 "id": "bolivia-ypfb-mercury-removal-adsorbers",
 "country": "Bolivia",
 "language": "Spanish",
 "buyer": "Yacimientos Petrolíferos Fiscales Bolivianos (YPFB)",
 "project": "Detail engineering, procurement, construction, commissioning and start-up (turnkey EPC) of mercury removal units at the Rio Grande and Carlos Villegas liquids separation plants, tender DCO-CDL-GIPI-56-19",
 "year": "2019",
 "files": [
  {
   "file": "3 DBC - LLAVE EN MANO IPC URM.pdf",
   "pages": 64,
   "text_layer": true,
   "what_it_is": "Bid conditions (Documento Base de Contratación, turnkey): dates, reference price, forms, model contract; converted from Word"
  },
  {
   "file": "Anexo 1.pdf",
   "pages": 12,
   "text_layer": true,
   "what_it_is": "Process considerations for the Carlos Villegas plant: pressure drop, drains, relief, fire water, adsorbent loading, adsorber internals"
  },
  {
   "file": "Anexo 10.pdf",
   "pages": 16,
   "text_layer": true,
   "what_it_is": "Requirements for final documentation and Data Books"
  },
  {
   "file": "Anexo 11.pdf",
   "pages": 5,
   "text_layer": true,
   "what_it_is": "Financial capacity evaluation"
  },
  {
   "file": "Anexo 12.pdf",
   "pages": 1,
   "text_layer": true,
   "what_it_is": "Invoicing and payment procedure"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/1.3 Planos de Ubicacion.pdf",
   "pages": 3,
   "text_layer": true,
   "what_it_is": "Location plans"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/2.2 Especificacion tecnica URM.pdf",
   "pages": 13,
   "text_layer": true,
   "what_it_is": "URM process specifications 12-2-PRO-SP-10001 (PSLCV) and 12-2-PRO-SP-20001 (PSLRG): scope, design parameters, inlet gas conditions, site data"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/2.3 Digramas de Flujo de Proceso.pdf",
   "pages": 3,
   "text_layer": true,
   "what_it_is": "Process flow diagrams (no stream data; drawing labels not in the text layer)"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/2.4 Diagramas de tuberia e instrumentacion.pdf",
   "pages": 11,
   "text_layer": true,
   "what_it_is": "P&IDs for both units, with vessel callouts"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf",
   "pages": 7,
   "text_layer": true,
   "what_it_is": "Pressure vessel data sheets V-101 A/B (12-2-PRO-DS-10001) and V-501 D (12-2-PRO-DS-20001) with sketches; U stamp/NB tick boxes are graphics"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/2.5.1 Filtros (strainers).pdf",
   "pages": 5,
   "text_layer": true,
   "what_it_is": "Strainer data sheets 12-2-PRO-DS-10003 (PSLCV) and 12-2-PRO-DS-20003 (PSLRG)"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/2.6 Adsorbentes.pdf",
   "pages": 5,
   "text_layer": true,
   "what_it_is": "Adsorbent data sheets 12-2-PRO-DS-10002 and 12-2-PRO-DS-20002"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/2.7 Tie-ins.pdf",
   "pages": 5,
   "text_layer": true,
   "what_it_is": "Tie-in lists"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/3.2 Tuberias.pdf",
   "pages": 37,
   "text_layer": true,
   "what_it_is": "Line lists and piping MTOs for both units (includes the Y-strainers)"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/3.3 Equipos.pdf",
   "pages": 5,
   "text_layer": true,
   "what_it_is": "Equipment list 12-2-MEC-LT-00001, plot plan and adsorber diagrams 12-2-MEC-DW-10002 and 12-2-MEC-DW-20002"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/4.1 Valvulas de Seguridad.pdf",
   "pages": 6,
   "text_layer": true,
   "what_it_is": "Safety valve (PSV) data sheets for the adsorbers"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/4.2 Manometros.pdf",
   "pages": 6,
   "text_layer": true,
   "what_it_is": "Pressure gauge data sheets"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/4.4 Analizadores de Hg.pdf",
   "pages": 5,
   "text_layer": true,
   "what_it_is": "Mercury analyzer data sheets"
  },
  {
   "file": "Anexo 13 Documentos de Ingenieria Basica/6.2 Planos de Fundaciones.pdf",
   "pages": 3,
   "text_layer": true,
   "what_it_is": "Foundation drawings for V-101 A/B and V-501 D"
  },
  {
   "file": "Anexo 14.pdf",
   "pages": 11,
   "text_layer": true,
   "what_it_is": "Project organization and planning"
  },
  {
   "file": "Anexo 2.pdf",
   "pages": 10,
   "text_layer": true,
   "what_it_is": "Process considerations for the Rio Grande plant"
  },
  {
   "file": "Anexo 3 .pdf",
   "pages": 15,
   "text_layer": true,
   "what_it_is": "Electrical specification"
  },
  {
