 "id": "us-annarbor-uv",
 "country": "United States",
 "language": "English",
 "buyer": "City of Ann Arbor, Michigan (Wastewater Treatment Services Unit); engineer Black & Veatch",
 "project": "RFP No. 23-13 Wastewater Treatment Plant UV Disinfection Equipment (UV system supplier preselection)",
 "year": "2023",
 "files": [
  {
   "file": "rfp_23-13_document.pdf",
   "pages": 215,
   "text_layer": true,
   "what_it_is": "RFP (pp. 1-15), B&V preselection specifications incl. bid form 00 41 63 and UV section 46 66 56.12 (pp. 17-130), City forms and terms (pp. 131-151); pp. 152-215 are image-only: Appendix A 1999 record drawings and Appendix B existing O&M manual"
  },
  {
   "file": "rfp_23-13_addendum1.pdf",
   "pages": 6,
   "text_layer": true,
   "what_it_is": "Addendum No. 1: due date moved to March 13, 2023, price hold cut to six months, bonds sentence removed, module-to-bank and sleeve 0.92-to-0.88 changes, 9 general and 15 technical Q&As"
  },
  {
   "file": "rfp_23-13_addendum2.pdf",
   "pages": 11,
   "text_layer": true,
   "what_it_is": "Addendum No. 2: adds PPI equipment price adjustment and Alternate D (redundant bank per channel); reissues bid form 00 41 63 in its entirety (pp. 4-11)"
  }
 ],
 "quality": "Key design values sit in a table whose superscript footnotes merge into the numbers in the text layer (dose reads 301, factors 802); two addenda change and then partly undo each other (module vs bank, bonds sentence); a third of the main PDF is image-only; the gate schedule the gate sections rely on is not in the package.",
 "read_by": "Mavlon, read from the documents with AI help before any run, November 2026",
 "items": [
  "Open-channel low-pressure high-output UV disinfection system for 54 mgd peak, at least 2 channels, in the existing UV canopy footprint",
  "UV banks/modules, quartz sleeves, automatic cleaning, ballast (driver) cabinets, PLC master control panel, instruments, fixed weirs, spare parts",
  "Influent and effluent open-channel slide gates with electric actuators",
  "Early Work: shop drawing submittal (lump sum up to $70,000); Balance of Work: equipment, delivery, installation assistance, startup, training, testing, warranty (price held 6 months for the GC contract)",
  "Add alternates A to D: 36-month warranty, 36-month warranty bond, NEMA 4X enclosures, redundant bank per channel"
 ],
 "checks": [
  {
   "n": 1,
   "area": "scope",
   "check": "Purchase route: how is the UV equipment bought?",
   "answer": "Preselection. The City preselects one UV system supplier (UVSS) and signs an Early Work agreement (shop drawings) that fixes the equipment price; the Balance of Work price is then sole-sourced into the general construction contract, and the purchase order is placed by the General Contractor.",
   "evidence": "rfp_23-13_document.pdf, p. 12",
   "quote": "Purchase order of the UVSS equipment shall be between the General Contractor and the UVSS after the construction contract has been awarded."
  },
  {
   "n": 2,
   "area": "scope",
   "check": "What must the UVSS supply?",
   "answer": "A complete open-channel UV system (lamp modules and banks with quartz sleeves, automatic cleaning, ballast/driver cabinets, PLC master control panel, instruments, fixed weirs, spares, special tools) plus slide gates with electric actuators, installation assistance and performance testing.",
   "evidence": "rfp_23-13_document.pdf, p. 103",
   "quote": "The UVSS shall provide all parts (sensors, probes, controls), equipment, slide gates and electric actuators, materials, components, installation assistance and performance testing"
  },
  {
   "n": 3,
   "area": "scope",
   "check": "Named UV manufacturers and or-equal rule",
   "answer": "Trojan Technologies, Xylem Wedeco or Suez Treatment Solutions, without exception (closed list, no or-equal).",
   "evidence": "rfp_23-13_document.pdf, p. 112",
   "quote": "Trojan Technologies of London, Ontario, Xylem Wedeco of Herford, Germany, or Suez Treatment Solutions Inc. of Leonia, New Jersey, without exception."
