 "id": "us-tampa-gritwashers",
 "country": "United States",
 "language": "English",
 "buyer": "City of Tampa, Florida (Wastewater Department, Contract Administration Department); engineer Hazen and Sawyer",
 "project": "Contract 17-C-00031, Howard F. Curren AWTP Screen and Grit Building 2 Grit Washer Replacements",
 "year": "2017",
 "files": [
  {
   "file": "17-c-00031bidnoticeu1.pdf",
   "pages": 1,
   "text_layer": true,
   "what_it_is": "Bid notice memo: bid date November 7, 2017, estimate $1,700,000, scope summary"
  },
  {
   "file": "17-c-00031specificationsu1.pdf",
   "pages": 213,
   "text_layer": true,
   "what_it_is": "Specification book: instructions to bidders, proposal form (pp. 22-24), agreement and general provisions (two-column pages), specific provisions (pp. 60-74), workmanship and materials sections W-9 to W-76, 11000 equipment general provisions (pp. 140-151), 11412 grit washers (pp. 152-171), 15000, 15995, 16050, 17000 instrumentation"
  },
  {
   "file": "17-c-00031plansu1.pdf",
   "pages": 18,
   "text_layer": true,
   "what_it_is": "17 drawing sheets plus a city cover page (sheet N is PDF page N+1); drawings are vector with very little extractable text, so notes and keynotes must be read from the image"
  },
  {
   "file": "17-c-00031add1u1.pdf",
   "pages": 9,
   "text_layer": true,
   "what_it_is": "Addendum 1 (November 3, 2017): bid date moved to November 21, 2017; changes to 15000, W-32, 11412 and 17000; replacement drawing sheets 14 and 16 (pp. 7-8, vector); scanned pre-bid sign-in sheet (p. 9)"
  }
 ],
 "quality": "A general construction contract where the grit washer is one section: the maker's scope is split across 11412, 11000, W-47, W-62 and 17000, Addendum 1 rewrites many 11412 paragraphs by sentence-level edits, the drawings carry their notes only as graphics, and the performance test terms disagree with each other.",
 "read_by": "Mavlon, read from the documents with AI help before any run, November 2026",
 "items": [
  "Two grit washer units (Eutek SlurryCup / Grit Snail basis of design, or approved equal): four 32-inch SlurryCup classifiers (two per escalator) and two Grit Snail dewatering escalators",
  "One control panel per grit washer with VFD, GE RX3i PLC, operator interface, UPS and Ethernet link to the Division 17 main control panel",
  "Manufacturer-supplied flexible rubber discharge boot and 316 stainless anchors (Addendum 1)",
  "Spare parts, field services (installation, startup and training, performance testing, 180-day return visit), performance guarantee with independent testing"
 ],
 "checks": [
  {
   "n": 1,
   "area": "scope",
   "check": "How many grit washers are supplied?",
   "answer": "Two grit washers. Addendum 1 (Item 4.1) inserts 'dual' so each grit washer includes dual grit classifiers (SlurryCups). Drawing sheet 9 shows units SG-GW-1 and SG-GW-2, each with two classifiers.",
   "evidence": "17-c-00031specificationsu1.pdf, p. 152",
   "quote": "Two grit washers shall be supplied."
  },
  {
   "n": 2,
   "area": "scope",
   "check": "How many SlurryCup classifiers and escalators, and what size?",
   "answer": "Four SlurryCup units (2 duty, 2 standby), 32-inch diameter, two per Grit Escalator; one escalator per two classification units, so two escalators.",
   "evidence": "17-c-00031specificationsu1.pdf, p. 152",
   "quote": "Number of Units: 4 (2 duty, 2 standby), 2 per Grit Escalator"
  },
  {
   "n": 3,
   "area": "scope",
   "check": "What is the basis of design and is an equal allowed?",
   "answer": "Slurry Cup / Grit Snail by Eutek Systems of Hydro International, or approved equal. The contractor may not order equipment before the engineer approves the manufacturer (SP-13, p. 61).",
   "evidence": "17-c-00031specificationsu1.pdf, p. 154",
   "quote": "Slurry Cup / Grit Snail as manufactured by Eutek Systems of Hydro International or approved equal"
  },
  {
   "n": 4,
   "area": "excluded",
   "check": "Which technologies are excluded?",
   "answer": "Grit screw classifiers, grasshoppers, reciprocating rakes and similar units are not accepted; units using Apex valves are not accepted.",
   "evidence": "17-c-00031specificationsu1.pdf, p. 153",
   "quote": "Grit screw classifiers, grasshoppers, reciprocating rakes and similar type of units shall not be accepted."