   "file": "Anexo 4.pdf",
   "pages": 21,
   "text_layer": true,
   "what_it_is": "Civil specification: foundations, steel structures, equipment table, PSV platform extensions"
  },
  {
   "file": "Anexo 5.pdf",
   "pages": 18,
   "text_layer": true,
   "what_it_is": "Instrumentation specification"
  },
  {
   "file": "Anexo 6.pdf",
   "pages": 25,
   "text_layer": true,
   "what_it_is": "Technical specification for pressure vessels"
  },
  {
   "file": "Anexo 7.pdf",
   "pages": 30,
   "text_layer": true,
   "what_it_is": "Technical specification for piping"
  },
  {
   "file": "Anexo 8.pdf",
   "pages": 19,
   "text_layer": true,
   "what_it_is": "QA/QC requirements for contractors"
  },
  {
   "file": "Anexo 9.pdf",
   "pages": 76,
   "text_layer": true,
   "what_it_is": "HSE (SMS) requirements for contractors"
  },
  {
   "file": "RG-02-A-GCC - ESP TEC IPC URM FINAL.pdf",
   "pages": 102,
   "text_layer": true,
   "what_it_is": "Main EPC technical specification RG-02-A-GCC (scope, schedule, deliverables, evaluation, guarantees, insurance); converted from Word"
  }
 ],
 "quality": "Vessel data sit in two preliminary data sheets whose U stamp and NB boxes are graphics, a separate vessel specification, P&IDs, line lists and MTOs that disagree in places (V-501 D design temperature, operating cases, strainer permanence, a missing drain nozzle), all in Spanish, with sizing explicitly pending the adsorbent vendor.",
 "read_by": "Mavlon, read from the documents with AI help before any run, November 2026",
 "items": [
  "V-101 A/B: two vertical mercury adsorbers (non-regenerative adsorbent beds), natural gas, Carlos Villegas plant (PSLCV); ID 3.80 m x 2.95 m T-T, hemispherical heads, skirt support; 1135 psig / 175°F; SA-516 Gr.70N",
  "V-501 D: one vertical mercury adsorber, natural gas, Rio Grande plant (PSLRG); ID 2.40 m x 2.45 m T-T, 2:1 elliptical heads, skirt support; 1150 psig / 120°F on the data sheet (P&ID shows 510°F); SA-516 Gr.70N",
  "Adsorber internals for all three vessels (inlet distributor, outlet collector, floating mesh if needed, removable unloading extension), AISI 316L, designed with the adsorbent supplier",
  "Two 20-inch Y-type start-up strainers for the PSLCV unit (12-2-PRO-DS-10003), ASTM A216 WCB body",
  "One 14-inch Y-type start-up strainer for the PSLRG unit (12-2-PRO-DS-20003), ASTM A216 WCB body"
 ],
 "checks": [
  {
   "n": 1,
   "area": "scope",
   "check": "Which pressure vessels are in scope: tags, quantities, plants and service?",
   "answer": "Three new carbon-steel mercury adsorbers: V-101 A/B, quantity 2, at the Carlos Villegas liquids separation plant (PSLCV); and V-501 D, quantity 1, at the Rio Grande plant (PSLRG). Both data sheets give service \"ADSORBEDOR DE MERCURIO\", fluid natural gas, vertical position.",
   "evidence": "Anexo 4.pdf, p. 7; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6",
   "quote": "1 V-101 A/B 2 PSLCV CS 175 1135 ... 2 V-501 D 1 PSLRG CS 120 1150"
  },
  {
   "n": 2,
   "area": "geometry",
   "check": "V-101 A/B: inside diameter, tangent-to-tangent length and head type?",
   "answer": "Inside diameter 3.80 m, height tangent-to-tangent 2.95 m, hemispherical heads (\"SEMIESFERICO\"); volume T-T 33.46 m3. The equipment list repeats 3800 mm x 2950 mm and 33.46 m3.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/3.3 Equipos.pdf, p. 3",
   "quote": "ALTURA (T-T) 2,95 m ... DIÁMETRO INTERNO: 3,80 m ... TIPO CABEZAL SEMIESFERICO"
  },
  {
   "n": 3,
   "area": "geometry",
   "check": "V-501 D: inside diameter, tangent-to-tangent length and head type?",
   "answer": "Inside diameter 2.40 m, height tangent-to-tangent 2.45 m, 2:1 elliptical heads (\"ELÍPTICO (2:1)\"); volume T-T 11.08 m3. The equipment list repeats 2400 mm x 2450 mm and 11.08 m3.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6; Anexo 13 Documentos de Ingenieria Basica/3.3 Equipos.pdf, p. 3",
   "quote": "ALTURA (T-T) 2,45 m ... DIÁMETRO INTERNO 2,40 m ... TIPO CABEZAL ELÍPTICO (2:1)"
  },
  {
   "n": 4,
   "area": "design",
   "check": "V-101 A/B: design pressure, design temperature, minimum design temperature and operating conditions?",
   "answer": "Design 1135 psig at 175°F; minimum design temperature 54°F. Operating 942.6 psig at 131°F, gas flow 1178 MMSCFD, downward flow. The P&ID callout (P dis 1135 psig, T dis 175°F) and the equipment list agree on design conditions.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.4 Diagramas de tuberia e instrumentacion.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/3.3 Equipos.pdf, p. 3",