  },
  {
   "n": 4,
   "area": "scope",
   "check": "Slide gates: where, which makers, what sizes?",
   "answer": "Gates on the upstream and downstream side of the UV equipment in each channel; acceptable makers Hydro Gate, RW Gate, Rodney Hunt and Whipps (p. 98). Sizes, heads, quantities and actuator power are deferred to a Slide Gate Schedule and valve and gate schedules that are not in the package (full text searched).",
   "evidence": "rfp_23-13_document.pdf, p. 98",
   "quote": "Slide gates will be required on the upstream and downstream side of the UV equipment of each channel to provide isolation of the equipment."
  },
  {
   "n": 5,
   "area": "scope",
   "check": "Gate actuators",
   "answer": "Intelligent electric actuators; any not listed in the (missing) gate schedules must be Rotork IQ Series multi-turn, without exception; other makes not acceptable. Actuators mounted before shipment are priced in Balance of Work (p. 96).",
   "evidence": "rfp_23-13_document.pdf, p. 92",
   "quote": "All other intelligent electric actuators for open-close service shall be multi-turn type and shall be Rotork \"IQ Series\", without exception."
  },
  {
   "n": 6,
   "area": "design",
   "check": "Design flows, channels and UV transmittance",
   "answer": "Peak 54 mgd with all channels in service, average daily 25 mgd, minimum daily 10 mgd; minimum 2 channels; design UV transmittance 60 percent.",
   "evidence": "rfp_23-13_document.pdf, p. 111",
   "quote": "Peak flow (with all channels in service) 54 mgd"
  },
  {
   "n": 7,
   "area": "design",
   "check": "Design UV dose",
   "answer": "30 mJ/cm2 minimum validated (MS2) dose at design conditions, at end of lamp life with fouled sleeves, at peak flow and 60 percent UVT. The text layer reads 301 because footnote 1 merges into the value.",
   "evidence": "rfp_23-13_document.pdf, p. 111",
   "quote": "Min. UV validated dosage, at design conditions ... based on MS2 phage | 30 [superscript 1] | mJ/cm2 (quote read from image)"
  },
  {
   "n": 8,
   "area": "design",
   "check": "End-of-lamp-life and fouling factors",
   "answer": "Lamp output at end of lamp life 80 percent and fouling factor 80 percent (the text layer reads 802 because footnote 2 merges into each value).",
   "evidence": "rfp_23-13_document.pdf, p. 111",
   "quote": "Lamp Output at End of lamp life, | 80 [superscript 2] | % ... Fouling factor | 80 [superscript 2] | % (quote read from image)"
  },
  {
   "n": 9,
   "area": "design",
   "check": "Maximum headloss",
   "answer": "8 inches, measured from the furthest upstream UV module to the top of the weir.",
   "evidence": "rfp_23-13_document.pdf, p. 112",
   "quote": "Maximum allowable headloss from furthest 8 Inches upstream UV module to top of the weir"
  },
  {
   "n": 10,
   "area": "design",
   "check": "How must the validated dose be proven?",
   "answer": "By bioassay to NWRI 2012 or USEPA UVDGM 2006 procedures; a certification letter showing State of California approval must be submitted, and any added validation is at UVSS cost.",
   "evidence": "rfp_23-13_document.pdf, p. 109",
   "quote": "verified by a bioassay conducted according to either NWRI Ultraviolet Disinfection Guidelines for Drinking Water and Reuse Water (2012) or Ultraviolet Disinfection Guidance Manual (2006)"
  },
  {
   "n": 11,
   "area": "design",
   "check": "Is installed redundancy required in the base bid?",
   "answer": "No. Addendum 1 confirms no installed redundancy, and changes 2.2.D.1 from 'redundant module' to 'redundant bank' (governing text: no redundant bank or channel required).",
   "evidence": "rfp_23-13_addendum1.pdf, p. 5",
   "quote": "Per Section 46 66 56, Paragraph 2.2.D.1, the specified system does not require installed redundancy."
  },
  {
   "n": 12,
   "area": "commercial",
   "check": "Alternate D (added by Addendum 2)",
   "answer": "Add price to provide a redundant UV bank in each channel with all ancillary equipment and cables; added to the reissued bid form.",
   "evidence": "rfp_23-13_addendum2.pdf, p. 2",
   "quote": "Provide redundant UV bank in each channel, including all ancillary equipment, cables, etc."