  },
  {
   "n": 5,
   "area": "design",
   "check": "What hydraulic design flows apply per SlurryCup?",
   "answer": "Design 330 gpm with 88 in headloss; minimum 280 gpm with 63 in; maximum 400 gpm with 128 in. Connections: 6 in flanged influent, 8 in flanged effluent drain, 3 in NPT underflow, 1.5 in NPT effluent water; 316 SS; continuous or intermittent operation (pp. 152-153).",
   "evidence": "17-c-00031specificationsu1.pdf, p. 152",
   "quote": "Design Flow/Unit: 330 gpm with 88“ of headloss"
  },
  {
   "n": 6,
   "area": "design",
   "check": "What performance must be guaranteed?",
   "answer": "Each grit washer removes at least 95% of grit larger than 75 micron with specific gravity 2.65 or more; dewatered grit at least 60% total solids and at most 20% volatile solids. The feed solids and test particle size are stated inconsistently (see contradictions).",
   "evidence": "17-c-00031specificationsu1.pdf, p. 152",
   "quote": "removing at least 95 percent of the grit (containing up to 1 percent solids) entering the feed inlet that is larger than 75 micron"
  },
  {
   "n": 7,
   "area": "design",
   "check": "What is the escalator capacity and size?",
   "answer": "6 CY/hour; minimum 72 in square clarifier; 36 in wide belt inclined at 30 degrees; clarifier settling rate not to exceed 3.2 gpm/sq ft; belt speed adjustable 1-5 ft/min by VFD (p. 157).",
   "evidence": "17-c-00031specificationsu1.pdf, p. 156",
   "quote": "The Grit Dewatering Escalator unit shall have a capacity of 6 CY/hour"
  },
  {
   "n": 8,
   "area": "design",
   "check": "What water supply does each SlurryCup and escalator combination need?",
   "answer": "Clarified non-potable water at a regulated 50 psig plus or minus 5 psi: 30 gpm continuous per SlurryCup, 47 gpm intermittent during backwash, 30 gpm continuous for the escalator.",
   "evidence": "17-c-00031specificationsu1.pdf, p. 157",
   "quote": "clarified non-potable water supplied at a regulated 50 psig ± 5 psi"
  },
  {
   "n": 9,
   "area": "materials",
   "check": "What are the SlurryCup vessel materials?",
   "answer": "32 in diameter, 316 stainless steel, acid passivated; dished heads 1/4 in, walls 3/16 in; 32 in top access manhole; Belzona abrasion coating on the inside bottom; stainless King 35 gpm flowmeter for fluidizing water; designed for 14.7 psig maximum.",
   "evidence": "17-c-00031specificationsu1.pdf, p. 155",
   "quote": "The washing unit shall be 32 inches in diameter and fabricated of 316 stainless steel acid passivated to a uniform finish."
  },
  {
   "n": 10,
   "area": "materials",
   "check": "What are the escalator materials?",
   "answer": "Clarifier and belt housing Type 316 stainless; detachable Type 316 covers with no odor control connection; Type 316 head and tail rolls; stainless glass bead blasted and acid washed; polyester belt with neoprene cleats; HDPE headroll scraper.",
   "evidence": "17-c-00031specificationsu1.pdf, p. 156",
   "quote": "The clarifier and belt housing shall be Type 316 stainless steel."
