubstation #1 LV main2500 A 3-pole main, drawn as drawout; SPD 400 kA; digital meterSubstation #1 switchboard bus, 2500 A, 50 kAIC2 same4 to checkDrawing · 1L
1FSubstation #1 feeders15 breakers: 800, 600, 400 x6, 225 x6, 100 A (E-108 frames 800 x2, 400 x5, 225 x8)ATS #14, #15, #2, #1; risers 1EHA, 7EHA; PFC; panels D.G., PBHA; elevator S-20; 5 spares3 to checkDrawing · 1F
2MSubstation #2 MV2 x 15 kV, 600 A load-interrupter switch, key-interlocked, 1 x 90E fuseSubstation #2 transformer, 1500 kVA1 same4 to checkDrawing · 2M
2TSubstation #2 transformer1500 kVA dry type, 13.2 kV delta / 480Y/277 VSubstation #2 switchboard3 to checkDrawing · 2T
2LSubstation #2 LV main2500 A 3-pole main, drawn as drawout; SPD 400 kA; digital meterSubstation #2 switchboard bus, 2500 A, 50 kAIC2 same4 to checkDrawing · 2L
2FSubstation #2 feeders16 breakers: 800, 600, 400 x5, 350, 300, 225 x2, 175, 150 x2, 100 x2 AATS #13, #11, #9; panels SBHA, 6ME, PCM, BMW, 2ME, 4ME, PSM; 225 kVAR PFC; elevator S-19; 4 spares3 to checkDrawing · 2F
TMSubstation "T" MV2 x 15 kV, 600 A load-interrupter switch, key-interlocked, 1 x 90E fuseSubstation "T" transformer, 1500 kVA2 same4 to checkDrawing · TM
TTSubstation "T" transformer1500 kVA dry type, 13.2 kV delta / 480Y/277 VSubstation "T" switchboard3 to checkDrawing · TT
TLSubstation "T" LV main2500 A 3-pole main, drawn as drawout; SPD 400 kA; digital meterSubstation "T" switchboard bus, 2500 A, 50 kAIC2 same4 to checkDrawing · TL
TFSubstation "T" feedersE-107: 20 spares; E-108: 17 spares (frames 800 x2, 400 x4, 225 x11)Temporary loads for Substations #1 and #2, then spare1 same2 to checkDrawing · TF
A1ATS #1 (relocated)Existing transfer switch, relocatedPanels DEC-1 and DEC-2, 225 kVA transformer1 to checkDrawing · A1
F12FDR12 (existing)1200 A drawout breaker, 3 CTs 200/5 A, 50/51New Substations #1, #2, and T via the tap boxes2 sameDrawing · F12
F19FDR19 (existing)1200 A drawout breaker, 3 CTs 200/5 A, 50/51New Substations #1, #2, and T via the tap boxes1 sameDrawing · F19

Switchboard schedules and elevations

#PositionEquipment on the drawingFeedsChecksWhere it is written
S1SWBD #12500 A, 50 kAIC, 16 modulesSubstation #1 loads2 to checkDrawing · S1
S2SWBD #22500 A, 50 kAIC, 17 modulesSubstation #2 loads1 to checkDrawing · S2
STSWBD T2500 A, 50 kAIC, 17 spare feedersTemporary, then spare1 same2 to checkDrawing · ST

Existing substations, demolition

#PositionEquipment on the drawingFeedsChecksWhere it is written
X1Existing Substation #1600 A air interrupter selector, 50E; 750 kVA; 1200 A mainRemoved; loads move to T, then to new Substation #11 sameDrawing · X1
X2Existing Substation #2600 A air interrupter selector, 50E; 750 kVA; 1200 A mainRemoved; loads move to T, then to new Substation #21 sameDrawing · X2
TIEExisting LV tie1200 A tie breaker and 1200 A bus ductRemoved; no tie on the new single-line1 to checkDrawing · TIE

Where the documents disagree 8

Biggest cost impact first. Each item shows both sides and their page numbers.