   "quote": "TEMPERATURA DE OPERACIÓN 131 ºF ... PRESIÓN DE DISEÑO 1135 psig ... TEMPERATURA DE DISEÑO 175 ºF ... TEMPERATURA MÍNIMA DE DISEÑO 54 ºF"
  },
  {
   "n": 5,
   "area": "design",
   "check": "V-501 D: design pressure, design temperature, minimum design temperature and operating conditions?",
   "answer": "Data sheet: design 1150 psig at 120°F; minimum design temperature 54°F. Operating 806 psig at 86.86°F, gas flow 209.5 MMSCFD, downward flow. The equipment list, Anexo 4 Table 1 and the PSV-50300/50301 data sheet also give 120°F, but the P&ID callout gives 54/510°F (see contradictions).",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6; Anexo 13 Documentos de Ingenieria Basica/3.3 Equipos.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/4.1 Valvulas de Seguridad.pdf, p. 6",
   "quote": "TEMPERATURA DE OPERACIÓN 86,86 ºF ... PRESIÓN DE DISEÑO 1150 psig ... TEMPERATURA DE DISEÑO 120 ºF ... TEMPERATURA MÍNIMA DE DISEÑO 54 ºF"
  },
  {
   "n": 6,
   "area": "code",
   "check": "Design code, ASME U stamp and National Board registration?",
   "answer": "Designed, fabricated, tested and inspected to ASME Section VIII Division 1, latest edition. All vessels must carry the ASME \"U\" stamp and be registered with the National Board (NB). Both vessel data sheets also give \"ASME SECC. VIII, DIV.1 (ULTIMA ED.)\" and tick SI for U stamp and NB registration (tick boxes read from the rendered image).",
   "evidence": "Anexo 6.pdf, p. 1; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6",
   "quote": "ASME Secc. VIII, División 1 en su Última Edición ... deberán tener estampa “U” de ASME y deberán estar registrados en la National Board (NB)"
  },
  {
   "n": 7,
   "area": "code",
   "check": "Inspection agency: who must release the vessels before shipment?",
   "answer": "Mechanical completion requires acceptance by an ASME Authorized Inspection Agency (AIA)/third party, and the vessels may not be prepared for shipment until released and accepted by an Authorized Inspector (IA) of the AIA. No specific inspection agency is named in any of the 29 files (text layers searched).",
   "evidence": "Anexo 6.pdf, p. 20",
   "quote": "liberados aceptados por un Inspector Autorizado (IA) de la AIA y no estén autorizados para el envío"
  },
  {
   "n": 8,
   "area": "materials",
   "check": "Shell, heads, skirt and external attachment materials?",
   "answer": "Shell and heads SA-516 Gr.70N; skirt \"SA 516 Gr.70N/SA-36\" with note 13 (a support or attachment of a different material must be welded on a transition pad of the shell material); reinforcements, clips and lifting lugs SA-516 Gr.70N. Same on both vessel data sheets.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 4; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6",
   "quote": "ENVOLVENTE: SA-516 Gr.70N CABEZAL: SA-516 Gr.70N ... SA 516 Gr.70N/SA-36 ... REFUERZOS, CLIPS, OREJAS DE IZAJE SA-516 Gr.70N"
  },
  {
   "n": 9,
   "area": "materials",
   "check": "Nozzle pipe, flanges, gaskets and external bolting materials?",
   "answer": "Nozzle pipe SA-106 Gr B; flanges and blind flanges SA-105; spiral-wound gaskets; bolts SA-193-2B7 M and nuts SA-194-2H M, both \"Cincado-Bibromatizado Dorado\". Same on both vessel data sheets.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6",
   "quote": "TUBERÍA: SA-106 Gr B BRIDAS/BRIDAS CIEGAS SA-105 JUNTAS: JUNTA ESPIROMETALICA SA-193-2B7 M Cincado-"
  },
  {
   "n": 10,
   "area": "materials",
   "check": "Internals materials?",
   "answer": "Internal structure AISI SS-316L; internal bolts SA-193 Gr B8 CL1; internal nuts SA-194 Gr.8 (both data sheets). Anexo 6 adds that internal support rings and clips welded to the shell are the same material as the shell.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6; Anexo 6.pdf, p. 13",
   "quote": "ESTRUCTURA INTERNO AISI SS-316L PERNOS: SA-193 Gr B8 CL1 TUERCAS: SA-194 Gr.8"
  },
  {
   "n": 11,
   "area": "materials",
   "check": "Corrosion allowance?",
   "answer": "Minimum 3.2 mm (0.125 in) for the vessel, added to all pressure parts in contact with the product; nozzles and manholes at least the shell value. Both vessel data sheets give 0.125 in.",
   "evidence": "Anexo 6.pdf, p. 11; Anexo 6.pdf, p. 12; Anexo 6.pdf, p. 9; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6",
   "quote": "La tolerancia mínima a la corrosión que debe aplicarse para el recipiente a presión es de 3,2 mm (0,125 pulg.)"