  },
  {
   "n": 11,
   "area": "scope",
   "check": "Who supplies the equipment anchors, and what type?",
   "answer": "Governing value from Addendum 1 (Item 4.3, revising 11412 2.03 B): anchors sized and provided by the manufacturer, epoxy set, Type 316 stainless anchor bolts, nuts and washers, with Type 316 leveling nuts on at least 1 in of grout, fixed to the existing concrete floor.",
   "evidence": "17-c-00031add1u1.pdf, p. 2",
   "quote": "Anchors shall be sized and provided by the manufacturer and shall be epoxy set, Type 316 stainless steel concrete anchor bolts, nuts, and washers"
  },
  {
   "n": 12,
   "area": "scope",
   "check": "What does the manufacturer supply at the escalator discharge?",
   "answer": "Governing value from Addendum 1 (Item 4.4, replacing 11412 2.03 C): a manufacturer-supplied, mechanically connected, replaceable flexible rubber boot that diverts grit into the Contractor-supplied aluminum discharge chute. The original 2.03 C (316 SS flange adaptor for a contractor rubberized chute) and 1.03 C (contractor flexible chute) are replaced.",
   "evidence": "17-c-00031add1u1.pdf, p. 3",
   "quote": "discharge shall include a manufacturer-supplied, mechanically connected, replaceable, flexible rubber boot to divert collected grit into the Contractor supplied aluminum discharge chute"
  },
  {
   "n": 13,
   "area": "electrical",
   "check": "What escalator drive motor is specified?",
   "answer": "1/2 hp, 3 phase, 230/460 VAC, 60 Hz, NEMA Design B, XPFC enclosure, Class 1 Division 1 Group D; table on p. 158: 460 V, 1735 rpm, Class H insulation, service factor 1.00, inverter duty, no space heater, no winding temperature switches; integral helical gear reducer with torque-limiting clutch.",
   "evidence": "17-c-00031specificationsu1.pdf, p. 157",
   "quote": "The motor shall be ½ hp, 3 phase, 230/460 VAC, 60 Hz, NEMA Design B, XPFC enclosure"
  },
  {
   "n": 14,
   "area": "electrical",
   "check": "What hazardous area rating applies to devices on the units?",
   "answer": "All manufacturer electrical appurtenances in and around the units (motors, solenoid valves, motion sensors) rated Class I, Division 1, Group D. Solenoids 120 VAC, Type 316 SS body, explosion proof, JD Gould or equal.",
   "evidence": "17-c-00031specificationsu1.pdf, p. 158",
   "quote": "shall be rated for installation in a Class I, Division 1, Group D, hazardous location"
  },
  {
   "n": 15,
   "area": "controls",
   "check": "What control panel construction is required?",
   "answer": "One wall-mounted panel per grit washer, UL 508 with serialized label, NEMA 12 painted steel minimum 14 gauge, in the ventilated non-classified electrical room; aluminum inner dead front; EXM, Hoffman or approved equal; fed 480 V from the existing MCC (p. 167).",
   "evidence": "17-c-00031specificationsu1.pdf, p. 159",
   "quote": "Enclosure shall be NEMA 12 painted steel enclosure, minimum 14 gauge suitable for mounting in the ventilated, non-classified electrical room"
  },
  {
   "n": 16,
   "area": "controls",
   "check": "Which named components must the panel use?",
   "answer": "Yaskawa VFD with Ethernet link and input line and output load filters (p. 160); GE Intelligent Platforms RX3i PLC; Maple Systems HMI5070LB 7 in operator interface; APC Schneider UPS with Ethernet and manual bypass; Stratix 5700 switch; Phoenix Contact phase monitor, load monitors and surge devices (pp. 161-162).",