  },
  {
   "n": 13,
   "area": "design",
   "check": "Basis of the 'dose with equipment out of service' calculation (spec 1.3.C.1.i.1, bid form A.9)",
   "answer": "Ambiguous. Addendum 1 changes A.9 from module to bank and Answer 7 says a duty bank per channel out of service, but Answer 8 on the same page says a duty module, and the Addendum 2 reissued bid form A.9 again says one UV module in each channel. Dose with all equipment operating must also be given.",
   "evidence": "rfp_23-13_addendum1.pdf, p. 5",
   "quote": "shall be based on a duty UV bank per channel out of service"
  },
  {
   "n": 14,
   "area": "commercial",
   "check": "How are proposals evaluated?",
   "answer": "History of installations 10 points, proposed system design 15 points, fee 75 points. Fee points come from the Engineer's 20-year life-cycle cost built from the bid form and Attachment A inputs (power at 54 and 25 mgd, replacement part prices and lives, cleaning chemicals, headloss); lowest life-cycle cost gets full points, others lose points by percentage difference.",
   "evidence": "rfp_23-13_document.pdf, p. 13",
   "quote": "The City’s Engineer will develop a 20-year life-cycle cost analysis to determine the lowest cost of the ownership"
  },
  {
   "n": 15,
   "area": "commercial",
   "check": "Bid form price items (governing: Addendum 2 reissued form)",
   "answer": "Early Work lump sum (capped at $70,000; Addendum 1 Answer 2 refuses a 15 percent cap), Balance of Work lump sum, and add alternates A (warranty to 36 months), B (warranty bond to 36 months), C (NEMA 12 to NEMA 4X) and D (redundant bank per channel). Attachment A also asks for a base-bid breakdown of spare parts, manufacturer's services, training and testing.",
   "evidence": "rfp_23-13_addendum2.pdf, p. 7",
   "quote": "Base Bid, Early (up to $70,000)"
  },
  {
   "n": 16,
   "area": "commercial",
   "check": "How long must the price be held? (changed by Addendum 1)",
   "answer": "Six months from the fully executed preselection agreement; Addendum 1 replaced 'one year' with 'six (6) months'.",
   "evidence": "rfp_23-13_addendum1.pdf, p. 3",
   "quote": "the UVSS shall hold the Balance of Work price for 6 months"
  },
  {
   "n": 17,
   "area": "commercial",
   "check": "Price escalation (added by Addendum 2)",
   "answer": "If the GC notice to proceed comes after the 6 months, one adjustment (up or down) of the Balance of Work using the BLS PPI 'Metals and Metal Products' (Group Code 10) from proposal month to notice-to-proceed month, plus 'Other Costs' of 2 percent of the adjustment for taxes and mark-ups on bonds, insurance and general conditions.",
   "evidence": "rfp_23-13_addendum2.pdf, p. 1",
   "quote": "Baseline materials costs will be indexed upon “Metals and Metal Products” (Group Code 10, Item Code NA)"
  },
  {
   "n": 18,
   "area": "commercial",
   "check": "Bonds, liquidated damages and insurance from the GC contract",
   "answer": "The UVSS must include in its Balance of Work the costs of what the GC's terms will require (payment bonds, liquidated damages, insurance; confirmed by Addendum 1 Answers 4 and 7). No LD rate or bond amount is stated anywhere in the package (full text searched).",
   "evidence": "rfp_23-13_document.pdf, p. 12",
   "quote": "These may include but not limited to Payment Bonds, Liquidated Damages, and Insurance."