  },
  {
   "n": 12,
   "area": "fabrication",
   "check": "Radiography and post-weld heat treatment on the vessel data sheets?",
   "answer": "Radiography 100%; heat treatment \"POR CÓDIGO\" (as the code requires), on both vessel data sheets. Anexo 6: any X-ray testing is done after heat treatment.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6; Anexo 6.pdf, p. 21",
   "quote": "RX: 100% TRATAMIENTO TÉRMICO POR CÓDIGO"
  },
  {
   "n": 13,
   "area": "fabrication",
   "check": "What must the PWHT procedure contain?",
   "answer": "PWHT per the ASME code. Before PWHT the supplier submits a PWHT procedure for approval with a scheme of thermocouple locations and quantity, temporary supports and a detailed description of the furnace (dimensions, burners, temperature records). PWHT of the vessel in one piece in a furnace is recommended; no welding on PWHT parts after PWHT; the supplier provides temporary supports and calibrated furnace instruments.",
   "evidence": "Anexo 6.pdf, p. 16; Anexo 6.pdf, p. 15",
   "quote": "un esquema indicando la localización y cantidad de termopares que se van a utilizar, soportes temporales y una descripción detallada del tipo de horno"
  },
  {
   "n": 14,
   "area": "testing",
   "check": "Hardness testing requirements?",
   "answer": "Vickers hardness per ASTM E 92 on the procedure qualification samples, measured on weld deposit, HAZ and base metal at three levels (both surfaces and mid-thickness); hardness test on the welds after PWHT. No numeric hardness limit is given in any file (text layers searched).",
   "evidence": "Anexo 6.pdf, p. 14; Anexo 6.pdf, p. 16",
   "quote": "la prueba de dureza de Vickers deberá estar de acuerdo con ASTM E 92 y se deben realizar en las muestras de calificación de procedimiento"
  },
  {
   "n": 15,
   "area": "testing",
   "check": "Is impact (Charpy) testing required?",
   "answer": "Not stated. No impact test requirement appears in the text layer of any of the 29 files. The only related value is the minimum design temperature of 54°F on both vessel data sheets; the piping spec (Anexo 7) only lists \"ASTM A516 Impact Tested Carbon Steel Plate\" among reference standards.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6; Anexo 7.pdf, p. 12",
   "quote": "TEMPERATURA MÍNIMA DE DISEÑO 54 ºF"
  },
  {
   "n": 16,
   "area": "nozzles",
   "check": "V-101 A/B nozzle schedule?",
   "answer": "C01 6\" unloading nozzle, quantity TBD (note 2: orientation for maximum adsorbent extraction, maximum suggested angle 30°, number of nozzles defined in detail engineering); G01 2\" vent; I01 20\" gas inlet; I02 20\" gas outlet; M01 and M02 24\" manholes; N01 2\" drain. All LWNRF; class and schedule TBD, projection left blank; vent and manhole diameters \"to be confirmed in detail engineering\".",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 4",
   "quote": "C01 TBD 6 \" LWNRF TBD TBD mm Boquilla de Vaciado"
  },
  {
   "n": 17,
   "area": "nozzles",
   "check": "V-501 D nozzle schedule?",
   "answer": "C01 6\" unloading nozzle, quantity TBD; G01 2\" vent; I01 14\" gas inlet; I02 14\" gas outlet; M01 and M02 24\" manholes. All WNRF; class and schedule TBD, projection left blank; vent and manhole diameters to be confirmed in detail engineering. No drain nozzle is listed (see contradictions).",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6",
   "quote": "I01 1 14 \" WNRF TBD TBD mm Entrada de Gas"
  },
  {
   "n": 18,
   "area": "nozzles",
   "check": "Flange and gasket standards?",
   "answer": "Flanges RF per ASME B16.5 with 125-250 microinch face finish; spiral-wound gaskets AISI 316 stainless per ASME B16.20, asbestos not acceptable. Anexo 6: flanges above 24\" per ASME B16.47 Series A; self-reinforced Long Welding Neck flanges recommended for high-pressure vessels unless the data sheet says otherwise.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 4; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 7; Anexo 6.pdf, p. 9",
   "quote": "Las bridas seran RF de acuerdo ASME B16.5 ... 125-250 microinches ... juntas espirometalicas AC. Inox. AISI 316, seran de acuerdo ASME B16.20"
  },
  {
   "n": 19,
   "area": "design",
   "check": "Nozzle load analysis required?",
   "answer": "Yes. Nozzles designed for external piping loads; local loads calculated with WRC 107/297 using the internal-pressure stress intensity factor and checked against ASME VIII Div.2 Part 5 stress-intensity limits by finite element analysis, in corroded condition and at design conditions.",
   "evidence": "Anexo 6.pdf, p. 8; Anexo 6.pdf, p. 9",
   "quote": "Las cargas locales en las conexiones se calcularán con WRC 107/297 ... según ASME VIII Div.2 Parte 5 mediante análisis finitos en condiciones corroídas"
  },
  {
   "n": 20,
   "area": "design",
   "check": "Fatigue analysis required?",
   "answer": "Data sheet note 9 (both vessels): fatigue analysis calculations per ASME VIII Div.2 (latest edition), to be part of the mechanical design. Anexo 6 also asks for study of secondary stresses from differential thermal expansion and fatigue, and for cyclic loads where UG-22(e) or Div.2 para. 5.5 requires (see contradictions).",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 4; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 7; Anexo 6.pdf, p. 8; Anexo 6.pdf, p. 13",
   "quote": "Cálculos de análisis de fatiga debera ser acorde ASME VIII, Div.2 (Ultima Edicion) para ser considerados parte del diseño mecánico."
