 "id": "us-opud-pressure-filters",
 "country": "United States",
 "language": "English",
 "buyer": "Olivehurst Public Utility District (California)",
 "project": "Wheeler WTP Capacity Increase, Filter Prepurchase, Project No. 2026-003 (horizontal manganese pressure filters)",
 "year": "2026",
 "files": [
  {
   "file": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf",
   "pages": 216,
   "text_layer": true,
   "what_it_is": "Bid book (project manual, May 22, 2026): front end, Agreement, General Conditions, Division 01 (delivery/LDs, summary, submittals, training), 22 05 48 seismic and slab design, 33 01 10 O&M, 33 08 11 commissioning; Appendix A geotechnical report (2004, scanned, pp. 162-207, no text layer); drawings pp. 208-216 (cover, G1, G2, P100, C101, C102, S101, M101, M102). Section 46 61 21 is listed in the contents but not bound in."
  },
  {
   "file": "Addendum+1+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf",
   "pages": 14,
   "text_layer": true,
   "what_it_is": "Addendum 1 (May 26, 2026): issues Section 46 61 21 Manganese Treatment Filters (pp. 3-14)."
  },
  {
   "file": "Addendum+2+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf",
   "pages": 24,
   "text_layer": true,
   "what_it_is": "Addendum 2 (June 2, 2026): adds Section 01 20 00 Measurement of Payment with supplier payment milestones (pp. 3-12); reissues 46 61 21 (pp. 13-24): design flow 1,250 gpm, warranty two filters, B102 struck in 2.05.D, installation days cut, concrete NSF by Contractor."
  },
  {
   "file": "Addendum+3+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf",
   "pages": 48,
   "text_layer": true,
   "what_it_is": "Addendum 3 (June 22, 2026): one-or-two filter bid (Schedules A and B), new engineer's estimate, bid date July 7, revised 00 11 13, 00 11 16, 00 21 13, 00 41 13, 01 00 00 (April 15, 2027), 01 11 01, training deleted; reissues 46 61 21 (pp. 37-48) with 235 ppb manganese."
  },
  {
   "file": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf",
   "pages": 20,
   "text_layer": true,
   "what_it_is": "Addendum 4 (July 2, 2026): bid date July 10, 2026; reissues 46 61 21 (pp. 9-20), the governing issue, striking supplier field service, startup, performance testing, training and field service summary (separate contract)."
  },
  {
   "file": "RFI+Responses+6-3-26.pdf",
   "pages": 1,
   "text_layer": true,
   "what_it_is": "RFI responses (June 2, 2026): concrete NSF by Contractor, 12 in. nozzles kept, 75 ppb manganese for bidding, warranty two filters, B102 removed. Not an addendum."
  }
 ],
 "quality": "The vessel specification (46 61 21) is missing from the 216-page bid book and arrives by addendum, reissued three times with strikethrough edits that the text layer still extracts (struck 1,560 gpm reads like a live value); drawings, Division 01, the Agreement and the commissioning section were never updated to match, and a 46-page scanned 2004 geotechnical report sits between the specifications and the drawings.",
 "read_by": "Mavlon, read from the documents with AI help before any run, November 2026",
 "items": [
  "Horizontal manganese pressure filter vessel, single cell, nominally 8 ft dia x 26 ft shell, SA-516 Gr 70, ASME Section VIII, 60 psi working pressure: one vessel (Bid Schedule A) or a second (Schedule B), each with stainless inlet distributor/backwash collector and stainless header-lateral wedge-wire underdrain, lined and coated, with manholes, 12 in. end-bell nozzles, saddles and lifting lugs",
  "Filter media for each vessel: silica sand and anthracite over graded support gravel, plus 10% spare of each type, bagged",
  "Engineering: concrete filter pad (slab) design (Schedule A item 2) and seismic/anchorage calculations by a California-licensed specialty engineer; PLC control strategy and five integrator meetings",
  "Freight, storage (up to 3 months within 100 miles) and delivery to the Wheeler WTP, Olivehurst CA"
 ],
 "checks": [
  {
   "n": 1,
   "area": "scope",
   "check": "How many filter vessels is the supplier pricing?",
   "answer": "One filter (Bid Schedule A) or two filters (Bid Schedules A and B). The District will choose after bid opening (Addendum 3). The original bid book asked for two filters.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 9",
   "quote": "The District will be bidding for the purchase of either one filter or two filters."
