 "id": "kenya-gdc-geothermal-separators",
 "country": "Kenya",
 "language": "English",
 "buyer": "Geothermal Development Company Ltd (GDC)",
 "project": "Connection of Additional Wells to the Menengai 105 MWe Steam Gathering System (EPC) - tender GDC/GRM/OT/005/2024:2025",
 "year": "2024",
 "files": [
  {
   "file": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf",
   "pages": 302,
   "text_layer": true,
   "what_it_is": "Single EPC tender document: instructions and forms (pp. 1-67), employer's requirements incl. scope, well/separator table, site data, piping/valve specs, codes, FAT (pp. 68-112), electrical and I&C (pp. 113-135), general technical requirements incl. welding, NDE, PMI, PWHT, painting, inspection and testing (pp. 136-199), work plan and evaluation criteria (pp. 201-205), price schedules (pp. 206-212), conditions of contract and forms (pp. 213-302)."
  }
 ],
 "quality": "Design-build tender with no vessel data sheet: the separators appear only as approximate t/hr capacities, and vessel rules are scattered through generic power-plant boilerplate that contradicts itself (RT extent, inspection travel, welding approval, separator tags).",
 "read_by": "Mavlon, read from the documents with AI help before any run, November 2026",
 "items": [
  "SS4 - new separator vessel for well MW-36, design capacity about 300 t/hr (approximate)",
  "SS8 - new separator vessel for well MW-37, design capacity about 150 t/hr (approximate)",
  "SS9 - new separator vessel for well MW-38, design capacity about 200 t/hr (approximate)",
  "Atmospheric flash tanks with weir boxes at MW-19B, MW-36, MW-37, MW-38, MW-22 and MW-07 (price schedule names only MW-19B as a flash tank; others appear as 'silencers')",
  "Associated two-phase, steam and brine piping, valves, rupture discs, platforms and ladders (EPC scope, not vessels)"
 ],
 "checks": [
  {
   "n": 1,
   "area": "scope",
   "check": "Which new pressure vessels are in scope?",
   "answer": "Three new separator vessels: SS4 for well MW-36, SS8 for MW-37 and SS9 for MW-38 (section 3.1.7). Wells MW-09B/19B, MW-10B, MW-13B and MW-17A go to existing separators SS3, SS6, SS2 and SS1.",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 71",
   "quote": "The three production wells MW-36, MW-37 and MW-38 will be connected to new individual separator vessels SS4, SS8 and SS9 respectively."
  },
  {
   "n": 2,
   "area": "design",
   "check": "What capacity and inlet flow are given for the new separators?",
   "answer": "Design capacity SS4 300 t/hr (MW-36 two-phase flow 100 t/hr, p. 69), SS8 150 t/hr (MW-37 100 t/hr), SS9 200 t/hr (MW-38 150 t/hr). All these values are flagged ** approximate, to be updated by the employer. No pressure, temperature, steam fraction or size is given.",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 70",
   "quote": "7 MW-37 100** SS8 150** N/A N/A 8 MW-38 150** SS9 200** N/A N/A ** - Approximate values."
  },
  {
   "n": 3,
   "area": "scope",
   "check": "Which flash tanks are in scope?",
   "answer": "Flash tanks with weir boxes at six wells: MW-19B, MW-36, MW-37, MW-38 and reinjection wells MW-22 and MW-07 (scope list). Section 3.1.2 calls the MW-19B one an atmospheric flash tank.",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 70",
   "quote": "Flash tanks and weir boxes at wells MW-19B, MW-36, MW-37, MW-38 and reinjection wells MW-22 and MW-07."
  },
  {
   "n": 4,
   "area": "scope",
   "check": "Who designs the separators and flash tanks?",
   "answer": "Design-build (EPC): the contractor does detailed design and construction drawings for employer approval; details of separators, flash tanks and other equipment are to be provided by the manufacturer the contractor buys from.",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 72",
   "quote": "Details of equipment to be installed such as instrumentation, valves, actuators, pipelines, separators, flash tanks and other items shall be provided by the manufacturer"
  },
  {
   "n": 5,
   "area": "design",
   "check": "Are vessel design pressure, temperature, dimensions or a data sheet given?",
   "answer": "No. There is no vessel data sheet and no design pressure, design temperature, MAWP, diameter, height, corrosion allowance or nozzle list for the separators or flash tanks anywhere in the 302 pages (full text layer searched; the only images are the cover logo and a few blank decorative fragments, and page 2 is blank). Only the approximate t/hr capacities are given; everything else is for the EPC contractor to design.",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 72",
   "quote": "This is an EPC contract, and the full construction drawings will be made and provided by the contractor."