1Transformer: cast coil or VPI?High cost
One document says
  • Spec 26 11 16 2.4 B: provide a cast-coil transformer with windings cast in epoxy, 185 °C insulation, and 80 °C rise. Specification p.472
Another says
  • Spec 26 11 16 2.4 C: provide a vacuum pressure impregnated (VPI) transformer with 220 °C insulation and 80 °C rise. Specification p.472
  • The drawings only say "DRY TYPE TRANSFORMER", and RFI 1 Q69 only answers "Refer to the Bid Drawings". RFI 1 answers p.14
Why it matters Cast coil and VPI differ significantly in price and lead time for three 1500 kVA units. Nothing in the package resolves this. Question 1 ↓
2LV main breaker: molded case or drawout?High cost
One document says
  • Spec 26 24 13 2.2 defines only a "Type 1" switchboard, and 2.5 A requires molded-case main circuit breakers for Type I or Type II. Specification p.495
Another says
  • E-107: all three "2500A 3P" mains have chevrons on both sides, which E-001 defines as a removable drawout low-voltage breaker; the feeders use the non-drawout symbol. E-001 symbols and legend
  • Spec 2.5 B (Type II clause): breakers larger than 1600 A frame must be electrically operated. Specification p.497
Why it matters A fixed 2500 A molded-case main and a drawout, electrically operated power or insulated-case breaker differ in price by three times. The statement of work gives the specification precedence, but the specification says "as shown on the drawings". Statement of work p.2Question 2 ↓
3"Metal-clad" substation, metal-enclosed interrupter switchCost
One document says
  • Spec 26 11 16 2.1 B: complete, grounded, continuous-duty, "metal-clad", dead-front substations with a dry-type transformer. Specification p.471
Another says
  • Spec 26 13 16: dead-front, air-break, three-pole gang-operated interrupter switches per IEEE C37.20.3 metal-enclosed interrupter switchgear. Specification p.479
  • E-107 keyed note 2: duplex load-interrupter fusible switch. E-107 single-line, new work · note 2
Why it matters Metal-clad (IEEE C37.20.2) means drawout breakers, but the design uses a fused load-interrupter. Read literally, that word changes the whole MV section. Question 4 ↓
4Substation T switchboard: 20 feeders on E-107, 17 on E-108Cost
One document says
  • E-107: 20 spare feeders, 800 x2, 600, 400 x3, 350 x2, 300, 225 x5, 175, 150, 100 x4. E-107 single-line, new work
Another says
  • E-108 SWBD T: 17 spare feeders, plugs 800 x2, 400 x4, 225 x5, 175, 150, 100 x4. E-108 schedules and elevations
  • E-101 Stage-1 note 4, E-103 keyed note 4, and E-107 general note 2 all point to E-108 for the temporary switchboard. E-101 installation notes
Why it matters E-108 has a frame for every Substation #2 load moving to T in Stage 3 (E-101 note 17): 800 for ATS #13 and the 600 A chiller, and 400 for the PFC, 6ME (350), and SBHA (300). Only the second 150 A was missing, and RFI 1 Q20 adds it to the E-108 schedule. The record favors E-108; only plug ratings and breaker count differ. E-101 installation notesRFI 1 answers p.5Question 8 ↓
5Metering and seismic sections cited but missing from the projectCost
One document says
  • Spec 26 13 16 2.2: for metering, refer to Section 25 10 10, Advanced Utility Metering. E-107 note 8: digital meter per switchboard specification. Specification p.481
  • Spec 26 11 16 1.2 cites Section 13 05 41 for seismic restraint, and 26 11 16 2.1 F cites 26 13 13 MV circuit breaker switchgear. Specification p.468
Another says
  • Table of contents: Division 25 and Division 13 are "Not Used"; 26 13 13 is not in the project. Specification p.3
