 "id": "us-mercerisland-sewer-scada",
 "country": "United States",
 "language": "English",
 "buyer": "City of Mercer Island, Washington (Public Works); engineer Brown and Caldwell",
 "project": "Sewer SCADA Systems Replacement, Bid No. 22-31 (BC project 153585)",
 "year": "2022",
 "files": [
  {
   "file": "22-31_advertisement_for_bids.pdf",
   "pages": 2,
   "text_layer": true,
   "what_it_is": "Advertisement for Bids (original October 21, 2022 due date, engineer's estimate range, list of 17 sites)."
  },
  {
   "file": "22-31_specs.pdf",
   "pages": 1292,
   "text_layer": true,
   "what_it_is": "Project manual: bidding forms, contract, general terms, Divisions 01, 26 and 40. Text layer is broken (unmapped fonts) on the work-sequence table p. 839, instrument index pp. 961-963, I/O list pp. 999-1036 and panel schedule pp. 1279-1281; pp. 121-832 are scanned reference as-builts with no text."
  },
  {
   "file": "22-31_plans.pdf",
   "pages": 425,
   "text_layer": true,
   "what_it_is": "Drawings (424 sheets plus cover): per-site demolition, PLC/IS/RIO/go-no-go panel layouts, I/O card wiring, network block diagrams, plans."
  },
  {
   "file": "mercer_island_22-31_addendum_1.pdf",
   "pages": 2,
   "text_layer": true,
   "what_it_is": "Addendum 1 (October 10, 2022): bid date moved to November 3, 2022; question deadline October 18; prevailing wage date."
  },
  {
   "file": "mercer_island_22-31_addendum_2.pdf",
   "pages": 6,
   "text_layer": true,
   "what_it_is": "Addendum 2 (October 25, 2022): 26 bidder Q&As (programming by Owner's Programmer, wiring reuse, wetwell, existing FOGRods) and PROFINET module part number change."
  },
  {
   "file": "mercer_island_22-31_addendum_3.pdf",
   "pages": 2,
   "text_layer": true,
   "what_it_is": "Addendum 3 (October 28, 2022): wetwell entry clarification and deletion of the excise tax bid line."
  }
 ],
 "quality": "The price-driving tables (I/O list, panel schedule, instrument index, cutover table) have no usable text layer, the programming is carved out to the engineer, and three addenda change the bid date, taxes, wiring reuse and wetwell entry.",
 "read_by": "Mavlon, read from the documents with AI help before any run, November 2026",
 "items": [
  "Replace PLC panels at 17 sewer sites (4 new back panels in existing enclosures, 13 complete new panels) with Siemens ET200SP PLCs and 12-inch TP1200 OITs",
  "8 new RIO panels at remote generator sites for generator monitoring",
  "New intrinsically safe panels at 15 sites; IS back panel and new level control panel at Pump Station 14",
  "14 go/no-go panels with horn and beacon; exhaust fan low flow switches at 15 stations",
  "FOGRod secondary wetwell level instruments (new at 11 sites, existing reused at PS 1 and PS 10)",
  "Motor control panel changes: remove motor reversing, add hardwired level control, remote flush valve operation at PS 15 and 16",
  "Generator monitoring improvements and generator wiring replacement at six sites",
  "Demolition of old control equipment, 'Operator in Trouble' panic buttons and abandoned float switches",
  "Circuit tracing and labeling; new conduit and cable only where scheduled, existing wiring reused elsewhere",
  "FAT, field testing, 21-day operational test and 4-week commissioning with the Owner's Programmer (Brown and Caldwell, who does all programming); hardware training"
 ],
 "checks": [
  {
   "n": 1,
   "area": "scope",
   "check": "How many sites are in the contract, and which ones?",
   "answer": "17 sites: Pump Stations 1, 4, 10, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25 and Flush Station 12. Pump Station 11 is not included (it is being upgraded under a King County project).",
   "evidence": "22-31_specs.pdf, p. 45",
   "quote": "furnish all labor and materials necessary to perform work at 17 sewer pump stations (not including pump station 11)"
  },
  {
   "n": 2,
   "area": "scope",
   "check": "How is the PLC panel work split between back-panel replacements and complete new panels?",