  },
  {
   "n": 6,
   "area": "code",
   "check": "What pressure vessel code is named?",
   "answer": "ASME VIII is listed among the standards, but both Division 1 and Division 2 are listed and the document never says which governs the separators. Bolting for ASME pressure equipment to ASME unified threads (p. 146).",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 108",
   "quote": "ASME VIII Div 1 Boiler and Pressure Vessel Design Code, Division 1: Rules for Construction of Pressure Vessels."
  },
  {
   "n": 7,
   "area": "materials",
   "check": "Is a plate material specified for the vessels?",
   "answer": "Not assigned. ASTM A516 appears only in the list of ASTM standards; no material is tied to the separators or flash tanks. Stated constraints: materials suited to geothermal service and corrosion (p. 73), and cast iron not permitted on pressure equipment (p. 147).",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 108",
   "quote": "ASTM A516 Specification for Pressure Vessel Plates, Carbon Steel, for"
  },
  {
   "n": 8,
   "area": "fabrication",
   "check": "What shop qualification is asked for the vessel fabricator?",
   "answer": "Evidence of an ASME-approved facility or workshop where the pressure vessels will be fabricated (manufacturer authorization, 1 mark). Company experience must include at least one geothermal steamfield project with a separator or equivalent high-pressure vessel (p. 204).",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 205",
   "quote": "Pressure vessels (Provide evidence of ASME approved facility/ workshop in which the vessels will be fabricated)."
  },
  {
   "n": 9,
   "area": "fabrication",
   "check": "What radiography is required on the vessels?",
   "answer": "100% radiography of all pressure-retaining welds on pressure vessels; all other welds MT or PT; RT after stress relieving. Shop RT with X-ray throughout (p. 150). The price schedule has a service item for 100% radiography of welded joints (p. 211). See contradiction with the 15% random RT clause.",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 151",
   "quote": "For pressure vessels, all pressure retaining welds shall be 100% radiographed. All other welds shall be either magnetic particle or dye penetrant tested."
  },
  {
   "n": 10,
   "area": "fabrication",
   "check": "Is PMI required?",
   "answer": "Yes, 100% PMI for high-pressure items such as separators, including weld metal; spectrographic or similar testing with records; approved colour coding; no hard stamping.",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 176",
   "quote": "In the case of high-pressure items such as separators, checks shall be on a 100% basis."
  },
  {
   "n": 11,
   "area": "fabrication",
   "check": "Is PWHT required?",
   "answer": "Yes, mandatory for all welds regardless of code, except austenitic stainless, plain carbon steel under 0.25% C up to and including 30 mm thick, and certain thin low-alloy cases. Carbon steels with 0.25-0.4% C: PWHT at 630-670 C; soak 2.5 min/mm, minimum 30 min. Welding after stress relieving is prohibited.",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 178",
   "quote": "it is a mandatory requirement of this Specification that all welds shall be subject to appropriate post weld treatment with the following exceptions"
  },
  {
   "n": 12,
   "area": "testing",
   "check": "What shop pressure test for the separators?",
   "answer": "Hydrotest in the maker's works per the design code at 1.5 times the design pressure of the operating system, held at least 30 minutes, before coating; certificates from the relevant national or international governing bodies.",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 181",
   "quote": "The pressure vessels shall be tested at 1.5 times the design pressure of the relevant operating system."
  },
  {
   "n": 13,
   "area": "testing",
   "check": "What test for atmospheric tanks?",
   "answer": "Prefabricated atmospheric tanks: hydrostatic test filled with water to full cylindrical height, external surfaces chalked, held at least 24 hours.",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 181",
   "quote": "All prefabricated tanks operating at atmospheric pressure shall be subjected to a hydrostatic test with the tank filled with water to full cylindrical height."