  • Spec 26 24 13 2.8 covers only CTs and VTs for the meter. Specification p.497
Why it matters Meter class, protocol, and any monitoring head end are undefined, even though E-101 Stage 4 lists a "power monitoring and control system". Seismic certification is required for the substations, switches, and switchboards, with no criteria given. E-101 installation notesSpecification p.470Question 7 ↓
6Lineup depth and temporary elevationSpace
One document says
  • E-108 elevations: The LV lineup is dimensioned at 38" deep, and the temporary elevation shows only the Option #1 narrow switch, 18" + 24". E-108 schedules and elevations
Another says
  • A-101 and E-103 plans: Distribution section 25" deep, MV switches 50" deep. A-101 floor plan
  • E-103 view 3 shows the narrow switch as 18" + 18"; view 2 (Option 2) shows T with 35" + 35" switches. E-103 electrical room plan
Why it matters Room fit and section sizes depend on this. Option 2 is the option to price, and E-108 has no Option 2 elevation of T. Question 10 ↓
7Existing feeder ratings: E-106 vs. as-built risersSmall
One document says
  • E-106 and E-107: SBHA 300 A; 75 kVAR PFC 225 A (E-108 225/225). E-108 schedules and elevations
Another says
  • As-built B02-SUB-2: "SBHA 400AF / 400AT"; B02-SUB-1: "75 kVAR PFU 400AF / 250AT". As-built riser B02-SUB-2
  • As-built sheet 6 also shows the PFC with a 250 A plug. As-built single lines, sheet 6
Why it matters Low impact: the SBHA panel has its own 300 A main (B02-SUB-2), so the new 300 A plug matches it. The 75 kVAR PFC trip drops from 250 A to 225 A. As-built riser B02-SUB-2Question 18 ↓
8Contract type: indefinite quantity or lump sum?Commercial
One document says
  • Solicitation E.3: the Government plans a Firm-Fixed-Price, Indefinite Quantity contract. Solicitation p.22
Another says
  • RFI 1 Q79 and RFI 2 Q27: one total price in block 17 of the SF 1442; no bid schedule. RFI 1 answers p.16
Why it matters Small for a supplier: it reads as a single lump-sum construction contract. Question 20 ↓
Minor errors in the documents (no cost impact)
  • Resolved: the spec and drawings still offer Option #1 and Option #2, and RFI 1 said "There is no option 1 or 2". RFI 2 Q10 settles it: price Option 2 only. Do not price the narrow switch. RFI 2 answers p.1
  • Resolved: E-107 refers tap notes to "E104"; RFI 1 Q23 already states the junctions are on E-105. RFI 1 answers p.6
  • Resolved in substance: the E-108 T header says circuit #12 "in BLDG. #19", and RFI 1 Q24-Q28 provide duplex switches on all three substations for either source. E-108 schedules and elevations
  • A-101 swaps the MV switch labels: the Substation-1 transformer has switches labeled "SUBSTATION-2", and vice versa. E-103 view 1 labels match. A-101 floor plan
  • Temporary ground bus bar: 12" x 4" on E-103 view 2, 24" x 4" in keyed note 9 and view 3, and 1'-4" (16") long in the ground bar detail on the same sheet. E-103 electrical room plan
  • Slab projection is "100 mm (8 inches)" in 26 11 16 and 26 13 16, "200 mm (8 inches)" in 26 24 13, and "4" larger on all side" on E-103. Specification p.474
  • E-107 tags the Substation #2 main with keyed note "2" instead of "4". Keyed note 6 says "new Substation #2" but is also tagged on Substation #1 feeders. E-107 single-line, new work
  • B02-SUB-2 shows BMW at 250AF / 100AT (E-108: 225/100), and its main breaker box is labeled "T-SUB-1 XFMR". As-built riser B02-SUB-2
  • The legend reads "(N) denotes new to match existing", not just new. E-001 symbols and legend