   "answer": "New custom back panels inside the existing enclosures (plus new OIT) at 4 sites: PS 4, 14, 15 and 25. Complete new PLC panels (back panel and enclosure) at 13 sites: PS 1, 10, 12, 13, 16, 17, 18, 19, 20, 21, 22, 23, 24. Total 17 PLC panels.",
   "evidence": "22-31_specs.pdf, p. 116",
   "quote": "Replace PLC back panels at four (4) sewer pump station sites (Pump Stations 4, 14, 15, and 25)"
  },
  {
   "n": 3,
   "area": "scope",
   "check": "How many remote I/O (RIO) panels, and where?",
   "answer": "8 new RIO panels (custom back panel and enclosure) at the remote generator sites of PS 1, 13, 17, 18, 19, 20, 21 and 24, so the generators can be monitored in SCADA.",
   "evidence": "22-31_specs.pdf, p. 116",
   "quote": "Provide new remote input/output (RIO) panels (custom fabricated back panel and enclosure) at eight (8) remote generator sites"
  },
  {
   "n": 4,
   "area": "scope",
   "check": "Which sites get intrinsically safe (IS) panels?",
   "answer": "New IS panels at 15 sites: PS 1, 4, 10, 13, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25. At PS 14 the existing IS back panel is replaced and a new level control panel is provided. Flush Station 12 has no IS panel.",
   "evidence": "22-31_specs.pdf, p. 116",
   "quote": "Provide new IS panels (custom fabricated back panel and enclosure) at select sewer pump station sites"
  },
  {
   "n": 5,
   "area": "scope",
   "check": "How many go/no-go panels and exhaust fan low flow switches?",
   "answer": "Go/no-go panels with horn and beacon at 14 stations (PS 1, 10, 13, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25). Exhaust fan low flow switches at 15 stations (the same 14 plus PS 4). No go/no-go panel at PS 4, PS 14 or Flush Station 12.",
   "evidence": "22-31_specs.pdf, p. 115",
   "quote": "Addition of an exhaust fan low flow switch at fifteen (15) stations. h. Installation of go/no-go panels at fourteen (14) stations."
  },
  {
   "n": 6,
   "area": "scope",
   "check": "How many custom panels are in the 40 67 00 panel schedule?",
   "answer": "56 panels: 17 PLC panels (CAB), 17 IS panels (one per IS site, two at PS 14: IS1440A new and IS1440B existing), 14 go/no-go panels (8 x 3.25 x 2.75 in), 8 RIO panels. Existing enclosures are reused for 5 of them: the PLC panels at PS 4, 14, 15 and 25, and IS1440B at PS 14.",
   "evidence": "22-31_specs.pdf, p. 1281; quote read from image",
   "quote": "56 SEWER PUMP STATION 25 SS_RH1_PS25_GNG2500 NEW ENCLOSURE N/A 8 x 3.25 x 2.75 WALL MOUNTED"
  },
  {
   "n": 7,
   "area": "controls",
   "check": "What PLC platform and processor are required, and are substitutes allowed?",
   "answer": "Siemens ET200SP family for PLC and RIO. CPU Siemens 1510SP-1 PN, part 6ES7510-1DJ01-0AB0, with 4MB SD card 6ES7954-8LC03-0AA0. No substitutions are permitted (Owner standard).",
   "evidence": "22-31_specs.pdf, p. 1248",
   "quote": "The PLC/RIO manufacturer and model shall be Siemens ET200SP family of PLC controllers."
  },
  {
   "n": 8,
   "area": "controls",
   "check": "What operator interface terminal is required, and how many?",
   "answer": "Siemens SIMATIC HMI TP1200 Comfort, 12 inch, part 6AV2124-0MC01-0AX0 with 2GB SD card. The panel schedule shows a 12-inch OIT on each of the 17 PLC panels and none on RIO panels.",
   "evidence": "22-31_specs.pdf, p. 1248",
   "quote": "The OIT manufacturer and model shall be Siemens TP1200 Comfort Panel."
  },
  {
   "n": 9,
   "area": "controls",
   "check": "Which PROFINET interface module part number governs (40 63 43 2.02.C.2.a)?",
   "answer": "Changed by Addendum 2, item 2.01: part 6ES7155-6AU01-0BN0 plus a bus adapter with 2 RJ45 ports, 6ES7193-6AR00-0AA0. This replaces 6ES7155-6AR00-0AN0 in the original specification. The RIO panel bills of materials list a PROFINET communication module.",
   "evidence": "mercer_island_22-31_addendum_2.pdf, p. 6",
   "quote": "a. Part number: 6ES7155-6AU01-0BN0."
