 "id": "canada-ottawa-pwgsc",
 "country": "Canada",
 "language": "English",
 "convention": "ANSI (legend cites ANSI Y32.2-1975)",
 "text_layer": false,
 "quality": "clean CAD export; no text layer (0 fonts, pdftotext returns nothing), corrected on 16 Nov 2026, after the run showed it",
 "buyer": "Public Works and Government Services Canada",
 "project": "KC01 Complex switchgear upgrade, 1 Haanel Drive, Ottawa (solicitation EP067-162617, 2016)",
 "drawing": "English/Drawings/01-Electrical/E201 - NEW SWITCHGEAR CONFIG.pdf, page 1 (E201, New switchgear configuration)",
 "read_by": "Mavlon, read from the drawing with AI help before any run, November 2026",
 "checks": [
  [
   "Cell count",
   "11 (cells 1 to 11)"
  ],
  [
   "Switchgear voltage",
   "13.8 kV"
  ],
  [
   "Breakers marked MAIN",
   "4: cells 1, 3, 8, 10, 1200 A"
  ],
  [
   "Tie breaker",
   "cell 5, 1200 A"
  ],
  [
   "Feeder breakers",
   "3: cells 3, 6, 8, 1200 A"
  ],
  [
   "Future feeders",
   "2: cells 4 and 7 (F-12, drawn dashed)"
  ],
  [
   "Potential transformers (2) L-L",
   "cells 1, 4, 7, 10"
  ],
  [
   "Provision for PTs",
   "cells 2 and 9 (PROV. (2) L-L)"
  ],
  [
   "Utility CTs (Hydro)",
   "cells 2 and 9"
  ],
  [
   "Control power transformers",
   "15 kVA in cells 5 and 6"
  ],
  [
   "Surge arresters",
   "12 kV, on the incoming cables at cells 1 and 10"
  ],
  [
   "Cell 11",
   "protective relay central cabinet for the 44 kV outside substation"
  ],
  [
   "Sources",
   "two transformers: T1 feeds cell 1 by cable 10, T2 feeds cell 10 by cable 11"
  ],
  [
   "T1/T2 rating",
   "5000/5600 kVA, 44 kV to 13.8 kV, type ONS"
  ],
  [
   "T1/T2 impedance",
   "T1 5.3/6.0% and T2 5.3/5.9% at 75 °C"
  ],
  [
   "Upstream supply",
   "two 44 kV Hydro overhead lines (QT 205-M1 and QT 205-M25) into an overhead 44 kV substation"
  ],
  [
   "Station service transformer",
   "225 kVA, 13,800-120/208 V, type LNAN, 3.27% at 85 °C"
  ],
  [
   "Meters",
   "main-tie-main breakers CM4250; branch breakers PM850 (notes 1 and 2)"
  ],
  [
   "Feeder protection",
   "50/51, 50/51N, 50G/51G (note 8)"
  ],
  [
   "Cell 11 relays",
   "87-B differential, 27-1 and 27-2 undervoltage, 47-T1 and 47-T2 phase sequence"
  ],
  [
   "Battery",
   "existing 125 V DC battery bank retained (note 3, N-2)"
  ],
  [
   "Shutdown",
   "new switchgear installed in one weekend shutdown (N-3)"
  ],
  [
   "Downstream loop",
   "13.8 kV loop (15353) leaving the switchgear on cables 1 and 9, with cables 2 to 8 between 8 load points"
  ],
  [
   "Downstream connected loads",
   "1500, 1500, 1500, 1500, 1500, 750, 750 and 125 kVA"
  ],
  [
   "Peak demand loads",
   "273.07, 379.26, 227.56, 303.41, 121.36, 60.68, 136.53 and 15.17 kW (June)"
  ],
  [
   "Load point switching",
   "load-break switches with fuses or switch-fuse units at each load point (I.S.-L to I.S.-L13, F1-L4/L5, F1-L14, F2-L)"
  ],
  [
   "New cables",
   "15 kV multi 3-conductor 350 kcmil (N-6); 46 kV 1/C 250 MCM power cable (N-4)"
  ]
 ]
}