  },
  {
   "n": 19,
   "area": "commercial",
   "check": "Delivery terms",
   "answer": "FOB job site; the bidder states the number of weeks after the general contractor receives notice to proceed (reissued bid form A.8).",
   "evidence": "rfp_23-13_addendum2.pdf, p. 11",
   "quote": "the equipment shall be delivered Freight on Board (FOB) job site"
  },
  {
   "n": 20,
   "area": "commercial",
   "check": "Buy America / American Iron and Steel",
   "answer": "Not stated. No Buy America, American Iron and Steel or Build America clause appears in the RFP, specifications or either addendum (full text layer searched; pp. 152-215 are image-only 1999 record drawings and O&M manual).",
   "evidence": "rfp_23-13_document.pdf, pp. 1-151 text layer; rfp_23-13_addendum1.pdf, pp. 1-6; rfp_23-13_addendum2.pdf, pp. 1-11 (full text searched)",
   "quote": "not found: searched 'Buy America', 'American Iron', 'Build America', 'BABA', 'domestic'"
  },
  {
   "n": 21,
   "area": "services",
   "check": "Equipment warranty",
   "answer": "One year from Substantial Completion of the construction contract regardless of when the equipment is made or delivered, including shipping damage. Alternate A extends the 12-month warranty to 36 months; Alternate B extends a 12-month warranty bond to 36 months.",
   "evidence": "rfp_23-13_document.pdf, p. 110",
   "quote": "for a period of 1 year from the date of Substantial Completion for the construction contract regardless of the date the equipment is manufactured"
  },
  {
   "n": 22,
   "area": "services",
   "check": "Lamp, driver and sensor warranties",
   "answer": "Lamps 15,000 operating hours, prorated after 9,000 hours, on/off cycles limited to an average of four per day; lamp drivers 5 years, replaced within 30 days, prorated after 2 years; intensity sensors 5 years prorated after 1 year; warranty includes parts and freight.",
   "evidence": "rfp_23-13_document.pdf, p. 110",
   "quote": "Lamps shall be warranted for a guaranteed lamp life of 15,000 hours based on actual operating hours"
  },
  {
   "n": 23,
   "area": "services",
   "check": "Quartz sleeve warranty (changed by Addendum 1)",
   "answer": "10 years from Substantial Completion; if 20 percent of sleeves fail to keep a transparency factor of 0.88 (Addendum 1; was 0.92), all sleeves are replaced within 30 days at no cost, shipping at UVSS expense.",
   "evidence": "rfp_23-13_addendum1.pdf, p. 4",
   "quote": "1.7.D will be revised from “0.92” to “0.88”"
  },
  {
   "n": 24,
   "area": "services",
   "check": "Spare parts",
   "answer": "Spares for one UV module or 10 percent of the installed system, whichever is greater, including lamps, wipers, sleeves and ballasts; any used during installation are replaced free.",
   "evidence": "rfp_23-13_document.pdf, p. 109",
   "quote": "UVSS shall provide spare parts for one UV module or 10% of the overall installed system, whichever is greater."
  },
  {
   "n": 25,
   "area": "services",
   "check": "Installation supervision and field visits",
   "answer": "UV system: minimum 5 days and 2 trips for installation supervision, plus revisits until the installation is satisfactory; return visits caused by an unready contractor are at the Installation Contractor's expense. Gates: minimum 2 days and 1 trip (p. 102).",
   "evidence": "rfp_23-13_document.pdf, p. 126",
   "quote": "shall include a minimum of 5 days and 2 trips to the site for Installation Supervision."
  },
  {
   "n": 26,
   "area": "services",
   "check": "Training",
   "answer": "At least 2 training visits of 3 days each at the plant; classes: UV system 2 shifts x 16 people (2 h classroom + 4 h hands-on), mechanical 2 shifts x 16 people (2 + 4 h), electrical/I&C 1 shift x 4 people (2 + 2 h) (pp. 129-130).",
   "evidence": "rfp_23-13_document.pdf, p. 130",
   "quote": "There will be a minimum of 2 training visits, for 3 days each."
  },
  {
   "n": 27,
   "area": "services",
   "check": "Field performance testing",
   "answer": "At UVSS expense after a 100-hour burn-in: each channel tested separately at peak and average flow, about 2 hours each, samples every 30 minutes, power metered at each bank; independent state-certified lab paid in Balance of Work (p. 128). After failed retests the Owner may reject the equipment and require removal, refund and the cost of a replacement system (p. 129).",
   "evidence": "rfp_23-13_document.pdf, p. 127",
   "quote": "Performance testing shall be at the expense of the UVSS."
  },
  {
   "n": 28,
   "area": "electrical",
   "check": "Power supply",
   "answer": "480/277 V, 3-phase, 4-wire plus ground, 60 Hz, fed from 480 V switchgear through 150 kVA isolation transformers and local disconnects; control system 120 V single phase.",
   "evidence": "rfp_23-13_document.pdf, p. 105",
   "quote": "The UV system shall be rated for a 480 / 277 volt, 3 phase, 4 wire + ground, and a 60 Hz power supply."