  },
  {
   "n": 2,
   "area": "scope",
   "check": "Which issue of Section 46 61 21 (Manganese Treatment Filters) governs?",
   "answer": "Section 46 61 21 is listed in the bid book table of contents but is not bound in the bid book. Addendum 1 (May 26, 2026) issues it on pp. 3-14; it is reissued in Addendum 2 (June 2, 2026, pp. 13-24), Addendum 3 (June 22, 2026, pp. 37-48) and Addendum 4 (July 2, 2026, pp. 9-20). The Addendum 4 issue governs; each addendum states that it governs over the earlier documents.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 2",
   "quote": "Reference: 46 61 21 Manganese Treatment Filters (See issued specification dated July 2, 2026)."
  },
  {
   "n": 3,
   "area": "geometry",
   "check": "Vessel type and size",
   "answer": "Horizontal, single-cell pressure filter, nominally 8 ft diameter by 26 ft long shell, to match the existing filters. Head type is not stated.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "quote": "Each filter vessel shall be nominally 8-foot diameter by 26-foot-long shell"
  },
  {
   "n": 4,
   "area": "design",
   "check": "Design / working pressure",
   "answer": "Designed working pressure 60 psi; the design table also gives maximum operating pressure 60 psi (Addendum 4, p. 12). No design temperature, MDMT or external pressure is given.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "quote": "the designed working pressure of 60 psi"
  },
  {
   "n": 5,
   "area": "code",
   "check": "Construction code and shop qualification",
   "answer": "ASME Code Section VIII (no division stated). The vessel must be fabricated in an ASME certified manufacturing facility, with a nameplate welded to the end bell showing manufacturer, serial number, dimension and pressure rating (Addendum 4, p. 11). The supplier must have 10 years in manganese pressure filters and five municipal references from the last 10 years (p. 9).",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "quote": "Each tank shall be constructed per ASME code section VIII."
  },
  {
   "n": 6,
   "area": "code",
   "check": "Code stamp, National Board, inspector, NDE, PWHT, corrosion allowance, design temperature",
   "answer": "Not stated. Beyond ASME Section VIII construction in an ASME certified facility and a welded nameplate with pressure rating, the package says nothing about a U stamp, National Board registration, Authorized Inspector, radiography or joint efficiency, PWHT, impact testing, corrosion allowance, design temperature or MDMT. Verified by searching the text layer of all six files and reading the drawing text layers (pp. 208-216) and viewing M101 and M102 as images; the only image pages without text are the 2004 geotechnical report (bid book pp. 162-207), which was sampled, not read in full.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 11",
   "quote": "pressure rating on a plate welded to the end bell"
  },
  {
   "n": 7,
   "area": "materials",
   "check": "Shell and head material",
   "answer": "Welded steel, SA-516 Grade 70. No separate materials are given for heads, nozzles, flanges or bolting.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "quote": "Each vessel shall be of welded steel construction using SA-516 Grade 70 steel"
  },
  {
   "n": 8,
   "area": "testing",
   "check": "Pressure test",
   "answer": "Hydrostatic test to 30% above the 60 psi designed working pressure (the documents do not write out the resulting number). Factory hydrostatic testing of each vessel 'in accordance with applicable ASME or manufacturer standards' is a condition of the 40% pre-shipment payment (Addendum 2, Section 01 20 00, p. 11).",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "quote": "tested to withstand a hydrostatic pressure 30% in excess of the designed working pressure of 60 psi"
  },
  {
   "n": 9,
   "area": "nozzles",