  },
  {
   "n": 10,
   "area": "controls",
   "check": "Which I/O modules are specified, and are analog outputs used?",
   "answer": "Digital inputs 6ES7131-6BH01-0BA0, digital outputs 6ES7132-6BH01-0BA0, analog inputs 6ES7134-6GD01-0BA1. Analog outputs 6ES7135-6HD00-0BA1 are for spares only. Spare parts: one of each unique processor and communication module, one per ten (minimum one) of each I/O module, three of each base unit, one 12-inch OIT.",
   "evidence": "22-31_specs.pdf, p. 1249",
   "quote": "4. Analog Outputs (SPARE ONLY): a. Part number: 6ES7135-6HD00-0BA1."
  },
  {
   "n": 11,
   "area": "controls",
   "check": "How many I/O points are in the Section 40 61 93 I/O list?",
   "answer": "1,852 rows: 1,848 hardwired channels (1,312 DI, 272 DO, 264 AI, no AO) plus 4 PROFINET networked points (the existing VFDs at PS 4). By status: 486 NEW, 354 EXISTING (re-terminated at the new panel), 173 FUTURE, 839 SPARE. Each RIO has 36 channels; each PLC has 92, 96 or 112, except Flush Station 12 with 32.",
   "evidence": "22-31_specs.pdf, p. 1036; quote read from image",
   "quote": "1852 SEWER PUMP STATION 25 ___ SPARE AI SS_RH1_PS25_CAB2500 SS_RH1_PS25_PLC2501 00 10 03"
  },
  {
   "n": 12,
   "area": "controls",
   "check": "What I/O quantity per site does the 01 12 16 work-sequence table give?",
   "answer": "FS 12: 32. PS 10, 14, 15, 25: 92. PS 16, 22, 23: 96. PS 4: 112. PS 1 and 13: 92 (PLC) + 36 (RIO). PS 17, 18, 19, 20, 21, 24: 96 (PLC) + 36 (RIO). Total 1,560 PLC + 288 RIO = 1,848, matching the hardwired channels in the I/O list. Allowed cutover downtime is 6 hours at every site.",
   "evidence": "22-31_specs.pdf, p. 839; quote read from image",
   "quote": "PUMP STATION 4 Anytime 112 6 Hours"
  },
  {
   "n": 13,
   "area": "controls",
   "check": "How do the PLCs communicate with SCADA, and what network hardware is specified?",
   "answer": "Each PLC has a DNP3 communication module (6GK7542-6VX00-0XE0 with a 2-port bus adapter). The network block diagrams (e.g., I-01501) show the PLC network switch and the generator RIO each connected to a cellular modem in its own Owner-provided communication panel, which links to the SCADA network. Managed Ethernet switches: Siemens SCALANCE XC (spelled 'SCALENCE XC' in 40 67 00) or equal, 8 or 16 ports as drawn. The Owner's SCADA platform is Siemens WinCC OA.",
   "evidence": "22-31_specs.pdf, p. 1249",
   "quote": "1. DNP3 Module. a. Part number: 6GK7542-6VX00-0XE0."
  },
  {
   "n": 14,
   "area": "controls",
   "check": "Who does the PLC, RIO, OIT and SCADA programming?",
   "answer": "Not the integrator. All PLC, RIO, OIT and SCADA/HMI application programming is done by the Owner's Programmer, Brown and Caldwell (Seattle), under a separate contract (Addendum 2 Q-1; 40 61 13 1.01.C.3; 01 11 00 1.01.D.2). The 40 61 96 control descriptions are 'Information Only' for the Contractor. The integrator supplies, builds and tests the hardware, and supports the Owner's Programmer at FAT, loop, functional and operational testing.",
   "evidence": "mercer_island_22-31_addendum_2.pdf, p. 1",
   "quote": "The SCADA HMI/PLC/RIO/OIT programming is being provided by the Owner’s Programmer, Brown and Caldwell"
  },
  {
   "n": 15,
   "area": "excluded",
   "check": "Who buys the PLC/HMI software licenses?",
   "answer": "The Owner (40 63 43 1.01.A.3).",
   "evidence": "22-31_specs.pdf, p. 1245",
   "quote": "Software licensing will be purchased by the Owner."