  },
  {
   "n": 29,
   "area": "electrical",
   "check": "Enclosure ratings",
   "answer": "Master Control Panel, ballast (driver) cabinets and the cleaning/lifting control cabinet are all NEMA 4X Type 316 stainless steel (p. 116); all electrical and control enclosures are outdoors at 33 to 104 F (p. 111); panel air conditioning if needed (p. 115). See the contradiction with Alternate C.",
   "evidence": "rfp_23-13_document.pdf, p. 116",
   "quote": "The panel shall be a NEMA 4X, Type 316 Stainless Steel, front opening, free standing panel"
  },
  {
   "n": 30,
   "area": "controls",
   "check": "PLC, SCADA and OIT",
   "answer": "Allen-Bradley ControlLogix 1756-L73 with at least 8 MB and RSLogix 5000, connected to the plant Ethernet; plant SCADA is Rockwell FactoryTalk V12 with PlantPAx 3.0. Addendum 1 Technical Answer 9 accepts ControlLogix L71. OIT at least 15 in, NEMA 4X; UPS for 30 minutes (Addendum 1 accepts a 24 VDC UPS). UVSS configures and commissions PLC/OIT.",
   "evidence": "rfp_23-13_document.pdf, p. 117",
   "quote": "The UV PLC shall be an Allen-Bradley ControlLogix controller model 1756-L73 with minimum 8MB of memory"
  },
  {
   "n": 31,
   "area": "materials",
   "check": "Materials of construction",
   "answer": "Wetted parts and all metal above the water Type 316 stainless steel; bank frames heavy-gauge 316 SS; all fasteners 316 SS (p. 124); fixed weirs by the UVSS in Type 304 SS (p. 115); slide gates 304L or 316L SS (p. 98); no blast cleaning of stainless (p. 124).",
   "evidence": "rfp_23-13_document.pdf, p. 113",
   "quote": "All wetted parts shall be AISI Type 316 stainless steel, quartz glass, Teflon, or plastics not susceptible to UV or chemical degradation"
  },
  {
   "n": 32,
   "area": "excluded",
   "check": "Work by others",
   "answer": "Installation by the Installation/General Contractor; incoming power, conduit, cable installation and field terminations; communication cabling to the plant control system (1.1.D, p. 103); anchor bolts; unloading and storage by the GC (p. 47); any external crane or jib crane by the Contractor (Addendum 1 Technical Answer 1).",
   "evidence": "rfp_23-13_document.pdf, p. 117",
   "quote": "Conduit for all power, data, control, and instrumentation field wiring and cable shall be provided and installed by Installation Contractor."
  }
 ],
 "contradictions": [
  {
   "topic": "Enclosure rating: Alternate C vs specification",
   "side_a": "Alternate C prices replacing NEMA 12 enclosures with NEMA 4X: \"Alternate C: Replace NEMA 12 enclosures with NEMA 4X.\"",
   "side_a_evidence": "rfp_23-13_document.pdf, p. 12",
   "side_b": "The specification already requires NEMA 4X Type 316 SS for the ballast cabinets, cleaning/lifting cabinet and Master Control Panel: \"Ballast (Driver) Cabinet enclosure shall be Type NEMA 4X construction, AISI Type 316 stainless steel.\"",
   "side_b_evidence": "rfp_23-13_document.pdf, p. 116",
   "why_it_matters": "If the base bid is already NEMA 4X 316 SS, Alternate C has nothing to add; if the base may be NEMA 12, the base price drops and the spec is wrong. Bidders can double count or under-price.",
   "status": "confirmed"
  },
  {
   "topic": "Outage dose basis inside Addendum 1: bank or module",
   "side_a": "Technical Answer 7 says one duty bank per channel out of service: \"shall be based on a duty UV bank per channel out of service\"",
   "side_a_evidence": "rfp_23-13_addendum1.pdf, p. 5",
   "side_b": "Technical Answer 8, same page, says one duty module per channel out of service: \"shall be based on a duty UV module per channel out of service\"",
   "side_b_evidence": "rfp_23-13_addendum1.pdf, p. 5",
   "why_it_matters": "The outage dose is a bid-form value used in the evaluation; taking a whole bank out removes many more lamps than one module, so lamp count and power change.",
   "status": "confirmed"
  },
  {
   "topic": "Outage dose basis: Addendum 1 correction vs Addendum 2 reissued bid form",