  },
  {
   "n": 21,
   "area": "design",
   "check": "What must the mechanical calculation cover, and what load cases?",
   "answer": "All components, supports, lifting elements, platforms and ladders, nozzle loads, anchor bolts and transport saddles, using internationally recognized software; vessels designed to allow a hydrostatic test in vertical position in corroded condition. Loads include pressure and hydrostatic head, weight, piping reactions, wind, earthquake and ice, differential thermal stresses and erection; vertical vessels and supports carry a full water load.",
   "evidence": "Anexo 6.pdf, p. 7; Anexo 6.pdf, p. 6; Anexo 6.pdf, p. 8",
   "quote": "elementos de izado, plataformas y escaleras, cargas en conexiones, pernos de anclaje, cunas de transporte ... prueba hidrostática en posición vertical y en estado corroído"
  },
  {
   "n": 22,
   "area": "supports",
   "check": "Supports, platforms, ladders, davits and lifting lugs?",
   "answer": "Skirt support (\"FALDON\"). Foundations, skirt, supports, platforms, lifting lugs and davit are calculated in detail engineering; the supply includes ladders, platforms and davit as required, and lifting lugs; the manhole cover must have a davit (note 10). Anexo 6: skirt to ASME VIII Div.1 with ventilation and access openings; contractor supplies carbon-steel anchor-bolt templates; ladder and platform supports welded in the shop.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 4; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 7; Anexo 6.pdf, p. 8; Anexo 6.pdf, p. 9; Anexo 6.pdf, p. 15",
   "quote": "Fundaciones, faldon, soportes, plataformas, orejas de izaje y pescante a ser calculados en la ingenieria de detalle ... debe contemplar escaleras, plataformas, davit según se requieran"
  },
  {
   "n": 23,
   "area": "testing",
   "check": "Hydrostatic test requirements?",
   "answer": "All vessels and components hydrostatically tested in the shop per ASME VIII Div.1; test before painting and after all welding; test value shown on the vessel engineering drawing; vessels dried with ambient air after acceptance; contractor supplies the test water, and if testing is done at site, disposes of it where YPFB says.",
   "evidence": "Anexo 6.pdf, p. 20; Anexo 6.pdf, p. 19",
   "quote": "Todos los recipientes a presión y sus componentes deben ser probados hidrostáticamente en el taller de acuerdo con ASME Secc. VIII, Div. 1"
  },
  {
   "n": 24,
   "area": "testing",
   "check": "Positive material identification (PMI)?",
   "answer": "PMI per API 578, in the shop and/or at site, at YPFB's absolute discretion; the contractor provides personnel, consumables and equipment, at its own cost. Materials come with mill test reports (MTR) and traceability.",
   "evidence": "Anexo 6.pdf, p. 18",
   "quote": "solicitará a su absoluta discreción al CONTRATISTA la Identificación Positiva de los Materiales (PMI, conforme API 578) tanto en Taller (Fabrica) y/o en Sitio"
  },
  {
   "n": 25,
   "area": "documents",
   "check": "Inspection and test plans and hold points?",
   "answer": "Supplier issues a single quality control plan; ITP and inspection activity plans (IAP) approved before fabrication starts; YPFB defines the hold points and witness points; test dates notified to YPFB at least 30 days in advance; final tests witnessed by the contractor, YPFB and the third party needed for ASME stamp certification.",
   "evidence": "Anexo 6.pdf, p. 19; Anexo 6.pdf, p. 18",
   "quote": "para que este último (YPFB) defina los HOLD- POINTS y WITNESSES requeridos ... por lo menos con 30 días de anticipación"
  },
  {
   "n": 26,
   "area": "commercial",
   "check": "YPFB shop inspections: who pays, and how many?",
   "answer": "The contractor covers transport and stay of one person from YPFB or its supervision (FISCALIZACIÓN) for inspections at the vessel fabricator, local or abroad; YPFB will require two hold-point/witness inspections in the shop.",
   "evidence": "RG-02-A-GCC - ESP TEC IPC URM FINAL.pdf, p. 54; RG-02-A-GCC - ESP TEC IPC URM FINAL.pdf, p. 12; RG-02-A-GCC - ESP TEC IPC URM FINAL.pdf, p. 13",
   "quote": "gastos de transporte y estadía (si aplica) de una (1) persona del CONTRATANTE ... el CONTRATANTE requerirá dos hold-points/witness y de inspección en taller"
  },
  {
   "n": 27,
   "area": "coating",
   "check": "Painting and insulation on the vessel data sheets?",
   "answer": "External paint yes, internal paint no, no insulation, on both vessel data sheets.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6",
   "quote": "AISLAMIENTO NO ... PINTURA INTERNA: NO ... PINTURA EXTENA: SI"
  },
  {
   "n": 28,
   "area": "coating",
   "check": "Which paint system, and any transport condition?",
   "answer": "Paint per the plant reference documents listed in Anexo 6 section 5 (PSLCV: 8535-WP-001-E Painting and Coating Specification; PSLRG: 3285-G000-634-2021-DB-900). If the vessels are fabricated abroad and shipped by sea, the contractor must consider marine atmospheric corrosion when choosing the paint system. Dry film thickness of each coat inspected.",
   "evidence": "Anexo 6.pdf, p. 16; Anexo 6.pdf, p. 4; Anexo 6.pdf, p. 20",
   "quote": "sean fabricados en el extranjero y sean importados por vía marítimo, el CONTRATISTA deberá considerar la corrosión atmósfera marina"
  },
  {
   "n": 29,
   "area": "documents",
   "check": "What goes in the vessel quality dossier?",
   "answer": "Among others: fabrication certificate, material certificates and MTRs, weld map, WPS, PQR, WPQ, NDE and PWHT procedures, hydrotest procedure and certificate, PMI records, dimensional record, heat-treatment charts, radiograph location drawing, ASME stamping certificate, National Board registration certificate, transport, preservation and installation procedures, as-built drawing with actual thicknesses, nameplate; then a final Data Book.",
   "evidence": "Anexo 6.pdf, p. 24; Anexo 6.pdf, p. 25",
   "quote": "Certificado de estampado según ASME. - Certificado de registro en la NB (National Board)."
