US Department of Veterans Affairs, solicitation 36C24426R0088, project 642-22-104. This construction contract is set aside for service-disabled veteran-owned small businesses. It includes three new 1500 kVA, 13.2 kV to 480Y/277 V dry-type unit substations, each with a duplex 15 kV fused load-interrupter switch and a 2500 A switchboard. Documents are in English.
42 files and 1,350 pages total, counting Word files converted to PDF. The 25 drawings, four amendments, both sets of RFI answers, statement of work, and solicitation were read in full. The 597-page specification was read in full for Division 26 and relevant Division 01 parts, and the medical-center safety policies were searched by keyword. Single-lines and schedules were read from the drawing image. Every point links to its source page: click a chip to see the wording on the page.
Drawing E-107, "Single line risers - Substations #1, #2 and "T" - new work", bid documents dated 21 Oct 2024. The PDF sheet is sideways; it is shown upright here. (E) is existing, (ER) is relocated, and (N) is new to match existing. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.
Drawing E-108, "Schedules and equipment elevations". The schedules are an image with no text layer; every value was read from the image. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.
Drawing E-106, "Single line risers - demolition": the two existing 750 kVA substations removed by this job. Click any boxed position to see what the drawing shows and how it compares with the specification, data sheet, and layout.

| # | Position | Equipment on the drawing | Feeds | Checks | Where it is written |
|---|---|---|---|---|---|
| 1M | Substation #1 MV | 2 x 15 kV, 600 A load-interrupter switch, key-interlocked, 1 x 90E fuse | Substation #1 transformer, 1500 kVA | 1 same5 to check | Drawing · 1M |
| 1T | Substation #1 transformer | 1500 kVA dry type, 13.2 kV delta / 480Y/277 V | Substation #1 switchboard | 3 to check | Drawing · 1T |
| 1L | Substation #1 LV main | 2500 A 3-pole main, drawn as drawout; SPD 400 kA; digital meter | Substation #1 switchboard bus, 2500 A, 50 kAIC | 2 same4 to check | Drawing · 1L |
| 1F | Substation #1 feeders | 15 breakers: 800, 600, 400 x6, 225 x6, 100 A (E-108 frames 800 x2, 400 x5, 225 x8) | ATS #14, #15, #2, #1; risers 1EHA, 7EHA; PFC; panels D.G., PBHA; elevator S-20; 5 spares | 3 to check | Drawing · 1F |
| 2M | Substation #2 MV | 2 x 15 kV, 600 A load-interrupter switch, key-interlocked, 1 x 90E fuse | Substation #2 transformer, 1500 kVA | 1 same4 to check | Drawing · 2M |
| 2T | Substation #2 transformer | 1500 kVA dry type, 13.2 kV delta / 480Y/277 V | Substation #2 switchboard | 3 to check | Drawing · 2T |
| 2L | Substation #2 LV main | 2500 A 3-pole main, drawn as drawout; SPD 400 kA; digital meter | Substation #2 switchboard bus, 2500 A, 50 kAIC | 2 same4 to check | Drawing · 2L |
| 2F | Substation #2 feeders | 16 breakers: 800, 600, 400 x5, 350, 300, 225 x2, 175, 150 x2, 100 x2 A | ATS #13, #11, #9; panels SBHA, 6ME, PCM, BMW, 2ME, 4ME, PSM; 225 kVAR PFC; elevator S-19; 4 spares | 3 to check | Drawing · 2F |
| TM | Substation "T" MV | 2 x 15 kV, 600 A load-interrupter switch, key-interlocked, 1 x 90E fuse | Substation "T" transformer, 1500 kVA | 2 same4 to check | Drawing · TM |
| TT | Substation "T" transformer | 1500 kVA dry type, 13.2 kV delta / 480Y/277 V | Substation "T" switchboard | 3 to check | Drawing · TT |
| TL | Substation "T" LV main | 2500 A 3-pole main, drawn as drawout; SPD 400 kA; digital meter | Substation "T" switchboard bus, 2500 A, 50 kAIC | 2 same4 to check | Drawing · TL |
| TF | Substation "T" feeders | E-107: 20 spares; E-108: 17 spares (frames 800 x2, 400 x4, 225 x11) | Temporary loads for Substations #1 and #2, then spare | 1 same2 to check | Drawing · TF |
| A1 | ATS #1 (relocated) | Existing transfer switch, relocated | Panels DEC-1 and DEC-2, 225 kVA transformer | 1 to check | Drawing · A1 |
| F12 | FDR12 (existing) | 1200 A drawout breaker, 3 CTs 200/5 A, 50/51 | New Substations #1, #2, and T via the tap boxes | 2 same | Drawing · F12 |
| F19 | FDR19 (existing) | 1200 A drawout breaker, 3 CTs 200/5 A, 50/51 | New Substations #1, #2, and T via the tap boxes | 1 same | Drawing · F19 |
| # | Position | Equipment on the drawing | Feeds | Checks | Where it is written |
|---|---|---|---|---|---|
| S1 | SWBD #1 | 2500 A, 50 kAIC, 16 modules | Substation #1 loads | 2 to check | Drawing · S1 |
| S2 | SWBD #2 | 2500 A, 50 kAIC, 17 modules | Substation #2 loads | 1 to check | Drawing · S2 |
| ST | SWBD T | 2500 A, 50 kAIC, 17 spare feeders | Temporary, then spare | 1 same2 to check | Drawing · ST |
| # | Position | Equipment on the drawing | Feeds | Checks | Where it is written |
|---|---|---|---|---|---|
| X1 | Existing Substation #1 | 600 A air interrupter selector, 50E; 750 kVA; 1200 A main | Removed; loads move to T, then to new Substation #1 | 1 same | Drawing · X1 |
| X2 | Existing Substation #2 | 600 A air interrupter selector, 50E; 750 kVA; 1200 A main | Removed; loads move to T, then to new Substation #2 | 1 same | Drawing · X2 |
| TIE | Existing LV tie | 1200 A tie breaker and 1200 A bus duct | Removed; no tie on the new single-line | 1 to check | Drawing · TIE |
Biggest cost impact first. Each item shows both sides and their page numbers.