   "check": "Manholes per vessel (governing)",
   "answer": "Two 14 in. x 18 in. upper elliptical manholes and two 14 in. x 18 in. lower elliptical manholes. Drawing M102 shows the lower manholes as 12 in. x 16 in. (see contradictions); the dated Addendum 4 specification governs under the General Conditions precedence rule. Side manhole orientation differs per filter for media access.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "quote": "Two (2) 14” x 18” lower elliptical manhole"
  },
  {
   "n": 10,
   "area": "nozzles",
   "check": "Process nozzles",
   "answer": "One 12 in. flanged inlet/backwash nozzle and one 12 in. flanged filter-effluent nozzle, both on the end bells. No pressure class or facing is stated. A bidder asked for 14 in. because of velocity; the District kept 12 in. (RFI response 2, RFI Responses p. 1).",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "quote": "One (1) 12” flanged nozzle for inlet/backwash end bell connection"
  },
  {
   "n": 11,
   "area": "nozzles",
   "check": "Small connections and shell attachments",
   "answer": "Two 2 in. thread-o-lets for air release/vacuum valves (valves by the Contractor) and two 2 in. pipe-support Unistrut welded to the shell (2 in. pipe by the Contractor). Drawing M102 also shows a 2 in. threadolet with ball valve for drain that is not in the specification list (see contradictions).",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "quote": "Two (2) 2” Thread-o-lets for 2” (ARBVs provided by Contractor)"
  },
  {
   "n": 12,
   "area": "supports",
   "check": "Supports and lifting",
   "answer": "Two saddle support legs and two lifting lugs per vessel. Shop drawings must show saddles and anchor bolt size and locations (Addendum 4, p. 9); drawing S101 says supports are centred on filter pedestals sized from the filter fabrication drawings.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "quote": "7. Two (2) lifting lugs 8. Two (2) saddle support legs"
  },
  {
   "n": 13,
   "area": "supports",
   "check": "Seismic and anchorage design",
   "answer": "The supplier provides seismic design and anchorage calculations per Section 22 05 48 (ASCE 7-05, California Building Code), prepared, signed and sealed by a California-licensed Specialty Engineer it provides; slab, anchor and component drawings are stamped by that engineer (bid book pp. 151-153; Addendum 4 p. 10).",
   "evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 151",
   "quote": "Specialty Engineer – Structural or Civil Engineer provided by the Manganese Treatment Supplier (MTS) licensed in the State of California"
  },
  {
   "n": 14,
   "area": "scope",
   "check": "Concrete filter pad design and internal concrete",
   "answer": "The supplier designs the reinforced concrete slab for the new filters (22 05 48, 1.04.A.2) and Bid Schedule A carries a separate lump sum 'Concrete Filter Pad Design' (Addendum 3 p. 26). The internal underdrain-support concrete itself, and its NSF 61 sampling and testing, are by the Contractor under a separate contract (Addendum 4 pp. 10-11; Addendum 2).",
   "evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 151",
   "quote": "Provide a structural concrete design of the slab including reinforcement to support the weight of the two new filters"
  },
  {
   "n": 15,
   "area": "fabrication",
   "check": "Internals: inlet distributor and underdrain",
   "answer": "Full-length stainless steel header inlet distributor/backwash collector; stainless steel header-and-lateral underdrain with slotted, wedge-flow, pipe-based laterals. No surface wash system. Filter valves, meters, gauges, air release valves and transmitters are by others.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 15",
   "quote": "The header and laterals shall be stainless steel. The laterals shall be slotted, wedge flow, pipe-based design."