   "evidence": "17-c-00031specificationsu1.pdf, p. 160",
   "quote": "The PLC shall be GE Intelligent Platforms RX3i"
  },
  {
   "n": 17,
   "area": "controls",
   "check": "Which PLC modules count as the City's standard (Addendum 1)?",
   "answer": "Addendum 1 Item 4.7 adds the City's standard RX3i list: GE IC694ALG392 AO, IC694ALG221 or IC695ALG616 AI, IC694MDL940 DO, IC694MDL240 DI, IC695ETM001 Ethernet, IC695PSA140 power supply, 12-slot (preferred) or 16-slot base, GE695CPE305 CPU.",
   "evidence": "17-c-00031add1u1.pdf, p. 3",
   "quote": "Rx3i CPU – GE695CPE305 CPU, 5 MB User Memory, Ethernet port"
  },
  {
   "n": 18,
   "area": "controls",
   "check": "What signals go to the Division 17 main control panel over Ethernet (as amended)?",
   "answer": "Addendum 1: pump interrupt during SlurryCup blowdown (Item 4.5); blowdown stops the associated grit pump via a pump enable over Ethernet (Item 4.10); belt speed via the Ethernet link instead of 4-20 mA (Item 4.11); minimum register list: SlurryCup enable, ready, running, blowdown, backwash, UPS status, VFD status/control, PLC and switch faults (Item 4.12, p. 4).",
   "evidence": "17-c-00031add1u1.pdf, p. 3",
   "quote": "shall send a pump interrupt signal to the Grit Removal System Main Control Panel PLC to temporarily stop the associated grit pump"
  },
  {
   "n": 19,
   "area": "controls",
   "check": "Who programs the grit washer PLC and to what standard?",
   "answer": "The manufacturer: its standard control algorithms modified to City practices for tagnames, file management, commenting and messaging blocks (Addendum 1 Item 4.9). The manufacturer also reviews and approves the main panel PLC programming before final programming (p. 159).",
   "evidence": "17-c-00031add1u1.pdf, p. 3",
   "quote": "PLC programming shall be manufacturer’s standard control algorithms modified to reflect standard City practices"
  },
  {
   "n": 20,
   "area": "excluded",
   "check": "Which control items are not in the grit washer supply?",
   "answer": "Remote LOR and OCR selector switches and emergency stops are supplied under Division 17; the main control panel is Division 17; the Ethernet cable is Division 17 and conduit Division 16 (p. 161); panel mounting and anchors by the Contractor (Addendum 1 Item 4.6).",
   "evidence": "17-c-00031specificationsu1.pdf, p. 162",
   "quote": "The remote mounted switches shall be supplied under Division 17."
  },
  {
   "n": 21,
   "area": "services",
   "check": "What field service trips and days are required?",
   "answer": "Installation and testing: 1 trip x 2 days; startup and training: 1 trip x 3 days minimum; performance testing: 1 trip x 5 days (Addendum 1 Item 4.15 changes 2 to 5); services after startup: 1 trip x 1 day (return 180 days after startup per 11000 3.03 C.5, p. 147). Times exclude travel (p. 147).",
   "evidence": "17-c-00031add1u1.pdf, p. 4",
   "quote": "revise the number of days/trips for performance testing in the table from “2” to “5”."
  },
  {
   "n": 22,
   "area": "services",
   "check": "How many training sessions?",
   "answer": "Training repeated three times: Tuesday afternoon, Thursday morning, and a third session for maintenance and instrumentation staff. 11000 requires training for three shifts between 6 AM and 6 PM with professional video recording by the Contractor (p. 147).",
   "evidence": "17-c-00031specificationsu1.pdf, p. 171",
   "quote": "Training will need to be repeated three times."