Points to settle in your quote 22

The RFI window closed with Amendment 0004, so send these to the general contractor or include them in the assumptions sent with your price. Highest cost impact first.

1Transformer constructionSpecification 26 11 16 2.4 B (cast coil, 185 °C insulation, 80 °C rise) and 2.4 C (VPI, 220 °C insulation, 80 °C rise) both state "Provide". Which transformer construction is required for the three 1500 kVA units?Specification p.472Specification p.472
2LV main breaker typeSpecification 26 24 13 allows a molded-case main (Type I), but E-107 shows the 2500 A mains as drawout. Confirm the required type (fixed molded-case, drawout insulated-case, or drawout LV power circuit breaker to IEEE C37.13) and whether it must be electrically operated (2.5 B 8).Specification p.495Specification p.497E-001 symbols and legend
3Buy AmericanBoth 52.225-9 (Buy American, construction materials) and 52.225-11 (under trade agreements, "Buy American restrictions are waived for designated country construction materials") are included. Which clause applies? This determines whether non-US-made switchgear and transformers are acceptable.Solicitation p.35Solicitation p.39
4"Metal-clad" wordingSpecification 26 11 16 2.1 B calls the substations "metal-clad". Confirm that a metal-enclosed fused load-interrupter primary section (IEEE C37.20.3, per 26 13 16) is acceptable.Specification p.471Specification p.479
5MV short-circuit ratingsSpecification 26 13 16 requires 61 kA momentary and 48 kA 2-second ratings. The 2023 study shows about 6.3 to 6.6 kA at 13.2 kV, and E-107 marks both PECO incomers "6300A MAX". Confirm whether these minimums stand, as they determine the switch frame, and clarify how to read "short circuit currents as shown on the drawings" in 26 11 16.Specification p.481Campus 13.2 kV one-line, 2023 studyE-107 single-line, new work
6Transformer rating basisIs 1500 kVA the self-cooled (AA) rating, with the fans in 26 11 16 2.4 G ("forced-air-cooled") adding capacity, or the fan-cooled (FA) rating? Also state the impedance (%Z), K-factor, and sound level requirements.Specification p.473E-107 single-line, new work · note 3
7Metering and monitoringE-107 note 8 calls for a "DIGITAL METER PER SWITCHBOARD SPECIFICATION". However, 26 24 13 2.8 covers only CTs and VTs, 26 13 16 2.2 refers to Section 25 10 10 (not in the project), and E-001 calls the boxed M an ammeter. E-101 Stage 4 also mentions a "power monitoring and control system". Specify the meter type, class, and communication protocol, and state whether a monitoring system (head end) is in scope.E-107 single-line, new work · note 8Specification p.481E-101 installation notesE-001 symbols and legend
8Substation T plug ratingsE-108 SWBD T schedules 17 spare feeders (plugs 800 x2, 400 x4, 225 x5, 175, 150, 100 x4), while E-107 shows 20 (adding 600 A, 2 x 350 A, and 300 A). E-108 includes a frame for every Substation #2 load moving to T in Stage 3, and E-101, E-103, and E-107 all refer to E-108 for the T schedule. We priced E-108 plus the RFI 1 Q20 change. Confirm which plug ratings govern.E-108 schedules and elevationsE-107 single-line, new workE-103 electrical room plan
9Loop feed on Substation #1Assumption to state: Per RFI 1 Q23 and E-105/E-107, Substation #2 is fed from the Substation #1 duplex line side. The Substation #1 duplex section includes loop-feed lugs and cable space for two cable sets per source, and the Substation #2 section takes one set per source.RFI 1 answers p.5E-105 MV conduit routingE-105 MV conduit routing