  },
  {
   "n": 16,
   "area": "excluded",
   "check": "Who provides the communication panels with the cellular modems?",
   "answer": "The Owner. Each site's communication panel (for example SS_RH4_PS01_CAB8000, and CAB8010 at the PS 1 generator) is provided and installed by the Owner before construction. The Contractor only provides new nameplates for these existing panels.",
   "evidence": "22-31_plans.pdf, p. 27",
   "quote": "COMMUNICATION PANEL TO BE PROVIDED AND INSTALLED BY OWNER PRIOR TO PROJECT CONSTRUCTION."
  },
  {
   "n": 17,
   "area": "materials",
   "check": "What secondary wetwell level instrument is specified, and is an equal allowed?",
   "answer": "FOGRod displacer level transmitter/switch (INSTRUSPEC LDT1): sensor FOG-7.5-50, transmitter LIT-100, accessory FOG-ISB, 10 level relays and 2 fault relays, 2-year warranty, sensor approved for Class I Div 1. No equal is allowed (Owner's standard).",
   "evidence": "22-31_specs.pdf, p. 1290",
   "quote": "a. FOGRod 1) Level-7.5-50 a) Sensor: FOG-7.5-50 b) Transmitter: LIT-100 2) Accessory: FOG-ISB b. No equal, per Owner’s standards."
  },
  {
   "n": 18,
   "area": "scope",
   "check": "Where is new wetwell level instrumentation installed?",
   "answer": "New level instrumentation in the existing wetwells at 11 sites: PS 13, 14, 15, 16, 17, 18, 21, 22, 23, 24, 25. The FOGRods at PS 1 and PS 10 are existing: they are repositioned and their cable is terminated in the new IS panel (Addendum 2 Q-10 and Q-15). The instrument index lists 15 FOGRod transmitters and 11 FOGRod sensors.",
   "evidence": "22-31_specs.pdf, p. 116",
   "quote": "Provide new level instrumentation in existing wetwells at select sites (Pump Stations 13, 14, 15, 16, 17, 18, 21, 22, 23, 24, and 25)."
  },
  {
   "n": 19,
   "area": "electrical",
   "check": "What panel shop certification and labels are required?",
   "answer": "All control panels, including new back panels, must be built in a UL 508A recognized shop and carry the UL 508A label. Panels with intrinsic safety barriers also need a factory-applied UL 698A label. Field modifications need a UL inspector to re-label the panel.",
   "evidence": "22-31_specs.pdf, p. 1255",
   "quote": "including new back panels, shall be fabricated by a UL 508A recognized facility and shall bear the appropriate UL 508A Industrial Control Panel label"
  },
  {
   "n": 20,
   "area": "electrical",
   "check": "Are all panel enclosures NEMA 4X?",
   "answer": "No. New enclosures are NEMA 4X, but the panel schedule rates the reused existing PLC enclosures at PS 4, 14, 15 and 25, and both PS 14 IS enclosures (outdoor, inside a NEMA 3R enclosure), as NEMA 4. Sheet I-04001 calls the PS 4 enclosure 'EXISTING NEMA 4 ENCLOSURE'.",
   "evidence": "22-31_plans.pdf, p. 40",
   "quote": "EXISTING NEMA 4 ENCLOSURE"
  },
  {
   "n": 21,
   "area": "excluded",
   "check": "Must all conduit and wiring at each station be replaced?",
   "answer": "No. Addendum 2 Q-4 governs: new conduit and wire only where the circuit and raceway schedules on drawings I-XX701 and I-XX801 show it. Otherwise existing conduit and wiring is reused and reconnected at the new PLC panel. The 01 11 00 1.01.C.11 wording is general in nature.",
   "evidence": "mercer_island_22-31_addendum_2.pdf, p. 2",
   "quote": "Otherwise, existing conduit/wiring is to be reused and reconnected at the new PLC panel."