  },
  {
   "n": 16,
   "area": "scope",
   "check": "Media and spare media",
   "answer": "Supplier furnishes silica sand and anthracite over graded support gravel, enough for startup and operation, plus spare media of 10% of each type in double-bagged one-cubic-foot bags on pallets. Media per AWWA B100 (Addendum 2 struck 'or 102' in 2.05.D).",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 15",
   "quote": "media type shall be equal to 10 percent of the total type of media being provided."
  },
  {
   "n": 17,
   "area": "design",
   "check": "Design flow per filter (governing)",
   "answer": "1,250 gpm per filter. Addendum 2 struck the original 1,560 gpm (the struck value still appears in the text layer; strikethrough seen on the rendered page). Other per-filter criteria unchanged: max loading 7.5 gpm/ft2, minimum service cycle 120 h, max backwash 15 gpm/ft2 and 3,120 gpm, max backwash waste 45,000 gal.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 12",
   "quote": "1,560 1,250 (Addendum 2) GPM"
  },
  {
   "n": 18,
   "area": "design",
   "check": "Raw-water manganese basis for bidding (governing)",
   "answer": "235 ppb (Addendum 3). The earlier RFI response (June 2, 2026) said 75 ppb; RFI answers are not addenda (see contradictions).",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 12",
   "quote": "For bidding purposes, the raw water manganese level that requires treatment is 235 ppb."
  },
  {
   "n": 19,
   "area": "design",
   "check": "Performance guarantee",
   "answer": "Effluent manganese <0.01 ppm average and 0.02 ppm maximum; filter clogging rate <0.5 ft/hr at 4 gpm/sf; backwash consumption <1% of throughput. Pressure drop no more than 3 psi clean and 10 psi before backwash (p. 12).",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 15",
   "quote": "Manganese concentrations in filter <0.01 ppm average"
  },
  {
   "n": 20,
   "area": "coating",
   "check": "Interior lining",
   "answer": "Abrasive blast to SSPC-SP10 near-white, paint within 8 hours of blasting, weld spatter ground off (p. 13); 100% solids epoxy, Tnemec Series 22 or equal, minimum 16 mils DFT; NSF/ANSI 61 certified and meeting NSF 600.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 14",
   "quote": "Product to be a 100% solids epoxy, Tnemec Series 22 or equal, applied to a minimum DFT of 16 mils."
  },
  {
   "n": 21,
   "area": "coating",
   "check": "Exterior coating",
   "answer": "Abrasive blast to SSPC-SP6 commercial; one coat high-solids epoxy primer, Tnemec Series 69 or equal, 2-4 mils DFT; polyurethane topcoat Tnemec Series 1075 or equal, colour selected by the District. Field touch-up after delivery is by the Contractor.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 14",
   "quote": "Prime coat to be a high solids epoxy, Tnemec Series 69 or equal."
  },
  {
   "n": 22,
   "area": "coating",
   "check": "Coating inspection",
   "answer": "Before delivery the supplier provides a third-party NACE III certified inspector to test interior and exterior coating per ASTM D5162-15; results to Engineering within 14 days of inspection and before delivery.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 14",
   "quote": "third-party NACE III certified inspector to test the interior and exterior coating of the filters per ASTM D5162-15"
  },
  {
   "n": 23,
   "area": "documents",
   "check": "NSF/ANSI 61 certification",
   "answer": "Certification of ANSI/NSF 61 compliance for all equipment in contact with water. NSF/ANSI 61 documentation for all wetted components is also a condition of the 40% pre-shipment payment (Addendum 2 p. 11).",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 10",
   "quote": "Provide certification compliance with ANSI/NSF 61 requirements for all equipment that comes in contact with the water."