  },
  {
   "n": 30,
   "area": "scope",
   "check": "Vessel supply scope: does it include transport and installation?",
   "answer": "Yes. Vessel supply covers detail engineering, materials, labour, fabrication, inspection, tests, painting, packing, preparation for shipment, transport and installation at site; the contractor prepares erection and lifting plans and carries the whole logistics chain to PSLCV and PSLRG, including customs and import costs.",
   "evidence": "Anexo 6.pdf, p. 1; Anexo 6.pdf, p. 2; Anexo 6.pdf, p. 3",
   "quote": "pintura, embalaje, preparación para el envío, transporte e instalación en sitio"
  },
  {
   "n": 31,
   "area": "scope",
   "check": "Who designs the adsorber internals?",
   "answer": "Inlet distributor and outlet collector are sized in detail engineering following the adsorbent supplier's recommendations; the need for a floating mesh is decided in detail engineering; the outlet collector must carry the bed load; the internal extension of the unloading flange must be removable.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 4; Anexo 1.pdf, p. 11; Anexo 1.pdf, p. 12",
   "quote": "En la ingeniería de detalle se dimensionara el distribuidor de entrada y el colector de salida ... La necesidad de malla flotante se determinara"
  },
  {
   "n": 32,
   "area": "scope",
   "check": "Are the data-sheet dimensions final, and who re-sizes the vessels?",
   "answer": "No. All dimensions are preliminary and must be confirmed by the fabricator (note 6). At project start the CONTRACTOR must adjust vessel dimensions to the selected adsorbent supplier's definitions (note 15; also Anexo 6 section 7.1).",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 4; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 7; Anexo 6.pdf, p. 7",
   "quote": "Todas las dimensiones son preliminares y deben ser confirmados por el Fabricante ... el CONTRATISTA deberá ajustar las dimensiones de los recipientes"
  },
  {
   "n": 33,
   "area": "commercial",
   "check": "How should bidders price the expected re-sizing, and how urgent are the vessels?",
   "answer": "YPFB pre-sized the vessels for one specific adsorbent; dimensions will be adjusted once the contractor confirms the adsorbent vendor, and bidders must include the needed margins in their proposal. The data sheets and drawings of V-501D and V-101 A and B are on the project critical path, with an early purchase order for the vessels.",
   "evidence": "RG-02-A-GCC - ESP TEC IPC URM FINAL.pdf, p. 22; RG-02-A-GCC - ESP TEC IPC URM FINAL.pdf, p. 23",
   "quote": "debe considerar los márgenes necesarios en previsión de tales cambios e incluirlos en su propuesta ... parte de la ruta crítica del proyecto"
  },
  {
   "n": 34,
   "area": "design",
   "check": "Carlos Villegas strainer (12-2-PRO-DS-10003): quantity, size and design data?",
   "answer": "Quantity 2; 20\" NPS, schedule S-60; Y type (to be confirmed by the EPC contractor with the supplier); flanged ends; 10 µm mesh; gas flow 589 MMSCFD (system total 1178 MMSCFD); design 1135 psig at 175°F, minimum 54°F; code ASME Sec. VIII Div1 and ASME B16.34; RX 100%; heat treatment per code; corrosion allowance per the piping class (note 6); inlet and outlet 20\" WNRF, class TBD. Described as a start-up device against adsorbent fines.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5.1 Filtros (strainers).pdf, p. 3",
   "quote": "CANTIDAD: 2 (DOS) ... DIAM. NOMINAL (NOMINAL PIPE SIZE) 20 inch. ... ESPESOR DE PARED (SCHEDULE) S-60 ... TIPO \"Y\" (Nota 2)"
  },
  {
   "n": 35,
   "area": "design",
   "check": "Rio Grande strainer (12-2-PRO-DS-20003): quantity, size and design data?",
   "answer": "Quantity 1; 14\" NPS, schedule S-80; Y type (to be confirmed); flanged ends; 10 µm mesh; 209.5 MMSCFD; design 1150 psig at 120°F, minimum 54°F; code ASME Sec. VIII Div1 and ASME B16.34; RX \"100% (SI APLICA)\"; heat treatment per code; corrosion allowance per piping class; inlet and outlet 14\" WNRF, class TBD.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5.1 Filtros (strainers).pdf, p. 5",
   "quote": "CANTIDAD: 1 (UNO) ... DIAM. NOMINAL (NOMINAL PIPE SIZE) 14 inch. ... ESPESOR DE PARED (SCHEDULE) S-80 ... 100% (SI APLICA)"
  },
  {
   "n": 36,
   "area": "materials",
   "check": "Strainer materials?",
   "answer": "Body ASTM A216 Gr. WCB; screen and mesh 304 SS - 316 SS (screens per ASTM E 674, mesh per ASTM E 2016); studs/nuts ASTM A193 Gr.B7/A194 Gr.2H; spiral-wound SS316 gasket with graphite filler (non-asbestos); flanged cover with drain and plug, ASTM A105; flanges per ASME B16.5 with 125-250 µin finish; body marking per MSS SP-25 with contractor and YPFB codes. Same on both strainer sheets.",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5.1 Filtros (strainers).pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.5.1 Filtros (strainers).pdf, p. 5",