10Lineup depth and temporary elevationE-108 dimensions the LV lineup 38" deep, while A-101 and E-103 draw the distribution section 25" deep. E-108 shows the temporary substation only with the Option #1 narrow switch (18" + 24", E-103 view 3: 18" + 18") and has no Option #2 elevation for T. Confirm the design depth and that T follows the Substations #1 and #2 elevation under Option 2.E-108 schedules and elevationsA-101 floor planE-103 electrical room plan
11225 kVAR power factor correctionE-108 SWBD #2 module 4 reads "(N) 225kVAR AUTOMATIC POWER F.C.U.", but no specification section covers it. Is a new 225 kVAR power factor correction unit in scope?E-108 schedules and elevations
12LV tieExisting Substations #1 and #2 have a 1200 A tie breaker and bus duct (E-106), while the new design shows no LV tie. Specification 26 25 11 Busways is included; confirm that no tie breaker or busway is required.E-106 single-line, demolitionSpecification p.505
13Seismic criteriaSpecifications 26 11 16, 26 13 16, and 26 24 13 require IBC seismic certification, but Section 13 05 41 is not included and no seismic design category or importance factor is given. State the seismic criteria.Specification p.470Specification p.468
14LV short-circuit ratingE-108 lists 50 kAIC for the 2500 A boards. The specification requires the manufacturer's study (26 05 73) to set ratings and forbids series ratings (26 24 13 2.1 A 8). Confirm whether 50 kA fully rated is the minimum or if the boards are rated to the study result.E-108 schedules and elevationsSpecification p.494
15MV fuse typeSpecification 26 13 16 2.1 A 9 requires "Expulsion fuses", while E-107 shows "90E". Are current-limiting fuses acceptable or required for an indoor unit substation?Specification p.480E-107 single-line, new work
16New ATSSpecification 26 36 23 (ATS, bypass-isolation) is included, but no new ATS appears on the drawings and existing ATS #1 is relocated. Confirm that no new ATS is in scope.Specification p.530E-107 single-line, new work
17Utility witness and approvalSpecification 26 24 13 3.2 B and 2.1 A 4 require utility (PECO) witness testing and coordination, and 26 05 13 requires utility cable approval. However, RFI 1 Q31 sets the demarcation at Building 6. Confirm that these utility requirements do not apply to the Building 2 substations.Specification p.500RFI 1 answers p.7
18SBHA and 75 kVAR feeder tripsThe existing SBHA feeder is 400AF / 400AT on as-built B02-SUB-2, but 300 A on E-106, E-107, and E-108 (the SBHA panel main is 300 A). The existing 75 kVAR PFU is 400AF / 250AT on B02-SUB-1, but 225 A on E-108. Confirm the new trip ratings.As-built riser B02-SUB-2As-built riser B02-SUB-1
19Which 100 A becomes 150 AThe RFI 1 Q20 answer, "Revise (1) 100A breaker to 150A breaker with 150A plug", does not say which of the four 100 A breakers on SWBD T is revised. Please identify it.RFI 1 answers p.5
20Contract typeConfirm the contract is a firm-fixed-price lump sum. Solicitation E.3 states "Firm-Fixed-Price, Indefinite Quantity", while RFI 1 Q79 asks for one total price in block 17.Solicitation p.22RFI 1 answers p.16
21Clerical errorsConfirm E-108, E-103, and E-105 govern for these errors: E-107 Substation #1 feeder #10 is unlabeled and #12 is double-labeled; A-101 MV switch labels are swapped; the E-108 T header reads "circuit #12 in BLDG. #19"; ground bar sizes are 12" x 4", 24" x 4", and a 1'-4" (16") detail on E-103; and slab projection is "100 mm (8 inches)".A-101 floor planE-103 electrical room planE-103 electrical room planE-103 electrical room plan
22Missing attachmentsRFI 2 Q13 and Q17 state that the FMS 011 LOTO SOP and the Fire Alarm and Fire Suppression Impairment Policy are "provided with Amendment 0004". However, Amendment 0004's attachment list names neither, and no file in the package contains them. Please provide them.RFI 2 answers p.2RFI 2 answers p.2Amendment 0004 p.2