  },
  {
   "n": 24,
   "area": "documents",
   "check": "Shop drawings and engineer stamp",
   "answer": "Shop drawings: plan and elevation with penetrations, internal piping, saddles and anchor bolts, media type and arrangement, material list (Addendum 4 pp. 9-10). Submittal plans stamped and signed by a California-registered engineer with seismic and anchoring calculations; approval triggers the 20% first payment. Two hard copies plus PDF; no fabrication before status NET or MCN; Engineer review 2 weeks (bid book pp. 141-144).",
   "evidence": "Addendum+2+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 11",
   "quote": "Submittals shall include plans stamped and signed by a registered engineer licensed in the State of California"
  },
  {
   "n": 25,
   "area": "documents",
   "check": "PLC / controls coordination still in supplier scope",
   "answer": "Supplier gives the PLC integrator a control strategy, attends five separate 8-hour meetings with the integrator to develop, review and factory test the program, and certifies the PLC program before operational testing. Controls, panel, external piping and valves are by others.",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 11",
   "quote": "The supplier shall provide five separate 8-hour meetings with the PLC integrator"
  },
  {
   "n": 26,
   "area": "scope",
   "check": "Field service, startup, performance testing and training (governing)",
   "answer": "Addendum 4 deletes 46 61 21 paragraphs 3.01.C (field service), 3.02 (startup), 3.03 (performance testing), 3.04 (training) and 3.05 (field service summary); assembly, installation, testing and startup are coordinated under a separate contract (1.06.A). Addendum 3 had already deleted training and the 'Manganese Treatment Support and Training' bid item; Addendum 2 had cut installation days from five to two. Several clauses still require supplier presence (see contradictions).",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 2",
   "quote": "Delete Paragraph 3.01.C Under Separate Contract"
  },
  {
   "n": 27,
   "area": "commercial",
   "check": "Delivery date and storage (governing)",
   "answer": "Filter fabricated and ready for delivery by April 15, 2027, based on Notice to Proceed and release of tank materials on July 30, 2026 (Addendum 3; was January 15, 2027 and July 17, 2026). Ship within two weeks after the Engineer's request (01 11 01). If the Contractor is not ready, the supplier stores the filter, internals and media up to 3 months after the completion date within 100 miles of Olivehurst, then delivers to the District's Wheeler WTP (Addendum 4 p. 16).",
   "evidence": "Addendum+3+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 3",
   "quote": "Change Paragraph 1.01 Date of Completion April 15, 2027 and Notice to Proceed July 30, 2026"
  },
  {
   "n": 28,
   "area": "commercial",
   "check": "Liquidated damages",
   "answer": "Section 01 00 00 (reissued in Addendum 3 with the rate unchanged): $500 per calendar day after the completion date, plus a further $500 per day for every day beyond 10 calendar days that the filter is not on site when the District asks. The Agreement form 00 52 00 separately states $2,500 per day for Final Completion (see contradictions).",
   "evidence": "Addendum+3+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 31",
   "quote": "liquated damages in the amount of five hundred ($500.00) per day for each calendar day after the date of Completion"
  },
  {
   "n": 29,
   "area": "commercial",
   "check": "Warranty",
   "answer": "Written two-year warranty of satisfactory performance of the new filters after system testing and acceptance (Addendum 2 changed 'three' to 'two'); advice within 24 hours of a call, and on-site correction at no cost if a deficiency lasts more than three days; plus a performance guarantee. The Agreement adds a maintenance and warranty bond of 10% of the final contract amount for one year (bid book p. 46).",
   "evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 16",
   "quote": "performance of the three two (Addendum 2) new filters for two years"
  },
  {
   "n": 30,
   "area": "commercial",
   "check": "Payment milestones",
