Template · Applications and Proposal Engineers

Specification Compliance Matrix: an Excel template, and 46 switchgear checks to start from

One row for every requirement, one answer beside it. Work through it here or download the Excel file. The rows that are not a plain comply become the clarifications page of your quote.

Download the Excel template
0 of 46 answered0 comply0 comply with clarification0 exception0 not applicable0 ask the engineer
The equipment and its standard
01Which product family is being asked for: switchboard, low voltage switchgear, metal-clad or metal-enclosed. The standards cited settle it.
Where: Summary paragraph, references list, construction paragraph
Seen: Illinois spec: pages 1 and 5 describe fused metal-enclosed switches, then page 15 asks for circuit breaker tests and assembly tests to the metal-clad standard.
02Sentences left over from a template that do not fit this equipment.
Where: Definitions, accessories, tests
Seen: Illinois spec: page 4 asks for a motor driven racking device and page 15 defines a space for a future circuit breaker, in a lineup that has no breakers.
03Named manufacturers, the basis of design, and how an equal will be judged.
Where: Manufacturers paragraph, then the bay or section descriptions
Seen: Illinois spec: page 4 lists four makers; pages 7 to 12 describe every bay in one maker's product names, and page 12 still reads "This quotation includes".
04Domestic content or buy-national rules.
Where: Next to the manufacturers list; front-end contract documents
Seen: Illinois spec, page 4: all products must comply with the Illinois Procurement of Domestic Products Act.
Ratings
05Voltage class, continuous current and impulse level, and that the assembly table matches the breaker table.
Where: Ratings paragraphs for the assembly and for the breakers
Seen: Powerhouse spec, pages 9 and 10: 5 kV, 1,200 A and 60 kV impulse appear in both tables and agree.
06Short-circuit ratings agree with each other. The peak should be 2.6 times the short-time rating.
Where: Ratings paragraphs
Seen: Powerhouse spec: page 9 gives 135 kA momentary beside 25 kA short-time; page 10 gives 65 kA peak, which is 25 times 2.6.
07Withstand voltages belong to the voltage class.
Where: Ratings paragraph
Seen: Powerhouse spec, page 9: a 36 kV power frequency withstand, the value for 15 kV class gear, beside a 5 kV maximum and a 60 kV impulse level.
08A fault level stated in MVA, and which voltage turns it into amps.
Where: Ratings paragraph or system description
Seen: Illinois spec, page 5: 600 MVA with 13.8 kV nominal and 12.47 kV system voltage, which is about 25.1 kA or about 27.8 kA.
09Bus metal, plating, and whether the bus must be density rated or may be sized by heat-rise test.
Where: Bus paragraph
Seen: Powerhouse spec, page 12: hard-drawn copper bus with silver-plated bolted joints.
10Ground bus size and what it has to terminate.
Where: Grounding paragraph
Seen: Powerhouse spec, page 13: not less than 1/4 by 1 inch, with pads for 500 kcmil cable.
Counts
11Number of sections, bays and breakers, taken from the one-line drawing and checked against the text.
Where: One-line diagram, schedules, bay descriptions
Seen: Illinois spec: ten bay headings, numbered 1, 2, 3, 4, 5, 46, 5, 67, 8 and 79.
12Fuse, refill and spare quantities agree with the number of units.
Where: Fuse paragraph, accessories list
Seen: Illinois spec: page 6 asks for six fuses per switch, page 12 for 36 refills, and the bay list names fuses on seven or eight bays.
13Devices required on some units only.
Where: Device paragraphs that name a unit or breaker number
Seen: Powerhouse spec, page 24: a capacitor trip device on breaker 3AG2 only.
14Accessories counted per breaker type, per lineup or per distance.
Where: Accessories paragraph
Seen: Powerhouse spec, page 27: a test cabinet for each breaker type, and another for any lineup more than 200 feet away.
Devices and options
15Who furnishes the protective relays, and what stays with you when someone else does.
Where: Relay paragraph
Seen: Powerhouse spec, page 26: relays furnished by the government. Test switches on every relay signal and a CT burden analysis are still required.
16Meter model, number of current transformers, and communications card.
Where: Metering paragraph and the one-line diagram
Seen: Texas submittal review: returned not approved for a fourth current transformer, the specified higher meter model and an Ethernet card. All three were in the specification at bid time.
17Accuracy class and mounting of current and voltage transformers.
Where: Instrument transformer paragraph
Seen: Powerhouse spec, pages 25 and 26: C50 at 100:5, C200 at 500:5 to 800:5, and voltage transformers in fused rollout trays.
18Infrared windows or sight glasses, and at which connections.
Where: Construction or accessories paragraph
Seen: Powerhouse spec, page 12: at the main, the tie and each feeder, unless the manufacturer can show it is impractical.
19Remote racking and remote operation.
Where: Configuration and accessories paragraphs
Seen: Powerhouse spec, pages 10, 12 and 27: provisions in every cubicle, and a wheeled racking device with a 25 foot pendant.
20Arc resistant construction and energy reduction maintenance switches.
Where: Construction paragraph; the owner's standard
Seen: Metrolinx requires arc resistant switchgear. Dartmouth asks for a maintenance switch above 800 A, where the electrical code threshold is 1,200 A.
21Surge protection: arresters, surge capacitors, surge protective devices.
Where: Surge protection paragraph
Seen: Powerhouse spec, page 26: station-class arresters and 0.5 microfarad surge capacitors.
22Control power source: battery, charger, capacitor trip.