  },
  {
   "n": 23,
   "area": "services",
   "check": "What spare parts are required?",
   "answer": "SlurryCup: 4 baffles, 2 x 1.5 in solenoid valves, 2 x 0-30 psi gauges, 1 x 0-100 psi gauge, 1 x 1.5 in flowmeter. Grit Snail: 1 set gaskets, bearings, scrapers; 1 motor; 1 gearbox; 1 x 1 in solenoid valve; 1 x 1 in flowmeter; 1 proximity switch (p. 168). Packed in cardboard boxes (Addendum 1 Item 4.14). Plus a one-year supply of lubricants (11000, p. 145).",
   "evidence": "17-c-00031specificationsu1.pdf, p. 167",
   "quote": "Provide the following spare parts in addition to the lubricants identified in Section 11000"
  },
  {
   "n": 24,
   "area": "design",
   "check": "Who runs the performance test and what if it fails?",
   "answer": "Independent firm Black Dog Analytical, retained by the Contractor, paid by the Owner from an allowance; test within 4 weeks of startup, three samples over a week for each of solids, volatile solids and capture (seeding with Ganusil 5010 at 250 lb/MG minimum if needed); manufacturer's representative present; on failure the manufacturer modifies at its own expense until three consecutive passing tests (p. 170).",
   "evidence": "17-c-00031specificationsu1.pdf, p. 169",
   "quote": "The cost for the testing by Black Dog Analytical shall be borne by the OWNER using the allowance indicated on the bid form."
  },
  {
   "n": 25,
   "area": "commercial",
   "check": "How much payment is held against the performance test?",
   "answer": "Up to 10% of the equipment cost, in addition to normal retainage, paid only after a successful test. A deduction table cuts 2.5%, 5%, 7.5% or 10% of the purchase price for shortfalls in volatile solids, solids or removal.",
   "evidence": "17-c-00031specificationsu1.pdf, p. 170",
   "quote": "A maximum of 10% of the cost of the equipment shall be set as the value for completion of the performance test."
  },
  {
   "n": 26,
   "area": "commercial",
   "check": "What equipment warranty applies?",
   "answer": "One year from start-up/final acceptance unless the equipment section says otherwise; it starts when the engineer accepts the equipment after a satisfactory 30-day operational period (delayed if that period fails). 11412 adds no longer warranty.",
   "evidence": "17-c-00031specificationsu1.pdf, p. 143",
   "quote": "for a period of one (1) year from date of start-up/final acceptance, unless otherwise specified"
  },
  {
   "n": 27,
   "area": "commercial",
   "check": "What contract time and liquidated damages apply?",
   "answer": "360 consecutive calendar days from the Notice to Proceed; liquidated damages $500 per calendar day.",
   "evidence": "17-c-00031specificationsu1.pdf, p. 8",
   "quote": "for completion of this project shall be $500 per calendar day."
  },
  {
   "n": 28,
   "area": "design",
   "check": "Is shop testing required before shipment?",
   "answer": "Yes. All equipment shop tested by the manufacturer to prove compliance; nothing ships until the engineer accepts certified results; five certified copies of test data (p. 146). A notarized performance affidavit signed by a vice president or higher, three originals, comes with the first shop drawings (p. 153).",
   "evidence": "17-c-00031specificationsu1.pdf, p. 145",
   "quote": "All equipment shall be tested in the shop of the manufacturer"
  },
  {
   "n": 29,
   "area": "commercial",
   "check": "Can both units be installed and started together?",
   "answer": "No. One grit washer stays in service; work on the second system starts only after successful startup and acceptance of the first, so startup work happens twice in sequence.",
   "evidence": "17-c-00031specificationsu1.pdf, p. 61",
   "quote": "Replacement work shall be on only one system at a time"
  },
  {
   "n": 30,
   "area": "excluded",
   "check": "Are the grit feed plug valve actuators in the grit washer supply?",