  },
  {
   "n": 22,
   "area": "services",
   "check": "What does the factory acceptance test (FAT) require?",
   "answer": "Integrated FAT of the panels at the integrator's shop, witnessed by the Owner and/or Engineer, with the Owner's Programmer present. The integrator first checks the wiring and certifies the I/O tested. The Contractor gives the Owner's Programmer up to one week (40 hours) at the panel shop to load the PLC program first. Written notice 30 working days before the FAT. FAT retests at no additional cost.",
   "evidence": "22-31_specs.pdf, p. 986",
   "quote": "Contractor shall provide up to a week (up to 40 hours) for the Owner’s Programmer to be onsite at the Contractor’s panel shop"
  },
  {
   "n": 23,
   "area": "services",
   "check": "What field testing follows installation?",
   "answer": "Wiring, network and loop tests (each I/O point from field device to card, with the Owner's Programmer), then functional testing led by the Owner's Programmer, then an operational test of at least 21 continuous days per site. After that, a 4-week commissioning period per site, which restarts on a significant equipment failure; the Contractor must be available at all times and pay for repairs.",
   "evidence": "22-31_specs.pdf, p. 990",
   "quote": "The test shall take place over a continuous twenty-one (21) day period as a minimum."
  },
  {
   "n": 24,
   "area": "services",
   "check": "What training is required?",
   "answer": "4 hours of PLC/RIO/OIT hardware training by the manufacturer or a certified representative (40 63 43 3.03), 4 hours of control panel hardware training (40 67 00 3.08), and two sessions of one hour for each instrument type (40 70 00 3.04). Training is held at Pump Station 16 unless agreed otherwise; lesson plans are due 30 days before.",
   "evidence": "22-31_specs.pdf, p. 1251",
   "quote": "provide four (4) hours of operating and maintenance training at the Project site to the Owner’s personnel on the product components/hardware"
  },
  {
   "n": 25,
   "area": "commercial",
   "check": "What is the warranty period?",
   "answer": "The longer of one year from Final Acceptance of the entire Project or any extended supplier warranty (General Terms 7.9.B). The FOGRod transmitter carries a 2-year warranty. Section 01 78 36 says warranties start at site Substantial Completion but also says the longest period governs (see contradictions).",
   "evidence": "22-31_specs.pdf, p. 107",
   "quote": "one year from the date of Final Acceptance of the entire Project"
  },
  {
   "n": 26,
   "area": "services",
   "check": "What qualifications must the systems integrator have?",
   "answer": "One integrator for all of Sections 40 06 70 to 40 70 00. At least 5 years of company experience with wastewater or sewer control systems; 3 similar projects in the last 10 years (one within 2 years); 3 years with the Siemens ET200SP platform; a UL 508A/698A panel shop of at least 5,000 sq ft in the continental US; a current Washington contractor's license at bid; 2 years of financials. Project manager and PCS testing manager: 5 years or 5 projects each.",
   "evidence": "22-31_specs.pdf, p. 974",
   "quote": "Three (3) years’ experience with Siemens SIMATIC ET200SP PLC platform installation and configuration."
  },
  {
   "n": 27,
   "area": "commercial",
   "check": "Must the systems integrator be named in the bid?",
   "answer": "Yes. The Subcontractor Listing in the bid must name the Systems Integrator (the bidder itself or one subcontractor meeting the 40 61 13 qualifications) with its UBI number. Leaving it out, or naming two, makes the bid nonresponsive.",
   "evidence": "22-31_specs.pdf, p. 33",
   "quote": "The bidder shall list as part of its Bid either itself or the name of the subcontractor for performance of the work of Systems Integrator"
  },
  {
   "n": 28,
   "area": "commercial",
   "check": "How is the bid schedule structured?",
   "answer": "18 lump-sum items: Items 1 to 17 are one lump sum per site, each covering Division 1 general conditions, Section 26 05 00 electrical work and Division 40 integrator work (including factory and field testing with the Owner's Programmer and hardware training). Item 18 is an Owner-set allowance of $40,000 for unforeseen items.",
   "evidence": "22-31_specs.pdf, p. 844",
   "quote": "the Owner has entered the amount of $40,000 for Unexpected Site Changes in the Proposal"
  },
  {
   "n": 29,
   "area": "commercial",
   "check": "Which tax lines apply to the bid?",
   "answer": "Addendum 3, item 3.01, deletes the 'Washington State Excise Tax (10.25%)' line from the bid schedule. The 'Washington State Sales Tax (10.1%)' line remains, so the Total Bid is the subtotal plus sales tax.",
   "evidence": "mercer_island_22-31_addendum_3.pdf, p. 2",
   "quote": "DELETE the following line in the Bid Schedule in the Bid Form:"
  },
  {
   "n": 30,
   "area": "commercial",
   "check": "What are the contract time and key dates?",
   "answer": "Final Completion within 631 calendar days of Notice to Proceed; Substantial Completion 30 calendar days before Final Completion; work starts within 10 days of NTP. NTP expected the week of January 9, 2023. Substantial Completion no later than September 30, 2024.",
   "evidence": "22-31_specs.pdf, p. 30",
   "quote": "achieve Final Completion within 631 calendar days from the Notice to Proceed"
  },
  {
   "n": 31,
   "area": "commercial",
   "check": "What are the liquidated damages?",
   "answer": "$150 per day for failing to reach Substantial Completion on time (Public Works Contract 1.3). No other liquidated damage amount is stated.",
   "evidence": "22-31_specs.pdf, p. 45",
   "quote": "Liquidated damages for failure to achieve timely Substantial Completion shall be in the amount of $150.00 per day."