Where: Control power paragraph
Seen: Illinois spec, page 14: a complete battery system under a heading marked "(remove??)".
23What has to report to a network, and by what protocol.
Where: Relay, metering and controls paragraphs
Seen: Illinois spec, pages 5, 6 and 13: addressable relays reporting switch position and blown fuses.
24Automatic transfer scheme and its sequence of operation.
Where: Controls paragraph; sequence of operation
Seen: Illinois spec, pages 7 to 12: the source-transfer control is named as one maker's product, so an equal has to be shown, not assumed.
Enclosure and construction
25Enclosure type, environment, wind and seismic requirements.
Where: Service conditions; enclosure paragraph; a separate seismic section
Seen: Illinois spec, page 6: NEMA 3R galvanized, rated for 150 mph wind. Powerhouse spec, page 10: seismic certification under another section.
26Finish and colour, stated once.
Where: Finish paragraph, and again near the end of the section
Seen: Illinois spec: gray on page 6, olive green on page 16.
27Space heaters, lights and receptacles in each compartment.
Where: Enclosure accessories
Seen: Illinois spec, page 6: a heater, an interior light and a GFCI receptacle in each compartment.
28Nameplates, mimic bus and labels: material, colour, size, language.
Where: Identification paragraph; general notes on the drawings
Seen: Powerhouse spec, page 17: engraved nameplates to a stated size. Illinois spec, page 5: position flags in three languages. Texas review: nameplate colours reversed between two drawings.
29Wiring rules that change labour: terminal blocks, spare terminals, wire markers, routing.
Where: Control wiring paragraph
Seen: Powerhouse spec, pages 14 to 16: 10 percent spare terminals, no push-in blocks, printed marking strips with two sets of wire numbers, CT leads in separate metal conduit.
30Mounting heights for displays and operating handles.
Where: Construction paragraph; accessibility rules
Seen: Texas review of the 4,160 V switchgear: displays drawn at 6 feet 2 inches above the floor against a 5 foot 6 inch maximum.
31Section widths, shipping splits and the route into the building.
Where: Configuration; delivery and handling
Seen: Powerhouse spec, page 7: the lineup must reach its place without being taken apart, along a route nobody has surveyed.
Scope boundary
32Work that belongs to the installer: foundations, field drilling, storage, outages.
Where: Execution part of the section
Seen: Powerhouse spec, pages 16 and 17: cable entry holes drilled in the field, and steel channel foundations.
33Work on existing equipment.
Where: Anywhere the word existing appears
Seen: Powerhouse spec, page 21: a mimic bus on the existing control benchboard, matching what is there, and a breaker at the benchboard for each switchgear breaker.
34Short-circuit, coordination and arc flash studies, and who sets the relays.
Where: A separate studies section; start-up paragraph
Seen: Veterans Affairs: the manufacturer's representative sets relays in the field. Dartmouth: the owner's commissioning agent does. University of Houston: the study is due before the submittal.
35Approvals needed before fabrication can start.
Where: Submittals paragraph; utility requirements
Seen: Illinois spec, pages 2 and 15: the utility approves the metering cubicle before fabrication.
Tests, services, spares and documents
36Factory tests, who witnesses them, and how much notice they need.
Where: Source quality control
Seen: Powerhouse spec, page 29: every test witnessed, with 21 days notice.
37Design tests, if they have not been run on identical equipment.
Where: Tests paragraph
Seen: Powerhouse spec, pages 28 and 29: performed under this contract if no report exists for identical equipment.
38Special tests on instrument transformers and relays.
Where: Tests paragraph
Seen: Powerhouse spec, pages 30 and 31: ratio and phase angle tests on current and voltage transformers.
39Field service: how many visits, and how far apart.
Where: Field quality control; start-up
Seen: Powerhouse spec, page 34: an engineer at both the contractor's and the government's commissioning. Illinois spec, page 18: an infrared scan within 60 days of final acceptance.
40Training: hours, sessions, class size, recording.
Where: Closeout or training paragraph
Seen: Veterans Affairs: one 4 hour session. Powerhouse spec, page 34: a recorded 8 hour class with a breaker teardown, on separate days if asked.
41Spare parts, listed line by line.
Where: Spare parts or maintenance materials
Seen: Powerhouse spec, page 28: one complete spare breaker plus transformers, coils and chargers. Metrolinx: 25 percent spare breakers. Defense template: two fuses of each type.
42Handling and test accessories.
Where: Accessories paragraph
Seen: Powerhouse spec, pages 27 and 28: a handling and testing accessory set.
43Manuals and record drawings: number of copies and format.
Where: Closeout submittals
Seen: Powerhouse spec, page 35: three draft copies and five final copies with discs.
44Submittal contents and deadlines.
Where: Submittals paragraph
Seen: Powerhouse spec, pages 3 to 5: deadlines starting 45 days after notice to proceed.
Commercial and open items
45Where the cost of tests and services is meant to sit.
Where: Front of the section; price schedule
Seen: Powerhouse spec, page 4: the cost of all tests is included in the equipment prices.
46Open items the author left in: TBD, question marks, tracked changes.
Where: Search the whole section
Seen: Illinois spec, page 10: a meter location marked TBD. Its footer calls the section bridging documents, a design left for others to finish.
Your own rows
For the quote: questions, exceptions and clarifications