  },
  {
   "n": 14,
   "area": "fabrication",
   "check": "How must welders be qualified?",
   "answer": "WPS and PQR to ASME IX; welders' tests witnessed and approved by an authorized third-party authority before they work; welder ID marked on all work; weld map kept for pressure equipment (p. 180).",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 177",
   "quote": "Welders' tests shall be witnessed and approved by an authorized third party authority before the welder or operator is permitted to work."
  },
  {
   "n": 15,
   "area": "testing",
   "check": "Which FATs are witnessed, and who pays travel?",
   "answer": "FAT attended by employer staff for pipes, valves, flow meters and separators. Employer pays air tickets for 4 staff per FAT trip, accommodation and airport transfers; contractor arranges visas, local transport and factory visits.",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 108",
   "quote": "The Employer will take care of Air tickets for 4 No. staff for each FAT trip, accommodation, airport transfers"
  },
  {
   "n": 16,
   "area": "testing",
   "check": "What notice is required for workshop tests?",
   "answer": "Workshop test dates announced at least 15 calendar days ahead; workshop test procedures submitted not later than 45 days before the tests. No shipping or packing until inspected and released or waived in writing (p. 172).",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 171",
   "quote": "procedures along with test for workshop tests shall be submitted not later than 45 days prior to the scheduled tests."
  },
  {
   "n": 17,
   "area": "coating",
   "check": "Which coating system applies to the vessels?",
   "answer": "Not assigned per item. Part F picks systems by surface temperature and exposure, e.g. non-insulated carbon steel tanks and vessels at 100-200 C: blast Sa 2 1/2, inorganic ethyl zinc silicate 75 um, silicone-acrylic coats, total at least 175 um; up to 100 C outdoors (C4): total at least 300 um. The separators' operating temperature is not stated, so the system cannot be fixed from the documents.",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 161",
   "quote": "Carbon steel surfaces not insulated, indoors and outdoors, such as structural steel, pipes, condensers, tanks and vessels exterior surfaces, valves and fittings."
  },
  {
   "n": 18,
   "area": "supports",
   "check": "Are platforms and ladders included?",
   "answer": "Yes: access platforms and ladders for all equipment at height are in scope; galleries, platforms, stairways and handrails galvanized and painted (p. 146).",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 70",
   "quote": "Access platforms and ladders for all equipment at height"
  },
  {
   "n": 19,
   "area": "commercial",
   "check": "How are the vessels priced?",
   "answer": "No separate vessel line. Separators sit inside per-well lump totals H, I, J ('two phase pipeline and valves, separators, silencers, steam & brine lines' for MW-36, MW-37, MW-38); the MW-19B flash tank is item G; FAT and 100% RT are service items (p. 211). Prices fixed (ITT 16.5); quantities remeasured.",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 208",
   "quote": "TOTAL FOR TWO PHASE PIPELINE AND VALVES, SEPARATORS, SILENCERS,"
  },
  {
   "n": 20,
   "area": "commercial",
   "check": "What is the programme length?",
   "answer": "Works programme must fit 12 months to practical completion; a bidder without it is disqualified. (Time for Completion in the contract data is left blank.)",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 201",
   "quote": "The bidders to prepare a works program that fits in a contract of Twelve (12) months of practical completion of works."
  },
  {
   "n": 21,
   "area": "commercial",
   "check": "What delivery and site conditions apply?",
   "answer": "Menengai field near Nakuru, about 180 km west of Nairobi; heavy equipment landed at Mombasa port (about 600 km) or JKIA Nairobi and trucked to site; elevation 2,050 m, ambient pressure 0.8 bar absolute; H2S present around the site up to 5 ppm (p. 113).",
   "evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 82",
   "quote": "the port of Mombasa (some 600km away) and transported to the site by truck."