   "answer": "20% on approved submittals; 40% before shipment after factory testing (hydrotest) and NSF 61 documentation; 20% on delivery (supplier pays transport and freight; off-loading by the separate Contractor); 20% on final acceptance (Addendum 2, Section 01 20 00, 1.08).",
   "evidence": "Addendum+2+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 11",
   "quote": "40% – Prior to Shipment After Factory Testing"
  },
  {
   "n": 31,
   "area": "commercial",
   "check": "Bid items, sales tax and bonds",
   "answer": "Schedule A: one filter with internals, media and support gravel; concrete filter pad design; 8.25% local sales tax on item 1; performance and payment bonds; freight, storage and delivery of item 1. Schedule B (second filter) has the same items without pad design. Bid security 10% of the Schedule B total (Addendum 3 p. 27); payment and performance bonds 100% of contract price (bid book p. 53).",
   "evidence": "Addendum+3+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 26",
   "quote": "Local Sales Tax @ 8.25% on Item 1"
  },
  {
   "n": 32,
   "area": "commercial",
   "check": "Engineer's opinion of probable cost (governing)",
   "answer": "$375,000 for one filter (Schedule A); $750,000 for two filters (Schedules A and B) (Addendum 3). The bid book gave $750,000 for two.",
   "evidence": "Addendum+3+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 9",
   "quote": "$375,000 for one filter (Bid Schedule A) (Addendum 3)"
  }
 ],
 "contradictions": [
  {
   "topic": "Lower manhole size",
   "side_a": "Specification 46 61 21, 2.03.F.2 (Addendum 4): \"Two (2) 14” x 18” lower elliptical manhole\"",
   "side_a_evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "side_b": "Drawing M102 labels the lower manholes: \"12\"x16\" LOWER ELLIPTICAL\"",
   "side_b_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 216",
   "why_it_matters": "Manhole size sets the forging/neck, cut-out and reinforcement; the General Conditions resolve drawing-vs-spec conflicts in favour of the latest-dated document, which is the Addendum 4 spec (14 x 18).",
   "status": "confirmed"
  },
  {
   "topic": "Drain connection",
   "side_a": "Specification 2.03.F lists only these small connections: \"Two (2) 2” Thread-o-lets for 2” (ARBVs provided by Contractor)\"",
   "side_a_evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "side_b": "Drawing M102 adds a drain connection not in the specification list: \"2\" THREADOLET W/BALL VALVE\"",
   "side_b_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 216",
   "why_it_matters": "An extra coupling and a ball valve are a small but real addition the specification does not ask for.",
   "status": "confirmed"
  },
  {
   "topic": "Nozzle orientation drawing",
   "side_a": "Specification 2.03.E refers to a drawing that does not exist: \"The orientation of the filter inlet and outlet nozzles are shown on Drawing M106.\"",
   "side_a_evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "side_b": "The drawing list ends at M102 (sheet 8 of 8): \"M102 8 Manganese Filter Details\"",
   "side_b_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 7",
   "why_it_matters": "Nozzle orientation and location are undefined; M102 note 2 says to use dimensions from the existing filter fabrication drawings, which are not in the package.",
   "status": "confirmed"
  },
  {
   "topic": "Number of existing filters",
   "side_a": "Specification 2.03.D: \"to match the existing two filters\"",
   "side_a_evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "side_b": "The same page, 2.03.A: \"piped in parallel to the existing three filter vessels\"",
   "side_b_evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "why_it_matters": "The new vessels must match existing filters whose drawings are not provided; the count of existing units (and so which design to copy) is inconsistent.",
   "status": "confirmed"
  },
  {
   "topic": "Quantity of new filters on drawings",
   "side_a": "Specification 2.03.A: \"There are to be two new filter vessels\"",
   "side_a_evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "side_b": "Process flow diagram P100 shows one new filter (and M101 marks Filter 5 as future, 'FILTER 5 (F)'): \"(1,250 gpm) 1 - 8' Ø BY 26' L FILTERS (N)\"",
   "side_b_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 211",