Nothing here yet. Rows you mark as a clarification, an exception, not applicable, or a question for the engineer collect here, in the order a quote usually gives them.

Your answers are kept in this browser only. Nothing you type here is sent to us.

What a specification compliance matrix is

A specification compliance matrix is a table with one row for every requirement in the customer's specification and your answer beside each. Buyers and manufacturers call it different things: a technical compliance sheet, a technical compliance statement, a spec compliance sheet, a clause by clause compliance statement. It is the same document. Some buyers ask for it with the bid. Even when nobody asks, it is the working paper behind every honest clarifications page.

It exists because a quote is a promise to meet a document somebody else wrote. The matrix is where you find out, before the price goes out, which sentences you can meet as written, which you can meet only if they are read a certain way, and which you cannot meet at all.

How to make a compliance matrix in three passes

  1. List. Go through the specification in page order and give a row to every requirement that could change what you build or what you charge. Copy the sentence as written and note the page.
  2. Answer. Give every row one of five responses. A row with no response is a requirement nobody has read yet.
  3. Write it down. For every row that is not a plain comply, write the sentence you want in the quote. Those rows, in order, are your clarifications and exceptions.

The matrix on this page does the third pass as you go. Mark a row, type the wording, and it appears in the list under the table, sorted the way a quote usually presents it: questions first, then exceptions, then clarifications.

The five responses, and what each one commits you to

  • Comply. You meet the requirement as written, at the price quoted.
  • Comply with clarification. You meet it, read a particular way. The clarification states the reading you priced.
  • Exception. You do not meet it as written, and you say what you offer instead. Some buyers call this a deviation.
  • Not applicable. The sentence does not apply to this equipment, or the work belongs to someone else. Say which.
  • Ask the engineer. The document disagrees with itself or leaves something open. Send the question early, and state what you priced in the meantime.

Compliance matrix example: four rows from a real switchgear specification

These four rows come from one public document, a 35 page specification for a 5 kV metal-clad lineup at a hydroelectric powerhouse. Each one needed a different response.

ReferenceRequirementResponseWording for the quote
26 13 26, page 9Momentary withstand 135 kA. Short-time withstand 25 kA.Ask the engineerPriced at 25 kA short-time and 65 kA peak, per the breaker ratings on page 10. Page 9 lists a 135 kA momentary rating. Please confirm.
Page 26Protective relays will be furnished, installed and tested by the government.Not applicableProtective relays excluded, furnished by the government per page 26. Test switches and the CT burden analysis are included.
Page 12Infrared windows at the main, the tie and each feeder, unless impractical.Comply with clarificationInfrared windows at all main and tie connections, and at feeder connections where the bus design permits.
Page 7Transported and installed within the access constraints of the powerhouse without disassembly.ExceptionShipping sections and weights as listed. The access route has not been surveyed. Disassembly or reassembly on site is not included.