   "answer": "No. Addendum 1 Item 3.1 changes the W-32.09 plug valve actuators from electric to pneumatic per W-32.12, supplied with the valve by the valve manufacturer as a single-source unit; plug valves are DeZurik PEF with no other maker considered (p. 104).",
   "evidence": "17-c-00031add1u1.pdf, p. 1",
   "quote": "pneumatic actuators as specified under W-32.12. Pneumatic actuators"
  }
 ],
 "contradictions": [
  {
   "topic": "Feed solids concentration for the guarantee",
   "side_a": "(containing up to 1 percent solids)",
   "side_a_evidence": "17-c-00031specificationsu1.pdf, p. 152",
   "side_b": "Influent Solids Concentration: ≤ 1.5 %",
   "side_b_evidence": "17-c-00031specificationsu1.pdf, p. 152",
   "why_it_matters": "The 95% capture guarantee is easier at 1% feed solids than at 1.5%; the maker must know which feed it is guaranteeing against before sizing and accepting penalty risk.",
   "status": "confirmed"
  },
  {
   "topic": "Grit particle size used for the capture guarantee and test",
   "side_a": "95 percent of the grit (containing up to 1 percent solids) entering the feed inlet that is larger than 75 micron",
   "side_a_evidence": "17-c-00031specificationsu1.pdf, p. 152",
   "side_b": "sieve to determine the portion greater than 0.105 mm in size",
   "side_b_evidence": "17-c-00031specificationsu1.pdf, p. 170",
   "why_it_matters": "The guarantee is at 75 micron, but the test sieves at 0.105 mm and the formula defines solids as 0.21 mm or larger (same page); the capture result and the penalty exposure depend on which size is measured.",
   "status": "confirmed"
  },
  {
   "topic": "Pass mark for capture: 90% passes, but 90-95% carries a deduction",
   "side_a": "results ≥90% would be considered passing",
   "side_a_evidence": "17-c-00031specificationsu1.pdf, p. 170",
   "side_b": "≥90%and <95% 2.5%",
   "side_b_evidence": "17-c-00031specificationsu1.pdf, p. 170",
   "why_it_matters": "A result of 90-95% is called passing yet appears in the table as a 2.5% price deduction; 3.02 G.6 also requires modification until the criteria are met, so it is unclear whether a shortfall costs money or rework.",
   "status": "confirmed"
  },
  {
   "topic": "Performance testing allowance that the bid form does not contain",
   "side_a": "shall be borne by the OWNER using the allowance indicated on the bid form",
   "side_a_evidence": "17-c-00031specificationsu1.pdf, p. 169",
   "side_b": "The contingency is for the purpose of compensating the Contractor for any incidental work that may arise as construction operations proceed",
   "side_b_evidence": "17-c-00031specificationsu1.pdf, p. 63",
   "why_it_matters": "The proposal (p. 23) has only a lump sum base bid and 'any allowances that may be stated in SP-60', and SP-60 is a $100,000 contingency for incidental work, not a testing allowance; bidders cannot tell whether Black Dog testing is in or out of their price.",
   "status": "confirmed"
  },
  {
   "topic": "Motor service factor",
   "side_a": "They shall have a 1.15 service factor.",
   "side_a_evidence": "17-c-00031specificationsu1.pdf, p. 123",
   "side_b": "Service Factor 1.00",
   "side_b_evidence": "17-c-00031specificationsu1.pdf, p. 158",
   "why_it_matters": "11412 2.05 A says W-47 also applies and the more stringent requirement governs, so the standard 1.0 SF escalator gear motor may have to be upgraded to 1.15 SF.",
   "status": "confirmed"
  },
  {
   "topic": "Pushbutton and pilot light rating",
   "side_a": "Push buttons, pilot lights, etcetera, shall be 30mm in diameter and rated NEMA 4X.",
   "side_a_evidence": "17-c-00031specificationsu1.pdf, p. 126",
   "side_b": "Indicator lights shall be NEMA 12, 1.2” (30 mm) dia. mounting hole",
   "side_b_evidence": "17-c-00031specificationsu1.pdf, p. 162",