  },
  {
   "n": 32,
   "area": "commercial",
   "check": "When and how are bids due?",
   "answer": "2:00 PM, November 3, 2022 (Addendum 1, item 1.01), as a PDF emailed to publicworks@mercerisland.gov. This replaces October 21, 2022 in the advertisement. Addendum 2 Q-6 refused any further extension.",
   "evidence": "mercer_island_22-31_addendum_1.pdf, p. 1",
   "quote": "Sealed bids will be received, not sent, electronically by the City until 2:00 PM on November 3, 2022."
  },
  {
   "n": 33,
   "area": "commercial",
   "check": "What is the engineer's estimate?",
   "answer": "$2,168,000 to $3,060,000.",
   "evidence": "22-31_advertisement_for_bids.pdf, p. 1",
   "quote": "Engineers Estimated Cost (range): $2,168,000 - $3,060,000"
  },
  {
   "n": 34,
   "area": "scope",
   "check": "What cutover and outage limits apply?",
   "answer": "Stations stay in service. An electrical shutdown may last at most 15 minutes, after a wetwell drawdown. PLC cutovers only Monday to Thursday; work hours 7 am to 6 pm, no weekends; 3 weeks' written notice. Allowed control-system cutover time is 6 hours per site. Finish one station before starting the next unless the Owner approves. The IS panel and FOGRod must be commissioned before each PLC cutover so the station can run on hardwired level control. PS 25 cutover only between October 1 and April 1.",
   "evidence": "22-31_specs.pdf, p. 833",
   "quote": "If an electrical shutdown is required at a sewer pump station site, a maximum of 15 minutes of downtime is allowed."
  },
  {
   "n": 35,
   "area": "scope",
   "check": "Should the bid assume wetwell entry?",
   "answer": "Yes. Addendum 3 Q-7 governs: assume wetwell entry at all stations for wetwell work such as float switch demolition and FOGRod installation or adjustment. The wetwells stay active and have historically been entered 'as is'. This replaces Addendum 2's statement that entry was unlikely.",
   "evidence": "mercer_island_22-31_addendum_3.pdf, p. 1",
   "quote": "assume work identified in the Contract Documents associated with the wetwell, e.g., float switch demolition and FOGRod installation/adjustment, will require wetwell entry at all stations."