   "why_it_matters": "Quantity drives the price; Addendum 3 resolves it with Bid Schedule A (one filter) and Schedule B (second filter), so both must be priced.",
   "status": "confirmed"
  },
  {
   "topic": "Quantity in Summary of Work",
   "side_a": "Specification 2.03.A (Addendum 4): \"There are to be two new filter vessels\"",
   "side_a_evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 13",
   "side_b": "Summary of Work 01 11 01 as reissued in Addendum 3, 1.01.A (not struck): \"The District plans to pre-purchase three horizonal pressure filters\"",
   "side_b_evidence": "Addendum+3+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 33",
   "why_it_matters": "A third filter would be a large scope change; Addendum 3 bid schedules (one or two) govern.",
   "status": "confirmed"
  },
  {
   "topic": "Raw-water manganese for bidding",
   "side_a": "RFI response 3 (June 2, 2026): \"For bidding purposes, use a manganese level of 75 ppb.\"",
   "side_a_evidence": "RFI+Responses+6-3-26.pdf, p. 1",
   "side_b": "Addendum 3, carried into Addendum 4 spec 2.02.A.1: \"For bidding purposes, the raw water manganese level that requires treatment is 235 ppb.\"",
   "side_b_evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 12",
   "why_it_matters": "Influent manganese sets media depth and the performance guarantee risk; the Instructions to Bidders say only addenda are binding, so 235 ppb governs.",
   "status": "confirmed"
  },
  {
   "topic": "AWWA B102 media testing",
   "side_a": "RFI response 5 says the B102 reference was removed from 3.01.F.2: \"Removed AWWA B102 reference.\"",
   "side_a_evidence": "RFI+Responses+6-3-26.pdf, p. 1",
   "side_b": "Addendum 4 spec 3.01.F.2 still requires the supplier to test media to B102: \"verify the conformance with AWWA B100 and B102.\"",
   "side_b_evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 17",
   "why_it_matters": "Media sampling and testing to a second (greensand) standard adds lab cost; only 2.05.D had 'or 102' struck.",
   "status": "confirmed"
  },
  {
   "topic": "Supplier startup attendance after Addendum 4",
   "side_a": "Addendum 4 deletes field service and startup paragraphs: \"Delete Paragraph 3.01.C Under Separate Contract\"",
   "side_a_evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 2",
   "side_b": "Paragraph 2.07.A.4 of the same Addendum 4 spec is not struck: \"The MTS shall be available during startup and testing for a period of not less than 15 days\"",
   "side_b_evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 16",
   "why_it_matters": "Fifteen or more days of site attendance is a major service cost that may or may not be in scope.",
   "status": "confirmed"
  },
  {
   "topic": "Commissioning section never amended",
   "side_a": "Addendum 4 deletes startup from 46 61 21: \"Delete Paragraph 3.02 Under Separate Contract\"",
   "side_a_evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 2",
   "side_b": "Section 33 08 11 Commissioning (MTS), not changed by any addendum: \"The commissioning period system shall be continuous period of 28 days.\"",
   "side_b_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 159",
   "why_it_matters": "A 28-day continuous availability period, with supplier-paid repairs, is a large cost if it still applies.",
   "status": "confirmed"
  },
  {
   "topic": "Training",
   "side_a": "Addendum 3 deletes training from 46 61 21: \"Delete Paragraph 3.04 No training required for this project\"",
   "side_a_evidence": "Addendum+3+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 3",
   "side_b": "Addendum 2 Section 01 20 00 makes supplier training (and performance testing) a condition of the final 20% payment: \"operator training provided by the Supplier to District personnel\"",
   "side_b_evidence": "Addendum+2+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 11",
   "why_it_matters": "The final 20% payment depends on training and performance testing that later addenda removed or moved to a separate contract; 01 11 01 (Addendum 3, p. 34) also still lists training.",
   "status": "confirmed"
  },
  {
   "topic": "Delivery date",
   "side_a": "Agreement 00 52 00, 1.04.A (bid book, not reissued): \"The MTS shall be able to deliver the filter and associated components to the project site by January 1, 2027.\"",