Notice what the first row does. The specification gives two fault ratings on the same page that cannot both be true. A matrix that summarised the requirement as "meet the ratings" would have hidden that. Copying the sentence as written is what makes the conflict visible.

Technical compliance sheet format: the columns that matter

The Excel template uses seven columns besides the row number: the specification reference down to the page or paragraph, the requirement as written, your response, your offer or the wording for the quote, whether the row changes the price, who inside your company answers it, and the evidence you would point to. The response column is a dropdown, the rows colour themselves by response, and a summary sheet counts them, including the rows nobody has answered yet.

The price column earns its place. Sort by it before the quote goes out and you have the short list of rows a manager should read: the ones where your reading of a sentence moved the number.

A deviation list is the same sheet, filtered

If a buyer asks for a deviation list or an exceptions and clarifications page instead of the whole matrix, you do not need a second template. Filter the response column for everything except comply. What is left is the deviation list, already tied to pages and already worded.

Where the 46 switchgear checks come from

Each starter row is a place where a real document changed the price. They come from two switchgear specifications issued for bid, the standard specifications of five large owners, and the published review records of two submittals on one Texas project, one of which came back not approved with 35 numbered comments. Every row names the document and the page where we saw it. The full reading is in how to quote switchgear, and the rejected submittals are in what engineers actually reject.

The list is not complete for any one project, and it is not meant to be. It tells you where requirements of this kind usually sit, so you look there in your own document.

What the template cannot do

A template gives the reading a shape. It does not do the reading. Somebody still has to go through every page, and the rows that cost money are the ones that are easy to pass over: a rating typed twice, a device required on one breaker only, a line an author meant to delete.

Sources. U.S. Army Corps of Engineers, Section 26 13 26.00 26, Metal-Clad Switchgear, Amendment 0002. Illinois Capital Development Board, Quincy Veterans' Home, Section 26 13 00, Amendment 3. Standard specifications of the Department of Veterans Affairs, the Department of Defense, Metrolinx, the University of Houston and Dartmouth College. Published submittal review records for a Texas water district's pump stations. Found a mistake? Write to atishay@mavlon.co and we will fix it.

The template tells you where to look. Mavlon does the reading.

Mavlon reads the customer's specification and drawings and returns what this matrix holds: every requirement that changes the price, tied to its page, the conflicts flagged, and the questions for the customer drafted for your review.

Book a Demo

Shown on a public switchgear specification

Frequently asked questions

What is a compliance matrix in engineering?
A table with one row for every requirement in the customer's specification and your answer beside each: comply, comply with a clarification, exception, not applicable, or a question for the engineer. It is also called a technical compliance sheet, a technical compliance statement or a clause by clause compliance statement. Its job is to show, line by line, what the price does and does not include.
What is the difference between a compliance matrix and a deviation list?
A deviation list is the compliance matrix with the plain comply rows filtered out. The matrix shows every requirement and its answer. The deviation list, or exceptions and clarifications page, shows only the rows where your offer differs from the words in the specification.
What does comply with clarification mean?
You meet the requirement, read a particular way. The clarification states the reading you priced, so that nobody finds out after award that you and the engineer read the sentence differently. For example: infrared windows at all main and tie connections, and at feeder connections where the bus design permits.
What columns does a technical compliance sheet need?
Seven do the work: the specification reference down to the page or paragraph, the requirement copied as written, your response, the wording for the quote, whether it changes the price, who inside your company answers it, and the evidence you would point to, such as a drawing, a data sheet or a test report.
How long should a compliance matrix be?
As long as the number of requirements that change what you build or what you charge. Two public switchgear specifications we read, 54 pages between them, held 55 such requirements. Rows that are a plain comply still belong in the matrix, because they show the requirement was read.
Can I use the template for equipment other than switchgear?
Yes. The Matrix sheet in the Excel file and the blank matrix on this page work for any specification. The 46 starter checks are specific to switchgear and switchboards because they come from switchgear documents.

The newsletter

Field Notes

The numbers that change your next quote. Once a month.

  • 01A material price that shifted this month, with the number.
  • 02What contracts in one segment actually closed for.
  • 03A real bid package taken apart page by page.