   "side_a": "Addendum 1 corrects bid form Attachment A, paragraph A.9: \"Replace “module” with “bank”.\"",
   "side_a_evidence": "rfp_23-13_addendum1.pdf, p. 2",
   "side_b": "Addendum 2 reissues the bid form 'in its entirety' and states it takes precedence over previous addenda, but A.9 again reads module: \"with one UV module in each channel out of service\"",
   "side_b_evidence": "rfp_23-13_addendum2.pdf, p. 11",
   "why_it_matters": "The outage dose and its power figure are bid-form values used in the evaluation; which equipment is assumed out of service (a whole bank or one module) changes lamp count and power.",
   "status": "confirmed"
  },
  {
   "topic": "Bonds sentence: removed by Addendum 1, back in Addendum 2",
   "side_a": "Addendum 1 replaces bid form 2.01 with a sentence without bonds: \"and replace it with: “Bidder will sign and submit the Agreement and other documents required by the Bidding Documents\"",
   "side_a_evidence": "rfp_23-13_addendum1.pdf, p. 1",
   "side_b": "The Addendum 2 reissued bid form (takes precedence) restores the bonds: \"Bidder will sign and submit the Agreement with the Bonds and other documents\"",
   "side_b_evidence": "rfp_23-13_addendum2.pdf, p. 5",
   "why_it_matters": "Decides whether a bond must be bought for the Early Work agreement.",
   "status": "confirmed"
  },
  {
   "topic": "Guaranteed lamp replacement price: 10 years vs 5 years",
   "side_a": "Construction paragraph 2.4.D.4: \"replacement costs shall be guaranteed for a minimum of 10 years from the date of Substantial Completion\"",
   "side_a_evidence": "rfp_23-13_document.pdf, p. 113",
   "side_b": "Submittal item 1.3.C.1.o: \"Certification of the specified guaranteed cost of replacement lamps for five years.\"",
   "side_b_evidence": "rfp_23-13_document.pdf, p. 108",
   "why_it_matters": "Lamp prices feed the 20-year life-cycle evaluation; a 10-year guarantee (with PPI adjustment) carries more price risk than 5 years.",
   "status": "confirmed"
  },
  {
   "topic": "Ultrasonic level sensor low temperature: -20 F vs 20 F",
   "side_a": "Original 2.7.L.5.b: \"operation over a temperature range of -20° to +150°F\"",
   "side_a_evidence": "rfp_23-13_document.pdf, p. 122",
   "side_b": "Addendum 1 revised paragraph (stated purpose was only to drop the 'If required' qualifier): \"range of 20° to +150°F\"",
   "side_b_evidence": "rfp_23-13_addendum1.pdf, p. 2",
   "why_it_matters": "Changes the minimum temperature rating the per-channel level sensor must meet; small price effect.",
   "status": "confirmed"
  },
  {
   "topic": "Who supplies communication modules and media converters for the SCADA link",
   "side_a": "Scope 1.1.D gives them to the Installation Contractor: \"Installation Contractor will be responsible for providing all data/communication cables/wires/communication modules/media converters\"",
   "side_a_evidence": "rfp_23-13_document.pdf, p. 103",
   "side_b": "PLC paragraph 2.7.E.2 (UVSS-furnished PLC): \"shall be provided with the required communication modules and media converters\"",
   "side_b_evidence": "rfp_23-13_document.pdf, p. 117",
   "why_it_matters": "Decides whether the UVSS prices the network hardware; 2.7.E.2 is passive voice, so the conflict may be only apparent.",
   "status": "likely"
  },
  {
   "topic": "Alternate B extends a warranty bond the base documents never require",
   "side_a": "Alternate B: \"Alternate B: Extend standard 12-month warranty bond to 36 months.\"",
   "side_a_evidence": "rfp_23-13_document.pdf, p. 12",
   "side_b": "No base requirement for a warranty bond found in the RFP, specifications or addenda (searched 'warranty bond' and 'bond'); only payment bonds from GC terms and the bid form bonds sentence appear: (no match in full text)",
   "side_b_evidence": "rfp_23-13_document.pdf, pp. 1-151 text layer; rfp_23-13_addendum1.pdf, pp. 1-6; rfp_23-13_addendum2.pdf, pp. 1-11 (full text searched)",
   "why_it_matters": "Unclear whether a 12-month warranty bond must be priced in the base bid.",
   "status": "likely"
  }
 ]
}