   "side_a_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 44",
   "side_b": "Addendum 3 changes Section 01 00 00: \"Date of Completion April 15, 2027\"",
   "side_b_evidence": "Addendum+3+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 3",
   "why_it_matters": "The date sets shop loading and the liquidated damages trigger; the addendum is the latest modification and should govern.",
   "status": "confirmed"
  },
  {
   "topic": "Liquidated damages rate",
   "side_a": "Agreement 00 52 00, 3.1.1: \"Two thousand, five hundred dollars ($ 2,500) for each Day\"",
   "side_a_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 46",
   "side_b": "Section 01 00 00, 1.02.A (reissued in Addendum 3): \"liquated damages in the amount of five hundred ($500.00) per day\"",
   "side_b_evidence": "Addendum+3+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 31",
   "why_it_matters": "A fivefold difference in daily exposure; the General Conditions rank contract forms (00 52 00) above Division 01, while 01 00 00 was reissued by addendum.",
   "status": "confirmed"
  },
  {
   "topic": "Delivery call-off time",
   "side_a": "Summary of Work 01 11 01, 3.02.C (Addendum 3): \"ship the filters within two weeks after Engineer requests the filters to be delivered to the Project Location.\"",
   "side_a_evidence": "Addendum+3+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 34",
   "side_b": "Section 01 00 00, 1.02.B: extra liquidated damages start after 10 days: \"for every day after 10 calendar days that the filter does not show up at the project site when asked by the District.\"",
   "side_b_evidence": "Addendum+3+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 31",
   "why_it_matters": "Days 11 to 14 after a call-off would carry liquidated damages even though the Summary of Work allows two weeks.",
   "status": "confirmed"
  },
  {
   "topic": "Filter numbering for manhole orientation",
   "side_a": "Drawing M102 note 1: \"HATCH LOCATIONS ARE SHOWN ON THE SOUTH SIDE FOR FILTER 6.\"",
   "side_a_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 216",
   "side_b": "Drawing M101 numbers the new filters 4 (new) and 5 (future): \"FILTER 5 (F)\"",
   "side_b_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 215",
   "why_it_matters": "There is no Filter 6; which vessel gets north-side and which south-side manholes (mirror-image vessels) is unclear.",
   "status": "confirmed"
  },
  {
   "topic": "O&M manual copies",
   "side_a": "Section 33 01 10, 1.04.A: \"Provide one hardcopy operation and maintenance manual\"",
   "side_a_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 155",
   "side_b": "Section 33 01 10, 1.06.D: \"Submit four sets of revised final volumes in final form\"",
   "side_b_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 157",
   "why_it_matters": "Small document cost difference (one vs four printed sets).",
   "status": "confirmed"
  },
  {
   "topic": "Geotechnical report reference",
   "side_a": "Section 22 05 48, 1.04.A.4 (seismic input): \"using the information provided in Appendix B - Geotechnical Report\"",
   "side_a_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 151",
   "side_b": "Section 46 61 21, 1.02 and the bid book contents call it Appendix A: \"Appendix A – Geotechnical Report for the Wheeler WTP\"",
   "side_b_evidence": "Addendum+4+Wheeler+WTP+Capacity+Expansion+Filter+Prepurchase.pdf, p. 9",
   "why_it_matters": "The seismic engineer must use Appendix A (a 2004 report); minor, but it is the input to the anchorage design.",
   "status": "confirmed"
  },
  {
   "topic": "Who submits the sealed seismic calculations",
   "side_a": "Section 22 05 48, 1.04.A: \"The Manganese Treatment Supplier (MTS) is responsible for the following:\"",
   "side_a_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 151",
   "side_b": "Section 22 05 48, 1.07.A: \"The Contractor is responsible for submitting signed and sealed structural calculations\"",
   "side_b_evidence": "Olivehurst+Wheeler+Ranch+WTP+Filter+Pre-Purchase+Project.pdf, p. 153",
   "why_it_matters": "'Contractor' can mean the bidder (Agreement) or the separate installer (46 61 21); if the supplier carries it, the specialty engineer's fee is in the bid.",