Requirements to meet

28 · 8 to clarify
RequirementStatusNotePage
Offers are due by 7 Dec 2026, 4:00 PM EST; no more RFIs after Amendment 0004.RequiredAmendment 0004 p.1
Enter the price on SF 1442 block 17; there is no bid schedule. Price Option 2 only.RequiredRFI 2 answers p.1
Total set-aside for service-disabled veteran-owned small businesses; best-value trade-off.RequiredThe switchgear manufacturer supplies through the general contractor.Solicitation p.1
Bid guarantee is 20% of the bid price or $3,000,000, whichever is less. RFI 2 Q29 confirms a bid bond is required.RequiredSolicitation p.24
Performance and payment bonds are 100% of the contract price.RequiredRFI 2 answers p.3
Offer is valid for 180 calendar days.RequiredLong price hold for transformers and switchgear.RFI 2 answers p.3
1,000 calendar days from a single notice to proceed, including substation lead time (bidders quoted about 18 months).RequiredRFI 1 answers p.7
All three units are bought and stored in contractor-supplied conditioned space before construction.RequiredStorage, insurance, and energized heaters during storage.Statement of work p.1
Buy American: clauses 52.225-9 and 52.225-11 are both included.To clarifyDetermines whether non-US equipment is acceptable.Solicitation p.35
The specification governs over the drawings, followed by the authority having jurisdiction.RequiredStatement of work p.2
Warranty is one year from acceptance, with joint 4-month and 9-month inspections.RequiredSpecification p.423
Manufacturer: at least 3 years producing the equipment and 3 similar installations in service for 3 years; one manufacturer per class of equipment; service within 4 hours.RequiredSpecification p.416
Shutdown work is off-hours (Friday 8:00 p.m. to Monday 6:00 a.m.); outages are requested through the COR.RequiredStatement of work p.2
Duplex 15 kV, 600 A fused load-interrupter selector switch with key interlocks on all three substations; front access only.RequiredAdd loop-feed lugs for two cable sets per source on Substation #1 (RFI 1 Q23, E-105).E-101 installation notes
MV switch: air-break, gang-operated, copper blades, quick-make/quick-break, expulsion fuses, 61 kA momentary, 48 kA 2 s, full ground bar; one spare fuse set per switch.To clarify61/48 kA against about 6.3 kA available; expulsion fuses are indoors.Specification p.480
Dry-type transformer: copper windings, delta/wye with neutral bushing, 95 kV / 10 kV BIL, four 2-1/2% taps, fans with temperature control, winding temperature indicator, and 120 V heaters.To clarifyBoth cast coil and VPI are specified.Specification p.473
Switchboard: 480Y/277 V, 2500 A, 50 kAIC, UL 891; fully rated copper bus; solid-state trips; no series ratings.RequiredSpecification p.495
"Metal-clad" substation wording.To clarifyThe MV section is metal-enclosed interrupter switchgear.Specification p.471
Surge protector: 400 kA type 2 per drawing (spec minimum 240 kA), with integral disconnect, 200 kA fuses, LEDs, alarm, Form-C contact, and event counter.RequiredPrice 400 kA.Specification p.545
Short-circuit, coordination, and arc-flash study by the equipment manufacturer's licensed engineer; trips are set in the field by the switchboard manufacturer.To clarifyThe manufacturer needs a licensed PE.Specification p.459
Certified factory tests; the Government may witness with 30 days' notice.RequiredSpecification p.417
Seismic certification by shake table or analysis for substations, switches, and switchboards.To clarifyNo seismic criteria are given.Specification p.470
Utility (PECO) witness testing before acceptance.To clarifyDemarcation is at Building 6.Specification p.500
Training: one 4-hour session each for substations, switches, and switchboards; 8 hours for the surge protector. Laminated as-built one-line and sequence of operation in the room.RequiredSpecification p.476
New 15 kV cables: insulation resistance, Tan Delta, and VLF withstand tests.RequiredSpecification p.433
All equipment NRTL listed or labeled.RequiredSpecification p.415
MV tap connectors: Eaton Cleer series load-break connectors.To clarifyNamed product; no "or equal" next to it.E-105 MV conduit routing
No brand is named for the substations, switches, transformers, or switchboards.RequiredExisting site gear is Square D; there is no requirement to match.Specification p.417

Not in the package