  }
 ],
 "contradictions": [
  {
   "topic": "Bid due date",
   "side_a": "Advertisement: bids due 2:00 PM on October 21, 2022. Quote: \"Sealed bids will be received, not sent, electronically by the City until 2:00 PM on October 21, 2022.\"",
   "side_a_evidence": "22-31_advertisement_for_bids.pdf, p. 1",
   "side_b": "Addendum 1, item 1.01: bids due 2:00 PM on November 3, 2022 (governs). Quote: \"Sealed bids will be received, not sent, electronically by the City until 2:00 PM on November 3, 2022.\"",
   "side_b_evidence": "mercer_island_22-31_addendum_1.pdf, p. 1",
   "why_it_matters": "Anyone reading only the advertisement prices to a date that no longer applies and loses about two weeks for supplier and panel quotes.",
   "status": "confirmed"
  },
  {
   "topic": "Bidder question deadline",
   "side_a": "Advertisement: questions until 5:00 PM on October 7, 2022 (also in Instructions to Bidders). Quote: \"The City will receive questions until 5:00 PM on October 7, 2022.\"",
   "side_a_evidence": "22-31_advertisement_for_bids.pdf, p. 1",
   "side_b": "Addendum 1, item 1.02: questions until 5:00 PM on October 18, 2022 (governs). Quote: \"The City will receive questions until 5:00 PM on October 18, 2022.\"",
   "side_b_evidence": "mercer_island_22-31_addendum_1.pdf, p. 1",
   "why_it_matters": "It decides whether scope questions, such as wiring reuse or wetwell entry, could still be asked before pricing.",
   "status": "confirmed"
  },
  {
   "topic": "Washington State excise tax line",
   "side_a": "Bid form schedule includes a 'Washington State Excise Tax (10.25%)' line next to the 10.1% sales tax line. Quote: \"Washington State Excise Tax (10.25%)\"",
   "side_a_evidence": "22-31_specs.pdf, p. 31",
   "side_b": "Addendum 3, item 3.01, deletes the excise tax line from the bid schedule (governs). Quote: \"DELETE the following line in the Bid Schedule in the Bid Form:\"",
   "side_b_evidence": "mercer_island_22-31_addendum_3.pdf, p. 2",
   "why_it_matters": "Keeping the line would add 10.25% to the total bid and could change who is low bidder.",
   "status": "confirmed"
  },
  {
   "topic": "New conduit and cable versus reuse of existing wiring",
   "side_a": "Summary of Work 1.01.C.11: pull and terminate new cable at all pump station locations. Quote: \"Pull and terminate new power, control, signal, and data cable at all pump station locations.\"",
   "side_a_evidence": "22-31_specs.pdf, p. 117",
   "side_b": "Addendum 2 Q-4: new conduit and wire only where the I-XX701/I-XX801 schedules show it; otherwise reuse existing (governs). Quote: \"Otherwise, existing conduit/wiring is to be reused and reconnected at the new PLC panel.\"",
   "side_b_evidence": "mercer_island_22-31_addendum_2.pdf, p. 2",
   "why_it_matters": "Rewiring every station versus re-terminating existing wiring is one of the largest labor swings in each site's lump sum.",
   "status": "confirmed"
  },
  {
   "topic": "Wetwell entry",
   "side_a": "Addendum 2 Q-7: wetwell entry is unlikely to be needed. Quote: \"It is unlikely that wetwell entry will be necessary.\"",
   "side_a_evidence": "mercer_island_22-31_addendum_2.pdf, p. 2",
   "side_b": "Addendum 3 Q-7 clarification: assume wetwell entry at all stations (governs). Quote: \"will require wetwell entry at all stations.\"",
   "side_b_evidence": "mercer_island_22-31_addendum_3.pdf, p. 1",
   "why_it_matters": "Confined-space entry crews, gas monitoring and extra time are needed at every station if entry is assumed.",
   "status": "confirmed"
  },
  {
   "topic": "PROFINET interface module part number",
   "side_a": "Section 40 63 43 2.02.C.2.a: PROFINET Interface Module part 6ES7155-6AR00-0AN0. Quote: \"PROFINET Interface Module. a. Part number: 6ES7155-6AR00-0AN0.\"",
   "side_a_evidence": "22-31_specs.pdf, p. 1249",
   "side_b": "Addendum 2 item 2.01: part 6ES7155-6AU01-0BN0 plus bus adapter 6ES7193-6AR00-0AA0 (governs). Quote: \"a. Part number: 6ES7155-6AU01-0BN0. b. Bus Adapter – 2 RJ45 Ports. Part number: 6ES7193-6AR00-0AA0.\"",
   "side_b_evidence": "mercer_island_22-31_addendum_2.pdf, p. 6",