   "why_it_matters": "11412 2.06 A applies W-62 with the more stringent requirement governing, which would push panel operators to NEMA 4X.",
   "status": "confirmed"
  },
  {
   "topic": "Panel cooling sized for two VFDs, but each panel has one VFD",
   "side_a": "including both VFDs at maximum heat output",
   "side_a_evidence": "17-c-00031specificationsu1.pdf, p. 161",
   "side_b": "The panel shall include a VFD suitable for the grit escalator 480V motor.",
   "side_b_evidence": "17-c-00031specificationsu1.pdf, p. 160",
   "why_it_matters": "Each grit washer has one escalator motor and one panel; 'both VFDs' suggests a shared panel or two drives, which changes panel size, fan and filter sizing.",
   "status": "confirmed"
  },
  {
   "topic": "When the one-year warranty starts",
   "side_a": "The period of such warranties shall start on the date the particular equipment is accepted for completion by the Engineer",
   "side_a_evidence": "17-c-00031specificationsu1.pdf, p. 143",
   "side_b": "for guaranty of all parts of the work, for one year after the date of acceptance of all the work on the project.",
   "side_b_evidence": "17-c-00031specificationsu1.pdf, p. 62",
   "why_it_matters": "Units are replaced one after the other, so a warranty from acceptance of all work stretches the first unit's coverage by the whole second-unit period.",
   "status": "confirmed"
  },
  {
   "topic": "Spare parts packing: wooden or cardboard boxes",
   "side_a": "Pack spare parts in wooden boxes",
   "side_a_evidence": "17-c-00031specificationsu1.pdf, p. 168",
   "side_b": "replace the words “wooden boxes” with “cardboard boxes” in paragraph B. and delete paragraph C.",
   "side_b_evidence": "17-c-00031add1u1.pdf, p. 4",
   "why_it_matters": "11412 2.07 B and C contradicted each other (wooden vs cardboard, same page); Addendum 1 resolves it to cardboard, which is cheaper.",
   "status": "confirmed"
  },
  {
   "topic": "Escalator discharge chute: original spec vs drawing (resolved by Addendum 1)",
   "side_a": "Contractor shall supply flexible rubberized discharge chute to divert dewatered grit to the truck bed located below.",
   "side_a_evidence": "17-c-00031specificationsu1.pdf, p. 154",
   "side_b": "CONTRACTOR TO PROVIDE CHUTE CONSTRUCTED OF 1/4 INCH THICK ALUMINUM",
   "side_b_evidence": "17-c-00031plansu1.pdf, p. 11 (sheet 10, quote read from image)",
   "why_it_matters": "The spec had the contractor supplying a flexible rubber chute and the drawing an aluminum chute with a flexible connection; Addendum 1 Item 4.4 makes the flexible rubber boot a manufacturer supply item, which the maker must now price.",
   "status": "confirmed"
  },
  {
   "topic": "Plug valve actuators: electric in W-32.09, pneumatic on the drawings (resolved by Addendum 1)",
   "side_a": "Plug valves shall be provided with electric actuators as specified under Section 15106, Actuators, Electric.",
   "side_a_evidence": "17-c-00031specificationsu1.pdf, p. 104",
   "side_b": "6\" PNEUMATIC PLUG VALVE (TYP OF 10)",
   "side_b_evidence": "17-c-00031plansu1.pdf, p. 10 (sheet 9 keynote 16, quote read from image)",
   "why_it_matters": "Section 15106 is not in the specification book; Addendum 1 Item 3.1 switches to pneumatic actuators supplied by the valve maker, so valve-control interfaces to the grit system are pneumatic.",
   "status": "confirmed"
  },
  {
   "topic": "Performance testing days per trip: spec vs Addendum 1",
   "side_a": "Performance Testing 1 2",
   "side_a_evidence": "17-c-00031specificationsu1.pdf, p. 171",
   "side_b": "revise the number of days/trips for performance testing in the table from “2” to “5”.",
   "side_b_evidence": "17-c-00031add1u1.pdf, p. 4",
   "why_it_matters": "Addendum 1 governs: five days on site for performance testing instead of two, a direct increase in field service cost.",
   "status": "confirmed"
  }
 ]
}