  }
 ],
 "contradictions": [
  {
   "topic": "Are SS4, SS8 and SS9 existing or new separators?",
   "side_a": "Concept section: all eight make-up wells, including MW-36/37/38 on SS4/SS8/SS9, go to 'existing separators'. Quote: \"It is proposed that the eight make-up wells be connected to the existing separators as shown in the table below.\"",
   "side_a_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 69",
   "side_b": "Section 3.1.7 and the scope list: SS4, SS8 and SS9 are new individual separator vessels (separator stations at MW-36/37/38). Quote: \"will be connected to new individual separator vessels SS4, SS8 and SS9 respectively.\"",
   "side_b_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 71",
   "why_it_matters": "This decides whether three separator vessels are fabricated at all; the rest of the document (scope list, price schedule) treats them as new.",
   "status": "confirmed"
  },
  {
   "topic": "Which separator goes with MW-36 and MW-37",
   "side_a": "Scope 3.1.7 and the electrical schedule: MW-36 with SS4, MW-37 with SS8. Quote: \"TOTAL FOR ELECTRICAL I&C FOR WELL MW-36 AND SS4\"",
   "side_a_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 209",
   "side_b": "Civil works schedule swaps them: MW-37 with SS4, MW-36 with SS8. Quote: \"TOTAL FOR CIVIL WORKS WELL MW-37 AND SS4\"",
   "side_b_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 210",
   "why_it_matters": "SS4 (300 t/hr approx.) and SS8 (150 t/hr approx.) differ in size; foundations and the vessel price land under the wrong well line if the tags are mixed.",
   "status": "confirmed"
  },
  {
   "topic": "Radiography extent on vessels",
   "side_a": "Pressure vessels: 100% radiography of all pressure-retaining welds (6.9.7). Quote: \"For pressure vessels, all pressure retaining welds shall be 100% radiographed.\"",
   "side_a_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 151",
   "side_b": "Section 7.5.4 'Metal Piping & Vessels': random radiography of at least 15% of all welds, escalating on failure. Section 7.4.4.2 (p. 178) also says not less than 10%. Quote: \"Random radiographic testing of at least 15% of all welds.\"",
   "side_b_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 182",
   "why_it_matters": "RT is a major vessel cost line; p. 73 says the most stringent requirement applies, which points to 100%.",
   "status": "confirmed"
  },
  {
   "topic": "Radiation source for shop radiography",
   "side_a": "Shop radiography with X-ray equipment throughout. Quote: \"Radiographic inspection at manufacturer's work shall be accomplished with X-ray equipment throughout.\"",
   "side_a_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 150",
   "side_b": "Shop radiography preferably X-ray; contractor may use X-ray or gamma isotope selectively. Quote: \"Contractor may use X-ray or Gamma ray isotope source selectively.\"",
   "side_b_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 175",
   "why_it_matters": "Whether gamma is allowed in the shop affects which NDE subcontractor and method can be priced for thick vessel seams.",
   "status": "confirmed"
  },
  {
   "topic": "Who pays employer/engineer travel to shop inspections",
   "side_a": "Employer/Engineer bears its own travel and lodging for inspections at the manufacturer's premises (and the FAT clause on p. 108 says the Employer pays air tickets and accommodation for 4 staff). Quote: \"any cost to be incurred for Employer/Engineer's travel, lodging will be borne by Employer/Engineer.\"",
   "side_a_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 169",
   "side_b": "Same page, section 3.0 Expenses: travelling expense and accommodation borne by the Contractor. Quote: \"Traveling expense and accommodation will be borne by the Contractor.\"",
   "side_b_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 169",
   "why_it_matters": "Separator FAT and witness visits abroad with four staff are a real cost; the bid must either carry or exclude it.",
   "status": "confirmed"
  },
  {
   "topic": "Approval and code basis of welding procedures",
   "side_a": "Welding procedures submitted to the Employer/Engineer for approval before welding, in accordance with ASME IX. Quote: \"Prior to the commencement of welding the CONTRACTOR shall submit to the Employer/Engineer for approval the welding procedures\"",
   "side_a_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 149",