   "why_it_matters": "A different interface module plus an added bus adapter changes the hardware bill of materials for every PROFINET interface module.",
   "status": "confirmed"
  },
  {
   "topic": "Pump Station 20 PLC enclosure: new or existing",
   "side_a": "Drawing I-20001 (PS 20 PLC panel layout) bill of materials item 11: 'EXISTING ENCLOSURE'. Quote: \"EXISTING ENCLOSURE\"",
   "side_a_evidence": "22-31_plans.pdf, p. 277",
   "side_b": "Summary of Work lists PS 20 among the 13 sites getting a complete new PLC panel; the 40 67 00 panel schedule (p. 1280) shows SS_RH2_PS20_CAB2000 as NEW ENCLOSURE, 72 x 30 x 16. Quote: \"at thirteen (13) sewer pump station sites (Pump Stations 1, 10, 12, 13, 16, 17, 18, 19, 20, 21, 22, 23, and 24)\"",
   "side_b_evidence": "22-31_specs.pdf, p. 116",
   "why_it_matters": "A new 72 x 30 x 16 NEMA 4X enclosure with installation versus reuse of the existing one is a clear material and labor difference at PS 20.",
   "status": "confirmed"
  },
  {
   "topic": "Digital output card channel count on PLC rack layouts",
   "side_a": "PLC rack layouts label slot 07 'DIGITAL OUTPUT 4-CHANNEL' (for example drawing I-20001). Quote: \"DIGITAL OUTPUT 4-CHANNEL\"",
   "side_a_evidence": "22-31_plans.pdf, p. 277",
   "side_b": "The same sheet's bill of materials lists a '16 CHANNEL DIGITAL OUTPUT MODULE'; DO card drawing I-01201 labels 6ES7132-6BH01-0BA0 'DIGITAL OUTPUT MODULE (SLOT 07)' with the line below; the I/O list has 16 DO channels per PLC. Quote: \"16 CHANNEL, 24 VDC / 0.5A\"",
   "side_b_evidence": "22-31_plans.pdf, p. 23",
   "why_it_matters": "Reading the rack label would under-count DO channels and terminals; the 16-channel part, the bill of materials and the I/O list agree.",
   "status": "confirmed"
  },
  {
   "topic": "Warranty start date",
   "side_a": "General Terms 7.9.B: warranty is the longer of one year from Final Acceptance of the entire Project or any extended supplier warranty. Quote: \"one year from the date of Final Acceptance of the entire Project\"",
   "side_a_evidence": "22-31_specs.pdf, p. 107",
   "side_b": "Section 01 78 36 1.03.A: warranties begin at Substantial Completion for each site or portion; 1.01.C says the longest period ending latest governs. Quote: \"All warranties begin at the date of Substantial Completion for the site\"",
   "side_b_evidence": "22-31_specs.pdf, p. 899",
   "why_it_matters": "If the warranty only starts at Final Acceptance of the whole project, sites cut over early carry a much longer warranty period.",
   "status": "confirmed"
  },
  {
   "topic": "Integrator qualification submittal deadline",
   "side_a": "Section 40 61 13 1.06.B.2: Quality Assurance submittal within 14 days of Notice to Proceed. Quote: \"Quality Assurance (within 14 days of contract Notice to Proceed)\"",
   "side_a_evidence": "22-31_specs.pdf, p. 973",
   "side_b": "Section 01 12 16 1.06.A.1.a: 40 61 13 Quality Assurance submittal within 21 days after Notice to Proceed. Quote: \"Quality Assurance Submittal within 21 days after the effective date of the Notice to Proceed.\"",
   "side_b_evidence": "22-31_specs.pdf, p. 834",
   "why_it_matters": "The integrator's qualification and personnel package has to be ready a week earlier under the stricter reading.",
   "status": "confirmed"
  },
  {
   "topic": "Factory test notice period",
   "side_a": "Section 40 61 21 3.02.A.1.b: written notice 30 working days before the FAT. Quote: \"Provide written notice to the Owner and Engineer 30 working days before the commencement of the FAT activity\"",
   "side_a_evidence": "22-31_specs.pdf, p. 986",
   "side_b": "Section 40 67 00 3.06.A: notify the Owner/Engineer at least three weeks before the factory shop test. Quote: \"notify the Owner/Engineer at least three (3) weeks in advance prior to the scheduled factory shop test.\"",
   "side_b_evidence": "22-31_specs.pdf, p. 1273",
   "why_it_matters": "About six weeks versus three weeks of notice moves the panel-shop schedule and ship dates; it is 'likely' only because the two sections may mean different factory tests.",
   "status": "likely"
  }
 ]
}