The RFI window closed with Amendment 0004, so send these to the general contractor or include them in the assumptions sent with your price. Highest cost impact first.
| Requirement | Status | Note | Page |
|---|---|---|---|
| Offers are due by 7 Dec 2026, 4:00 PM EST; no more RFIs after Amendment 0004. | Required | Amendment 0004 p.1 | |
| Enter the price on SF 1442 block 17; there is no bid schedule. Price Option 2 only. | Required | RFI 2 answers p.1 | |
| Total set-aside for service-disabled veteran-owned small businesses; best-value trade-off. | Required | The switchgear manufacturer supplies through the general contractor. | Solicitation p.1 |
| Bid guarantee is 20% of the bid price or $3,000,000, whichever is less. RFI 2 Q29 confirms a bid bond is required. | Required | Solicitation p.24 | |
| Performance and payment bonds are 100% of the contract price. | Required | RFI 2 answers p.3 | |
| Offer is valid for 180 calendar days. | Required | Long price hold for transformers and switchgear. | RFI 2 answers p.3 |
| 1,000 calendar days from a single notice to proceed, including substation lead time (bidders quoted about 18 months). | Required | RFI 1 answers p.7 | |
| All three units are bought and stored in contractor-supplied conditioned space before construction. | Required | Storage, insurance, and energized heaters during storage. | Statement of work p.1 |
| Buy American: clauses 52.225-9 and 52.225-11 are both included. | To clarify | Determines whether non-US equipment is acceptable. | Solicitation p.35 |
| The specification governs over the drawings, followed by the authority having jurisdiction. | Required | Statement of work p.2 | |
| Warranty is one year from acceptance, with joint 4-month and 9-month inspections. | Required | Specification p.423 | |
| Manufacturer: at least 3 years producing the equipment and 3 similar installations in service for 3 years; one manufacturer per class of equipment; service within 4 hours. | Required | Specification p.416 | |
| Shutdown work is off-hours (Friday 8:00 p.m. to Monday 6:00 a.m.); outages are requested through the COR. | Required | Statement of work p.2 | |
| Duplex 15 kV, 600 A fused load-interrupter selector switch with key interlocks on all three substations; front access only. | Required | Add loop-feed lugs for two cable sets per source on Substation #1 (RFI 1 Q23, E-105). | E-101 installation notes |
| MV switch: air-break, gang-operated, copper blades, quick-make/quick-break, expulsion fuses, 61 kA momentary, 48 kA 2 s, full ground bar; one spare fuse set per switch. | To clarify | 61/48 kA against about 6.3 kA available; expulsion fuses are indoors. | Specification p.480 |
| Dry-type transformer: copper windings, delta/wye with neutral bushing, 95 kV / 10 kV BIL, four 2-1/2% taps, fans with temperature control, winding temperature indicator, and 120 V heaters. | To clarify | Both cast coil and VPI are specified. | Specification p.473 |
| Switchboard: 480Y/277 V, 2500 A, 50 kAIC, UL 891; fully rated copper bus; solid-state trips; no series ratings. | Required | Specification p.495 | |
| "Metal-clad" substation wording. | To clarify | The MV section is metal-enclosed interrupter switchgear. | Specification p.471 |
| Surge protector: 400 kA type 2 per drawing (spec minimum 240 kA), with integral disconnect, 200 kA fuses, LEDs, alarm, Form-C contact, and event counter. | Required | Price 400 kA. | Specification p.545 |
| Short-circuit, coordination, and arc-flash study by the equipment manufacturer's licensed engineer; trips are set in the field by the switchboard manufacturer. | To clarify | The manufacturer needs a licensed PE. | Specification p.459 |
| Certified factory tests; the Government may witness with 30 days' notice. | Required | Specification p.417 | |
| Seismic certification by shake table or analysis for substations, switches, and switchboards. | To clarify | No seismic criteria are given. | Specification p.470 |
| Utility (PECO) witness testing before acceptance. | To clarify | Demarcation is at Building 6. | Specification p.500 |
| Training: one 4-hour session each for substations, switches, and switchboards; 8 hours for the surge protector. Laminated as-built one-line and sequence of operation in the room. | Required | Specification p.476 | |
| New 15 kV cables: insulation resistance, Tan Delta, and VLF withstand tests. | Required | Specification p.433 | |
| All equipment NRTL listed or labeled. | Required | Specification p.415 | |
| MV tap connectors: Eaton Cleer series load-break connectors. | To clarify | Named product; no "or equal" next to it. | E-105 MV conduit routing |
| No brand is named for the substations, switches, transformers, or switchboards. | Required | Existing site gear is Square D; there is no requirement to match. | Specification p.417 |