   "quote": "CUERPO (BODY) ASTM A216 GR. WCB ... PERNOS/TUERCAS (STUDS/BOLTING) ASTM A193 GR.B7/A194 GR.2H ... BRIDA CON CON DRENAJE Y TAPON / ASTM A105"
  },
  {
   "n": 37,
   "area": "nozzles",
   "check": "Strainer pressure class?",
   "answer": "The strainer data sheets leave the connection class TBD (\"TDB = To be defined by EPC contractor\"). The piping MTOs list each Y-strainer as ASME B16.5 Class 600, raised-face flanged (PSLCV inlet and outlet lines, PSLRG outlet line).",
   "evidence": "Anexo 13 Documentos de Ingenieria Basica/3.2 Tuberias.pdf, p. 5; Anexo 13 Documentos de Ingenieria Basica/3.2 Tuberias.pdf, p. 6; Anexo 13 Documentos de Ingenieria Basica/3.2 Tuberias.pdf, p. 29; Anexo 13 Documentos de Ingenieria Basica/2.5.1 Filtros (strainers).pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.5.1 Filtros (strainers).pdf, p. 5",
   "quote": "Y-STRAINER, ASME B16.5, CLASS 600, RAISED FACE FLANGED END"
  },
  {
   "n": 38,
   "area": "commercial",
   "check": "Overall execution time for the EPC?",
   "answer": "Maximum 430 calendar days for the whole project (engineering, procurement, construction, pre-commissioning, commissioning, start-up and performance tests) at both plants, from the working day after the Order to Proceed to provisional acceptance of both units.",
   "evidence": "RG-02-A-GCC - ESP TEC IPC URM FINAL.pdf, p. 16",
   "quote": "es de 430 días calendario, computable a partir del día hábil siguiente de la emisión de la Orden de Proceder"
  }
 ],
 "contradictions": [
  {
   "topic": "V-501 D design temperature",
   "side_a": "Vessel data sheet 12-2-PRO-DS-20001: \"TEMPERATURA DE DISEÑO 120 ºF\". The equipment list, Anexo 4 Table 1 and the PSV-50300/50301 data sheet (\"1150 Psig 120 °F\") also give 120°F.",
   "side_a_evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6; Anexo 13 Documentos de Ingenieria Basica/3.3 Equipos.pdf, p. 3; Anexo 4.pdf, p. 7; Anexo 13 Documentos de Ingenieria Basica/4.1 Valvulas de Seguridad.pdf, p. 6",
   "side_b": "P&ID 12-2-PRO-PI-20002, V-501D callout: \"Pd = 1150 psig @ 54/510 F\".",
   "side_b_evidence": "Anexo 13 Documentos de Ingenieria Basica/2.4 Diagramas de tuberia e instrumentacion.pdf, p. 7",
   "why_it_matters": "Design temperature goes into the thickness calculation; 510°F against 120°F changes plate thickness and weight, so the basis must be confirmed before pricing.",
   "status": "confirmed"
  },
  {
   "topic": "V-101 A/B operating temperature (Carlos Villegas)",
   "side_a": "Vessel data sheet 12-2-PRO-DS-10001: \"TEMPERATURA DE OPERACIÓN 131 ºF\" (the PSLCV strainer sheet also gives 131°F).",
   "side_a_evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3; Anexo 13 Documentos de Ingenieria Basica/2.5.1 Filtros (strainers).pdf, p. 3",
   "side_b": "URM process specification 12-2-PRO-SP-10001 inlet conditions: \"Temperatura °F 110\"; adsorbent data sheet 12-2-PRO-DS-10002: \"Temperatura 110 °F (43.3°C)\".",
   "side_b_evidence": "Anexo 13 Documentos de Ingenieria Basica/2.2 Especificacion tecnica URM.pdf, p. 5; Anexo 13 Documentos de Ingenieria Basica/2.6 Adsorbentes.pdf, p. 3",
   "why_it_matters": "The operating case feeds the adsorbent vendor's bed sizing, which re-sizes the vessels; the contractor has to say which temperature governs before dimensions are frozen.",
   "status": "confirmed"
  },
  {
   "topic": "V-501 D operating conditions (Rio Grande)",
   "side_a": "Vessel data sheet 12-2-PRO-DS-20001: \"TEMPERATURA DE OPERACIÓN 86,86 ºF ... PRESION DE OPERACIÓN 806 psig\" (repeated on the PSLRG strainer sheet and the PSV data sheet).",
   "side_a_evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6; Anexo 13 Documentos de Ingenieria Basica/2.5.1 Filtros (strainers).pdf, p. 5; Anexo 13 Documentos de Ingenieria Basica/4.1 Valvulas de Seguridad.pdf, p. 6",
   "side_b": "URM process specification 12-2-PRO-SP-20001 inlet conditions: \"Temperatura °F 75 ... Presión Psia 855\" (the adsorbent data sheet 12-2-PRO-DS-20002 also gives 75°F and 855 psia).",
   "side_b_evidence": "Anexo 13 Documentos de Ingenieria Basica/2.2 Especificacion tecnica URM.pdf, p. 11; Anexo 13 Documentos de Ingenieria Basica/2.6 Adsorbentes.pdf, p. 5",
   "why_it_matters": "Two different operating cases for the same vessel; the vendor resizing and the strainer selection depend on which one governs.",
   "status": "confirmed"
  },
  {
   "topic": "Strainers: temporary start-up device or permanent?",
   "side_a": "Strainer data sheet note 1: \"El strainer servirá como un dispositivo de puesta en marcha\"; technical specification: \"hoja de datos preliminar para los filtros temporales de partículas de cada URM\".",
   "side_a_evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5.1 Filtros (strainers).pdf, p. 3; RG-02-A-GCC - ESP TEC IPC URM FINAL.pdf, p. 9",