   "side_b": "Section 7.4.1.1: welding to an international standard 'will not be subject for approval', and ISO procedures may replace ASME, while the same clause ends 'shall be in accordance with ASME Codes'. Quote: \"Welding shall be executed in accordance to the international defined standard and will not be subject for approval by Employer/Engineer.\"",
   "side_b_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 177",
   "why_it_matters": "A shop with ISO-qualified procedures may or may not need new ASME IX PQRs and an approval cycle before cutting steel.",
   "status": "confirmed"
  },
  {
   "topic": "FAT list: is the flash tank witnessed?",
   "side_a": "Section 10.0: FATs attended by employer staff are pipes, valves, flow meters and separators (no flash tank). Quote: \"1. PIPES 2. VALVES 3. FLOW METERS 4. SEPARATORS\"",
   "side_a_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 108",
   "side_b": "Price schedule (5) item 4: FAT for flash tank, pipes, valves, separators, flow meters. Quote: \"1. FLASHTANK\"",
   "side_b_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 211",
   "why_it_matters": "An extra witnessed FAT for the flash tanks adds shop hold time and hosting cost.",
   "status": "confirmed"
  },
  {
   "topic": "Flash tanks versus silencers at MW-36/37/38 and MW-07/22",
   "side_a": "Scope list: flash tanks and weir boxes at MW-19B, MW-36, MW-37, MW-38, MW-22 and MW-07. Quote: \"Flash tanks and weir boxes at wells MW-19B, MW-36, MW-37, MW-38 and reinjection wells MW-22 and MW-07.\"",
   "side_a_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 70",
   "side_b": "Price schedule (2): a flash tank line only for MW-19B; the other five wells list 'silencers' (and weirbox) instead. Quote: \"TOTAL FOR FLASH TANK FOR WELL MW-19B\"",
   "side_b_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 208",
   "why_it_matters": "Whether five more atmospheric vessels are flash tanks or a different 'silencer' item changes the vessel count and how they are priced.",
   "status": "likely"
  },
  {
   "topic": "Where coatings are applied",
   "side_a": "All surface preparation, prime and finish coating carried out at works. Quote: \"All steps for surface preparation, prime coating, finish coating have to be carried out at work.\"",
   "side_a_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 160",
   "side_b": "The systems themselves put intermediate and finish coats under 'At site' (e.g. 3.5.3 for outdoor carbon steel up to 100 C; also 3.4.3). Quote: \"3.5.3 At site Pre-treatment Thorough cleaning to remove oil, grease, dirt\"",
   "side_b_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 161",
   "why_it_matters": "Shop-applied full systems versus shop primer only changes the fabricator's painting scope and the transport-damage repair allowance.",
   "status": "confirmed"
  },
  {
   "topic": "Inspection and testing scope omits the new separator wells",
   "side_a": "Part on inspection and testing covers wells MW-09B, MW-10B, MW-13B, MW-17A, MW-19B and the SS7 brine line only. Quote: \"This covers the complete Inspection and Testing of the Connection of Wells MW-09B, MW-10B, MW-13B MW-17A , MW-19B and SS7 brine line\"",
   "side_a_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 169",
   "side_b": "Scope of works includes separator stations at MW-36, MW-37 and MW-38. Quote: \"Separator stations at wells MW-36, MW-37 and MW-38 with instruments and controls\"",
   "side_b_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 70",
   "why_it_matters": "The new separators are the main pressure vessels; read literally the I&T part does not cover them, though p. 73 applies the most stringent requirement.",
   "status": "confirmed"
  },
  {
   "topic": "Ultrasonic examination standard",
   "side_a": "UT to ASME V Art. 4 for pressure equipment designed to ASME codes (6.9.3). Quote: \"Ultrasonic examination of welds shall be carried out in accordance with ASME V Art. 4 for pressure equipment designed to ASME codes\"",
   "side_a_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 150",
   "side_b": "UT to AD 2000 Merkblatt HP 5/3 or an equivalent standard (7.2.3). Quote: \"Ultrasonic examination shall be performed in accordance with the AD 2000 MERKBLATT HP5/3 or an equivalent standard.\"",
   "side_b_evidence": "005 - Connection of Additional Wells - Menengai Steam Gathering System.pdf, p. 175",
   "why_it_matters": "Different acceptance standards for the same welds; 'or an equivalent' may reconcile them, so this is a likely rather than certain conflict.",
   "status": "likely"
  }
 ]
}