   "side_b": "Piping MTO, each Y-strainer: \"RAISED FACE FLANGED END, PERMANENT\" (PSLCV inlet and outlet lines, PSLRG outlet line).",
   "side_b_evidence": "Anexo 13 Documentos de Ingenieria Basica/3.2 Tuberias.pdf, p. 5; Anexo 13 Documentos de Ingenieria Basica/3.2 Tuberias.pdf, p. 6; Anexo 13 Documentos de Ingenieria Basica/3.2 Tuberias.pdf, p. 29",
   "why_it_matters": "A temporary start-up strainer and a permanent in-line Y-strainer are different products with different prices; the strainer supplier needs to know which one to quote.",
   "status": "confirmed"
  },
  {
   "topic": "V-501 D drain nozzle",
   "side_a": "V-501 D data sheet nozzle list ends at the manholes with no drain: C01, G01, I01, I02, M01, M02; last line \"M02 1 24 \" WNRF TBD TBD mm Entrada de Hombre\". (The V-101 A/B sheet does list N01 2\" drain.)",
   "side_a_evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 6; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3",
   "side_b": "PSLRG line list 12-2-MEC-LT-20002: a 2\" drain line starting at the vessel, \"2 DR 50208 CA100 L B - V-501D 2\"-DR-50209-CB10-B\".",
   "side_b_evidence": "Anexo 13 Documentos de Ingenieria Basica/3.2 Tuberias.pdf, p. 27",
   "why_it_matters": "The line list needs a 2\" drain connection on V-501 D that is not in its nozzle list, so the nozzle count on the quote would be short by one.",
   "status": "confirmed"
  },
  {
   "topic": "Tag V-101: adsorbers or dehydrators?",
   "side_a": "URM process specification 12-2-PRO-SP-10001: \"El gas tratado en la URM es enviado hacia los deshidratadores V-101 A/B/C/D\".",
   "side_a_evidence": "Anexo 13 Documentos de Ingenieria Basica/2.2 Especificacion tecnica URM.pdf, p. 4",
   "side_b": "Piping MTO: \"LÍNEA \"B\" DE SALIDA DE FLUIDO DE V-101A/B A V-102A/B/C/D\"; the vessel data sheet uses V-101 A/B for the two new adsorbers.",
   "side_b_evidence": "Anexo 13 Documentos de Ingenieria Basica/3.2 Tuberias.pdf, p. 6; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 3",
   "why_it_matters": "The same tag is used for the existing dehydrators and the new adsorbers; a reader counting \"V-101\" units could quote four vessels instead of two.",
   "status": "confirmed"
  },
  {
   "topic": "Drawing referenced by data sheet note 14",
   "side_a": "Both vessel data sheets, note 14: \"Para mayor detalle del diagrama y distancias referirse al documento 12-2-MEC-DW-10001.\"",
   "side_a_evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 4; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 7",
   "side_b": "Anexo 1 lists \"12-2-MEC-DW-10001 - MAQUETA 3D URM-PSLCV\" (the 3D model); the adsorber diagrams are numbered 12-2-MEC-DW-10002 (V-101 A y B) and 12-2-MEC-DW-20002 (V-501D).",
   "side_b_evidence": "Anexo 1.pdf, p. 6; Anexo 13 Documentos de Ingenieria Basica/3.3 Equipos.pdf, p. 4; Anexo 13 Documentos de Ingenieria Basica/3.3 Equipos.pdf, p. 5",
   "why_it_matters": "Low price impact: the reference points to the 3D model, while the vessel diagrams with layer heights and the 1500 mm minimum skirt are in 3.3 Equipos pp. 4-5.",
   "status": "confirmed"
  },
  {
   "topic": "Fatigue analysis: always or only if the code requires it?",
   "side_a": "Vessel data sheets note 9: \"Cálculos de análisis de fatiga debera ser acorde ASME VIII, Div.2 (Ultima Edicion) para ser considerados parte del diseño mecánico.\"",
   "side_a_evidence": "Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 4; Anexo 13 Documentos de Ingenieria Basica/2.5 Recipientes.pdf, p. 7",
   "side_b": "Anexo 6 section 8.6 makes cyclic-load design conditional: \"si así lo exige el párrafo del Código UG-22 (e) o ASME Secc. VIII, Div. 2 Párrafo 5.5\".",
   "side_b_evidence": "Anexo 6.pdf, p. 13",
   "why_it_matters": "A Div.2 fatigue analysis is extra engineering cost; the data sheet reads as mandatory while the vessel specification reads as conditional. Marked likely because note 9 can also be read as only setting the method.",
   "status": "likely"
  },
  {
   "topic": "Hydrostatic test location: shop or site?",
   "side_a": "Anexo 6: \"Todos los recipientes a presión y sus componentes deben ser probados hidrostáticamente en el taller de acuerdo con ASME Secc. VIII, Div. 1\".",
   "side_a_evidence": "Anexo 6.pdf, p. 20",
   "side_b": "Same page: \"En caso de que las pruebas hidráulicas de los recipientes se realice en sitio\", the contractor disposes of the water where YPFB says.",
   "side_b_evidence": "Anexo 6.pdf, p. 20",
   "why_it_matters": "A site hydrotest adds water supply, disposal and field work; it is not clear whether a site test is extra, an alternative, or only for vessels assembled at site. Marked likely because both clauses can be read as compatible.",
   "status": "likely"
  }
 ]
}